2013 -- S 0758

=======

LC02055

=======

STATE OF RHODE ISLAND

IN GENERAL ASSEMBLY

JANUARY SESSION, A.D. 2013

____________

A N A C T

RELATING TO AN ACT AUTHORIZING THE TOWN OF NEW SHOREHAM TO PLAN,

CONSTRUCT, OPERATE, AND MAINTAIN A SEWAGE DISPOSAL SYSTEM AND

AUTHORIZING THE FINANCING THEREOF INCLUDING THE ISSUE OF NOT MORE

THAN $1,750,000 BONDS THEREOF

     

     

     Introduced By: Senator V. Susan Sosnowski

     Date Introduced: March 13, 2013

     Referred To: Senate Housing & Municipal Government

It is enacted by the General Assembly as follows:

1-1

     SECTION 1. The town of New Shoreham is hereby authorized to plan, Sewage disposal

1-2

construct, operate, maintain, extend and improve a sewage disposal system for the town or any

1-3

part or parts thereof. Such system may include facilities for collecting, treating and disposal of

1-4

sewage and commercial and industrial wastes. The town of New Shoreham, acting by its town

1-5

council, may enter into agreements for periods with the state or any other municipal or quasi-

1-6

municipal corporation or any private party for the treatment or disposition by one party of sewage

1-7

and wastes collected by the other and the state, such other municipal or quasi-municipal

1-8

corporations and private parties are authorized to enter into such agreements with the town. Such

1-9

agreements may be for a period of years or of permanent duration and may provide for the

1-10

arbitration of disputes arising thereunder.

1-11

     SECTION 2. There is hereby established a board of sewer commissioners for the town of

1-12

New Shoreham consisting of five qualified electors of the town. Except as otherwise provided

1-13

herein, said board of sewer commissioners shall have power and authority to supervise the

1-14

planning, construction, operation, maintenance, extension and improvement of the sewage

1-15

disposal system and to make contracts therefor on behalf of the town.

1-16

     Forthwith after the effective date of this section, the town council, shall appoint five

1-17

sewer commissioners, one to serve until May 1, 1973, one until May 1, 1974, one to serve until

1-18

May 1, 1975, one to serve until May 1, 1976, and one until May 1, 1977, and thereafter until

2-1

their successors are appointed and take office. Not more than sixty days prior to the expiration of

2-2

each term the town council shall appoint a successor for a term of five years from such expiration

2-3

and thereafter until his successor is appointed and takes office.

2-4

     The board of sewer commissioners may act despite a vacancy on the board but, in the

2-5

event of any vacancy the town council shall appoint a commissioner to serve for the unexpired

2-6

term and thereafter until his successor is appointed and takes office.

2-7

     Any member of the board may be removed for cause by the town council.

2-8

     Each appointment or removal by the town council shall be by vote of a majority of the

2-9

whole number thereof, including vacancies therein.

2-10

     The town council may require the members of the board of sewer commissioners to

2-11

furnish bond for the faithful performance of their duties, in such amounts and with such sureties

2-12

as the town council may deem desirable. Premiums on surety bonds shall be paid from funds of

2-13

the board of sewer commissioners.

2-14

     No contract shall be made by the board of sewer commissioners with any member of the

2-15

board or with the superintendent of the sewer system (except his contract of employment) or with

2-16

any member of their immediate families or with any firm or corporation in which the

2-17

superintendent or any member of the board, together in either case with the members of his

2-18

immediate family, owns more than one per cent of the total proprietary interest, unless such direct

2-19

or indirect interest of the member or superintendent is set forth in the minutes of a meeting of the

2-20

board prior to the making of such contract and the member or superintendent abstains from voting

2-21

or acting for the district, as the case may be, in making such contract. A violation of this

2-22

paragraph shall be grounds for avoiding, rescinding or canceling the contract on such terms as the

2-23

interests of the town and innocent third parties may require or for the recovery of damages from

2-24

any party acting in violation of the paragraph.

