It is enacted by the General Assembly as follows: | |
1-1 |
     SECTION 1. Section 39-1-27.7 of the General Laws in Chapter 39-1 entitled "Public |
1-2 |
Utilities Commission" is hereby amended to read as follows: |
1-3 |
     39-1-27.7. System reliability and least-cost procurement. -- Least-cost procurement |
1-4 |
shall comprise system reliability and energy efficiency and conservation procurement as provided |
1-5 |
for in this section and supply procurement as provided for in section 39-1-27.8, as complementary |
1-6 |
but distinct activities that have as common purpose meeting electrical and natural gas energy |
1-7 |
needs in Rhode Island, in a manner that is optimally cost-effective, reliable, prudent and |
1-8 |
environmentally responsible. |
1-9 |
      (a) The commission shall establish not later than June 1, 2008, standards for system |
1-10 |
reliability and energy efficiency and conservation procurement, which shall include standards and |
1-11 |
guidelines for: |
1-12 |
      (1) System reliability procurement, including but not limited to: |
1-13 |
      (i) Procurement of energy supply from diverse sources, including, but not limited to, |
1-14 |
renewable energy resources as defined in chapter 26 of this title; |
1-15 |
      (ii) Distributed generation, including, but not limited to, renewable energy resources and |
1-16 |
thermally leading combined heat and power systems, which is reliable and is cost-effective, with |
1-17 |
measurable, net system benefits; |
1-18 |
      (iii) Demand response, including, but not limited to, distributed generation, back-up |
1-19 |
generation and on-demand usage reduction, which shall be designed to facilitate electric customer |
1-20 |
participation in regional demand response programs, including those administered by the |
2-1 |
independent service operator of New England ("ISO-NE") and/or are designed to provide local |
2-2 |
system reliability benefits through load control or using on-site generating capability; |
2-3 |
      (iv) To effectuate the purposes of this division, the commission may establish standards |
2-4 |
and/or rates (A) for qualifying distributed generation, demand response, and renewable energy |
2-5 |
resources; (B) for net-metering; (C) for back-up power and/or standby rates that reasonably |
2-6 |
facilitate the development of distributed generation; and (D) for such other matters as the |
2-7 |
commission may find necessary or appropriate. |
2-8 |
      (2) Least-cost procurement, which shall include procurement of energy efficiency and |
2-9 |
energy conservation measures that are prudent and reliable and when such measures are lower |
2-10 |
cost than acquisition of additional supply, including supply for periods of high demand. |
2-11 |
      (b) The standards and guidelines provided for by subsection (a) shall be subject to |
2-12 |
periodic review and as appropriate amendment by the commission, which review will be |
2-13 |
conducted not less frequently than every three (3) years after the adoption of the standards and |
2-14 |
guidelines. |
2-15 |
      (c) To implement the provisions of this section: |
2-16 |
      (1) The commissioner of the office of energy resources and the energy efficiency and |
2-17 |
resources management council, either or jointly or separately, shall provide the commission |
2-18 |
findings and recommendations with regard to system reliability and energy efficiency and |
2-19 |
conservation procurement on or before March 1, 2008, and triennially on or before March 1, |
2-20 |
thereafter through March 1, 2017. |
2-21 |
      (2) The commission shall issue standards not later than June 1, 2008, with regard to |
2-22 |
plans for system reliability and energy efficiency and conservation procurement, which standards |
2-23 |
may be amended or revised by the commission as necessary and/or appropriate. |
2-24 |
      (3) The energy efficiency and resources management council shall prepare by July 15, |
2-25 |
2008, a reliability and efficiency procurement opportunity report which shall identify |
2-26 |
opportunities to procure efficiency, distributed generation, demand response and renewables, |
2-27 |
which report shall be submitted to the electrical distribution company, the commission, the office |
2-28 |
of energy resources and the joint committee on energy. |
2-29 |
      (4) Each electrical and natural gas distribution company shall submit to the commission |
2-30 |
on or before September 1, 2008, and triennially on or before September 1, thereafter through |
2-31 |
September 1, 2017, a plan for system reliability and energy efficiency and conservation |
