2012 -- H 7632 | |
======= | |
LC01485 | |
======= | |
STATE OF RHODE ISLAND | |
| |
IN GENERAL ASSEMBLY | |
| |
JANUARY SESSION, A.D. 2012 | |
| |
____________ | |
| |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS - DUTIES OF UTILITIES AND | |
CARRIERS | |
|
      |
|
      |
     Introduced By: Representatives Hull, O`Neill, San Bento, Lally, and Slater | |
     Date Introduced: February 16, 2012 | |
     Referred To: House Corporations | |
It is enacted by the General Assembly as follows: | |
1-1 |
     SECTION 1. Chapter 39-2 of the General Laws entitled "Duties of Utilities and Carriers" |
1-2 |
is hereby amended by adding thereto the following section: |
1-3 |
     39-2-25. Reliable and high quality utility service. – (a) Every electric transmission |
1-4 |
company and electric distribution company as defined in section 39-1-2 shall promulgate and |
1-5 |
implement written guidelines and procedures for periodic inspection of each category of its |
1-6 |
equipment. Electric transmission and distribution companies shall establish inspection |
1-7 |
procedures for at least the following categories of equipment: meters, transformers, switching |
1-8 |
and protective devices, regulators and capacitors, overhead and underground cables and |
1-9 |
conductors, and wooden and other poles which carry cables, electrical conductors and apparatus. |
1-10 |
     (b) Every electric distribution and electric transmission company shall provide the public |
1-11 |
utilities division with a periodic summary report on the status of each category of equipment |
1-12 |
inspected. The division shall have the authority to require such additional inspections or surveys |
1-13 |
as it deems appropriate, and to review and approve the inspection plans of transmission and |
1-14 |
distribution companies. The public utilities division shall adopt final regulations regarding |
1-15 |
adoption and implementation of periodic inspection and maintenance programs by transmission |
1-16 |
and distribution companies including, but not limited to, inspection standards for the equipment |
1-17 |
categories listed in subsection (a), no later than one hundred eighty (180) days after enactment of |
1-18 |
this section. |
2-19 |
     (c) No later than one year after enactment of this section, the public utilities division shall |
2-20 |
complete a report on rates of outages, and service disruptions experienced by customers of |
2-21 |
transmission and distribution companies. The report shall identify those communities or areas |
2-22 |
within any company’s territory that suffer above average rates of outages and service disruptions, |
2-23 |
and shall include comparisons of the rates among the several companies. For purposes of this |
2-24 |
section, “community or area” means an area no greater than the size of a United States postal |
2-25 |
zone. |
2-26 |
     SECTION 2. This act shall take effect upon passage. |
      | |
======= | |
LC01485 | |
======= | |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS - DUTIES OF UTILITIES AND | |
CARRIERS | |
*** | |
3-1 |
     This act would require electric transmission and electric distribution companies to |
3-2 |
conduct periodic equipment inspections. Such companies would also be required to submit a |
3-3 |
periodic report to the public utilities division regarding the status of such inspections. |
3-4 |
     This act would take effect upon passage. |
      | |
======= | |
LC01485 | |
======= |