2016 -- H 7549 | |
======== | |
LC004581 | |
======== | |
STATE OF RHODE ISLAND | |
IN GENERAL ASSEMBLY | |
JANUARY SESSION, A.D. 2016 | |
____________ | |
A N A C T | |
RELATING TO PUBLIC PROPERTY AND WORKS | |
| |
Introduced By: Representatives Shekarchi, and Casey | |
Date Introduced: February 10, 2016 | |
Referred To: House Finance | |
It is enacted by the General Assembly as follows: | |
1 | SECTION 1. Title 37 of the General Laws entitled "PUBLIC PROPERTY AND |
2 | WORKS" is hereby amended by adding thereto the following chapter: |
3 | CHAPTER 25 |
4 | PAYMENTS TO CONTRACTORS AND SUBCONTRACTORS |
5 | 37-25-1. Applications for payment. -- (a) A contractor shall, once in each month on the |
6 | day of the month corresponding to the day specified in the contractor agreement, on forms |
7 | provided and in the manner prescribed by the awarding authority, submit to the awarding |
8 | authority a statement showing the total amount of work done from the time of the estimate and |
9 | the value thereof as approved by the resident engineer and the designer. It shall be the |
10 | responsibility of the contractor to deliver, or cause to be delivered, to the resident engineer said |
11 | periodic estimate in proper form and approved as provided above. All periodic estimates shall |
12 | contain such certifications and other evidence supporting the contractor's right to payment as the |
13 | awarding authority may require, including without limitation, lien waivers, on forms as the |
14 | awarding authority may require. If there is no resident engineer assigned to the contract, the |
15 | designer shall act in lieu thereof. If there is neither a resident engineer, nor a designer, the |
16 | awarding authority shall designate a person at the office of the awarding authority. The contractor |
17 | shall include in the periodic estimate only materials incorporated in the work, except as may |
18 | otherwise be provided in herein. The awarding authority shall retain five percent (5%) of such |
19 | estimated value as security for the completion of the work and shall pay to the contractor while |
| |
1 | carrying on the work the balance not retained, subject to the approval of the awarding authority |
2 | and after deducting therefrom all previous payments and all sums to be kept under the provisions |
3 | of the contract. |
4 | (b) Each periodic estimate shall constitute the contractor's representation that: |
5 | (1) The payment requested to be disbursed has been incurred by the contractor on account |
6 | of the work and is justly due to subcontractors or, to the contractor in the case of other work |
7 | performed by the contractor on account thereof; |
8 | (2) The materials, supplies and equipment for which application for payment is being |
9 | submitted have been installed or incorporated into the work or have been stored at the site or at |
10 | such off-site storage locations as the awarding authority shall have approved; |
11 | (3) The materials, supplies and equipment are insured in accordance with the provisions |
12 | of the contract; |
13 | (4) The materials, supplies and equipment are owned by the owner and are not subject to |
14 | any liens or encumbrances; |
15 | (5) The work which is the subject of the periodic estimate has been performed in |
16 | accordance with the contract; and |
17 | (6) That all due and payable bills with respect to the work have been paid to date or shall |
18 | be paid from the proceeds of the periodic estimate. |
19 | (c) The contractor may include in a periodic estimate the value of materials or equipment |
20 | delivered at the site (or at some other location agreed to in writing) only upon delivery to the |
21 | awarding authority of: |
22 | (1) An acceptable transfer of title on a form provided by the awarding authority; |
23 | (2) Written certification by the contractor (or applicable subcontractor) on a form |
24 | provided by the awarding authority that the contractor (or the subcontractor) is the lawful owner |
25 | and that the materials or equipment are free from all encumbrances, accompanied by invoices or |
26 | other acceptable proof of prior payment for such materials; |
27 | (3) A stored materials insurance binder that covers the materials for which payment is |
28 | requested that names the owner as an insured party should the stored materials be subjected to |
29 | any casualty, loss or theft prior to their inclusion in the work. The material(s) or equipment must, |
30 | in the judgment of the designer: |
31 | (i) Meet the requirements of the contract, including prior shop drawing, product data, and |
32 | sample approval; |
33 | (ii) Be ready for use; and |
34 | (iii) Be properly stored by the contractor and be adequately protected until incorporated |
| LC004581 - Page 2 of 10 |
1 | into the work. |
2 | (d) The awarding authority may make changes in any periodic estimate submitted by the |
3 | contractor and the payment due shall be computed in accordance with the changes made. The |
4 | provisions of the general laws shall govern payments on which the awarding authority has made |
5 | changes. |
6 | (e) No certificate for payment and no progress payment shall constitute acceptance of |
7 | work that is not in accordance with the contract documents. |
8 | (f) The contractor and all subcontractors furnishing labor on this contract agree to furnish |