2-32 |
procurement. In developing the plan, the distribution company may seek the advice of the |
2-33 |
commissioner and the council. The plan shall include measurable goals and target percentages for |
2-34 |
each energy resource, pursuant to standards established by the commission, including efficiency, |
3-1 |
distributed generation, demand response, combined heat and power, and renewables. |
3-2 |
      (5) The commission shall issue an order approving all energy efficiency measures that |
3-3 |
are cost effective and lower cost than acquisition of additional supply, with regard to the plan |
3-4 |
from the electrical and natural gas distribution company, and reviewed and approved by the |
3-5 |
energy efficiency and resources management council, and any related annual plans, and shall |
3-6 |
approve a fully reconciling funding mechanism to fund investments in all efficiency measures |
3-7 |
that are cost effective and lower cost than acquisition of additional supply, not greater than sixty |
3-8 |
(60) days after it is filed with the commission. |
3-9 |
      (6) Each electrical and natural gas distribution company shall provide a status report, |
3-10 |
which shall be public, on the implementation of least cost procurement on or before December |
3-11 |
15, 2008, and on or before February 1, 2009, to the commission, the division, the commissioner |
3-12 |
of the office of energy resources and the energy efficiency and resources management council |
3-13 |
which may provide the distribution company recommendations with regard to effective |
3-14 |
implementation of least cost procurement. The report shall include the targets for each energy |
3-15 |
resource included in the order approving the plan and the achieved percentage for energy |
3-16 |
resource, including the achieved percentages for efficiency, distributed generation, demand |
3-17 |
response, combined heat and power, and renewables. |
3-18 |
      (i) Beginning on or before January 1, 2013 each electric distribution company shall, to |
3-19 |
the extent eligible projects are available and conforming applications are submitted, fund |
3-20 |
investments in at least twenty megawatts (20 MW) of combined heat and power installations at |
3-21 |
commercial, institutional or industrial facilities. The distribution company and commission shall |
3-22 |
allocate at least fifteen percent (15%) of the demand side management funds collected pursuant to |
3-23 |
section 39-2-1.2 to fund combined heat and power installations. Such investments shall be made |
3-24 |
to achieve the energy efficient targets established in the triennial plan for system reliability and |
3-25 |
energy efficiency and conservation procurement, and shall be included in the distribution |
3-26 |
company’s 2013 energy efficiency program plan submitted to the commission. In order to |
3-27 |
effectuate this provision, the commission shall amend or revise as necessary the standards |
3-28 |
adopted pursuant to subdivision (c)(2) of this section no later than September 1, 2012. |
3-29 |
      (d) If the commission shall determine that the implementation of system reliability and |
3-30 |
energy efficiency and conservation procurement has caused or is likely to cause under or over- |
3-31 |
recovery of overhead and fixed costs of the company implementing said procurement, the |
3-32 |
commission may establish a mandatory rate adjustment clause for the company so affected in |
3-33 |
order to provide for full recovery of reasonable and prudent overhead and fixed costs. |
4-34 |
      (e) The commission shall conduct a contested case proceeding to establish a performance |
4-35 |
based incentive plan which allows for additional compensation for each electric distribution |
4-36 |
company and each company providing gas to end-users and/or retail customers based on the level |
4-37 |
of its success in mitigating the cost and variability of electric and gas services through |
4-38 |
procurement portfolios. |
4-39 |
     SECTION 2. This act shall take effect upon passage. |
      | |
======= | |
LC02253 | |
======== | |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS - PUBLIC UTILITIES COMMISSION | |
*** | |
5-1 |
     This act would require all electrical distribution companies to fund a percentage of the |
5-2 |
investments in twenty megawatts (20 MW) combined heat and power facilities, in order to |
5-3 |
achieve the energy efficiency targets, and would require the public utilities commission to amend |
5-4 |
or revise its standards accordingly. |
5-5 |
     This act would take effect upon passage. |
      | |
======= | |
LC02253 | |
======= |