2013 -- S 0294 | |
======= | |
LC00849 | |
======= | |
STATE OF RHODE ISLAND | |
| |
IN GENERAL ASSEMBLY | |
| |
JANUARY SESSION, A.D. 2013 | |
| |
____________ | |
| |
A N A C T | |
RELATING TO PUBLIC PROPERTY AND WORKS -- LABOR AND PAYMENT OF DEBT | |
BY CONTRACTORS | |
|
      |
|
      |
     Introduced By: Senators DiPalma, Sosnowski, Pearson, Lombardi, and Ciccone | |
     Date Introduced: February 12, 2013 | |
     Referred To: Senate Labor | |
It is enacted by the General Assembly as follows: | |
1-1 |
     SECTION 1. Section 37-13-4 of the General Laws in Chapter 37-13 entitled "Labor and |
1-2 |
Payment of Debts by Contractors" is hereby amended to read as follows: |
1-3 |
     37-13-4. Provisions applicable to public works contracts -- Lists of subcontractors. -- |
1-4 |
All public works shall be done by contract, subject to the same provisions of law relating thereto |
1-5 |
and to the letting thereof, which are applicable to similar contracts of the awarding authority or |
1-6 |
authorized agency, hereinafter called the "proper authority", in the general location where the |
1-7 |
work is to be performed and which are not contrary to the provisions of sections 37-13-1 -- 37- |
1-8 |
13-14 and section 37-13-16. Each |
1-9 |
award |
1-10 |
potential subcontractors of any part or all of the work. The list shall be submitted in such manner |
1-11 |
or form as the proper authority shall uniformly require from |
1-12 |
works. In the event that said bidder chooses to contract with a subcontractor that was not on the |
1-13 |
list provided to the proper authority then, prior to contracting with the subcontractor, the bidder |
1-14 |
shall provide the name of the subcontractor to the proper authority at least seven (7) days prior to |
1-15 |
contracting with said contractor. |
1-16 |
     SECTION 2. This act shall take effect upon passage. |
      | |
======= | |
LC00849 | |
======= | |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO PUBLIC PROPERTY AND WORKS -- LABOR AND PAYMENT OF DEBT | |
BY CONTRACTORS | |
*** | |
2-1 |
     This act would require that bidders provide a list of subcontractors prior to an award of a |
2-2 |
contract for public works. |
2-3 |
     This act would take effect upon passage. |
      | |
======= | |