9 | certified payroll reports if requested to do so, at no additional expense to the awarding authority. |
10 | The awarding authority may at all reasonable times audit such reports. |
11 | 37-25-2. Periodic payments. – (a) The awarding authority shall make payment to the |
12 | contractor in accordance with existing law. Within fifteen (15) days (thirty (30) days in the case |
13 | of the state, including local housing authorities) after receipt from the contractor, at the place |
14 | designated by the awarding authority if such a place is so designated, of a periodic estimate |
15 | requesting payment of the amount due for the preceding month, the awarding authority shall |
16 | make a periodic payment to the contractor for the work performed during the preceding month |
17 | and for the materials not incorporated in the work but delivered and suitably stored at the site or |
18 | at some location agreed upon in writing to which the contractor has title or to which a |
19 | subcontractor has title and has authorized the contractor to transfer title to the awarding authority |
20 | upon certification by the contractor that they are the lawful owner and that the materials are free |
21 | from all encumbrances, but less: |
22 | (1) A retention based on its estimate of the fair value of its claims against the contractor; |
23 | less |
24 | (2) A retention for direct payments to subcontractors based on demands for same; and |
25 | less |
26 | (3) A retention not exceeding five percent (5%) of the approved amount of the periodic |
27 | payment. |
28 | (b) After the receipt of a periodic estimate requesting final payment and within sixty-five |
29 | (65) days after: |
30 | (1) The contractor fully completes the work or substantially completes the work so that |
31 | the value of the work remaining to be done is, in the estimate of the awarding authority, less than |
32 | one percent (1%) of the original contract price; or |
33 | (2) The contractor substantially completes the work and the awarding authority takes |
34 | possession for occupancy, whichever occurs first, the awarding authority shall pay the contractor |
| LC004581 - Page 3 of 10 |
1 | the entire balance due on the contract less: |
2 | (i) A retention based on its estimate of the fair value of its claims against the contractor |
3 | and of the cost of completing the incomplete and unsatisfactory items of work; and less |
4 | (ii) A retention for direct payments to subcontractors based on demands for same, or |
5 | based on the record of payments by the contractor to the subcontractors under this contract if such |
6 | record of payment indicates that the contractor has not paid subcontractors. If the awarding |
7 | authority fails to make payment as herein provided, there shall be added to each payment daily |
8 | interest at the rate of three (3) percentage points above the discount rate then charged by the |
9 | Federal Reserve Bank of Boston commencing on the first day after payment is due and |
10 | continuing until the payment is delivered or mailed to the contractor; provided, that no interest |
11 | shall be due, in any event, on the amount due on a periodic estimate for final payment until fifteen |
12 | (15) days (twenty-four (24) days in the case of the state) after receipt of such periodic estimate |
13 | from the contractor, at the place designated by the awarding authority if such a place is so |
14 | designated. The contractor agrees to pay to each subcontractor a portion of any interest paid in |
15 | accordance with the amount due each subcontractor. |
16 | (c) The awarding authority may make changes in any periodic estimate submitted by the |
17 | contractor and the payment due on said periodic estimate shall be computed in accordance with |
18 | the change so made, but such changes or any requirement for a corrected periodic estimate shall |
19 | not affect the due date for the periodic payment or the date for the commencement of interest |
20 | charges on the amount of the periodic payment computed in accordance with the changes made, |
21 | as provided herein; provided, that the awarding authority may, within seven (7) days after receipt, |
22 | return to the contractor for correction, any periodic estimate which is not in the required form or |
23 | which contains computations not arithmetically correct and, in that event, the date of receipt of |
24 | such periodic estimate shall be the date of receipt of the corrected periodic estimate in proper |
25 | form and with arithmetically correct computations. The date of receipt of a periodic estimate |
26 | received on a Saturday shall be the first working day thereafter. These provisions shall not apply |
27 | to any contract for the construction, reconstruction, alteration, remodeling, repair or demolition of |
28 | any public building to which this section applies. |
29 | (d) All periodic estimates shall be submitted to the awarding authority, or to its designee |
30 | as set forth in writing to the contractor, and the date of receipt by the awarding authority or its |
31 | designee shall be marked on the estimate. All periodic estimates shall contain a separate item for |
32 | each filed subtrade and each sub-subtrade listed in sub-bid form as required by specifications and |
33 | column listing the amount paid to each filed subcontractor as of the date of the periodic estimate |