2-25

     SECTION 3. Forthwith after the appointment of the original board of sewer

2-26

commissioners and after the appointment and taking office of a member upon the expiration of a

2-27

term, the board shall appoint a chairman from among the members of the board and shall appoint

2-28

a secretary, who need not be a member of the board, or designate the town clerk as a secretary.

2-29

The chairperson shall preside at meetings of the board and the secretary shall keep the records of

2-30

the meetings of the board. The board may designate other officers and assistant officers with such

2-31

powers and for such terms as the board may determine but the board may at any time remove any

2-32

such other officers and assistant officers with or without cause, subject to any damages which

2-33

may be payable for cancellation of a contract with the superintendent as authorized below.

3-34

     The board may adopt by-laws or rules for the transaction of its affairs.

3-35

     SECTION 4. The board of sewer commissioners may employ and fix the compensation

3-36

of attorneys, engineers, surveyors, draftsmen, clerks and other employees and agents. The board

3-37

may appoint a superintendent of the sewage disposal system and contract for his services but no

3-38

such contract shall be for a term of more than five years. The board may require a surety bond of

3-39

any of its agents and employees. The premiums shall be paid from funds of the board.

3-40

     Each of the commissioners may be compensated for his services at the rate to be

3-41

determined by the town council. The secretary, if not a member of the board or the town clerk

3-42

acting by designation, may be compensated at a rate determined by the board.

3-43

     SECTION 5. Section 5. Any contract of the board involving more than $1,000 for

3-44

construction or for the purchase of materials or equipment shall be publicly advertised.

3-45

     Section 5. Any contract of the board involving more than ten thousand dollars

3-46

($10,000,000) for construction or five thousand dollars ($5,000) for the purchase of materials or

3-47

equipment shall be publicly advertised pursuant to 45-55-9.

3-48

     All funds of the board shall be held in the custody of the town treasurer and shall be

3-49

expended by or under the direction of the board.

3-50

     In addition to the funds hereinafter provided, the board is authorized to expend for the

3-51

purposes of this act such sums as may be appropriated therefor by the town.

3-52

     In carrying out the purposes of this act, the board of sewer commissioners may lease

3-53

property or acquire the same by purchase or gift or by eminent domain as hereinafter provided,

3-54

may make contracts and shall have such further powers as shall be necessary or incidental to the

3-55

purposes and powers set forth in this act. Any lease, purchase or taking of real property shall be

3-56

subject to authorization or approval of the town council.

3-57

     SECTION 6. The initial cost of any project or projects for the construction, completion,

3-58

extension, enlargement or improvement of the sewage disposal system may be shared between

3-59

the abutting property owners and all the taxpayers of the town of New Shoreham in the following

3-60

manner. The board of sewer commissioners shall, to the extent described below assess the cost of

3-61

any project or projects for the construction, completion, extension, enlargement or improvement

3-62

of the sewage disposal system upon the owners of the estates which abut that portion of any street

3-63

or highway in or along which any sewer constituting any portion of such project or projects may

3-64

be located or which otherwise specially benefit from such project or projects. Such assessment

3-65

may be made separately for each project or for several projects taken together as the board of

3-66

sewer commissioners may deem equitable.

4-67

     SECTION 1. This act shall take effect upon passage.

     

=======

LC02055

=======

EXPLANATION

BY THE LEGISLATIVE COUNCIL

OF

A N A C T

RELATING TO AN ACT AUTHORIZING THE TOWN OF NEW SHOREHAM TO PLAN,

CONSTRUCT, OPERATE, AND MAINTAIN A SEWAGE DISPOSAL SYSTEM AND

AUTHORIZING THE FINANCING THEREOF INCLUDING THE ISSUE OF NOT MORE

THAN $1,750,000 BONDS THEREOF

***

5-1

     This act would mandate the board of sewer commissioners for the town of New

5-2

Shoreham to publically advertise any contract involving more than ten thousand dollars ($10,000)

5-3

for construction or five thousand dollars ($5,000) for the purchase of materials.

5-4

     This act would take effect upon passage.

     

=======

LC02055

=======

S0758