34 | is filed. The person making payment for the awarding authority shall add the daily interest |
| LC004581 - Page 4 of 10 |
1 | provided for herein to each payment for each day beyond the due date of receipt marked on the |
2 | estimate. A certificate of the architect to the effect that the contractor has fully or substantially |
3 | completed the work shall be conclusive for the purposes of this section. Notwithstanding the |
4 | provisions of this section, at any time after the value of the work remaining to be done is, in the |
5 | estimation of the awarding authority, less than one percent (1%) of the adjusted contract price, or |
6 | the awarding authority has determined that the contractor has substantially completed the work |
7 | and the awarding authority has taken possession for occupancy, the awarding authority may send |
8 | to the general contractor by certified mail, return receipt requested, a complete and final list of all |
9 | incomplete and unsatisfactory work items, including, for each item on the list, a good faith |
10 | estimate of the fair and reasonable cost of completing such item. The general contractor shall then |
11 | complete all such work items within thirty (30) days of receipt of the list or before the contract |
12 | completion date, whichever is later. If the general contractor fails to complete all incomplete and |
13 | unsatisfactory work items within forty-five (45) days after receipt of such items furnished by the |
14 | awarding authority or before the contract completion date, whichever is later, subsequent to an |
15 | additional fourteen (14) days' written notice to the general contractor by certified mail, return |
16 | receipt requested, the awarding authority may terminate the contract and complete the incomplete |
17 | and unsatisfactory work items and charge the cost of same to the general contractor and such |
18 | termination shall be without prejudice to any other rights or remedies the awarding authority may |
19 | have under the contract. The awarding authority shall note any termination in the evaluation form |
20 | to be filed by the awarding authority. |
21 | 37-25-3. Payment of subcontractors. -- (a) Within five (5) business days after a general |
22 | contractor receives payment on account of a periodic estimate, the general contractor shall pay to |
23 | each subcontractor the amount paid for the labor performed and the materials furnished by that |
24 | subcontractor, less any amount specified in any court proceedings barring such payment and also |
25 | less any amount claimed due from the subcontractor by the general contractor. |
26 | (b) Not later than sixty-five (65) days after each subcontractor substantially completes |
27 | their work in accordance with the plans and specifications, the entire balance due under the |
28 | subcontract less amounts retained by the awarding authority as the estimated cost of completing |
29 | the incomplete and unsatisfactory items of work, shall be due the subcontractor; and the awarding |
30 | authority shall pay that amount to the general contractor. The general contractor shall, within five |
31 | (5) business days, pay to the subcontractor the full amount received from the awarding authority |
32 | less any amount as may be specified in any court proceedings barring such payment and also less |
33 | any amount claimed due from the subcontractor by the general contractor. |
34 | (c) Each payment made by the awarding authority to the general contractor for the labor |
| LC004581 - Page 5 of 10 |
1 | performed and the materials furnished by a subcontractor shall be made to the general contractor |
2 | for the account of that subcontractor, and the awarding authority shall take reasonable steps to |
3 | compel the general contractor to make each such payment to each such subcontractor. If the |
4 | awarding authority has received a demand for direct payment from a subcontractor for any |
5 | amount which has already been included in a payment to the general contractor or which is to be |
6 | included in a payment to the general contractor for payment to the subcontractor, the awarding |
7 | authority shall act upon the demand as provided in this section. |
8 | (d) If, within seventy (70) days after the subcontractor has substantially completed the |
9 | subcontract work, the subcontractor has not received from the general contractor the balance due |
10 | under the subcontract including any amount due for extra labor and materials furnished to the |
11 | general contractor, less any amount retained by the awarding authority as the estimated cost of |
12 | completing the incomplete and unsatisfactory items of work, the subcontractor may demand |
13 | direct payment of that balance from the awarding authority. The demand shall be by a sworn |
14 | statement delivered to or sent by certified mail to the awarding authority, and a copy shall be |
15 | delivered to or sent by certified mail to the general contractor at the same time. The reply shall |
16 | contain a detailed breakdown of the balance due under the subcontract and also a statement of the |
17 | status of completion of the subcontract work. Any demand made after substantial completion of |
18 | the subcontract work shall be valid even if delivered or mailed prior to seventy (70) days after the |
19 | subcontractor has substantially completed the subcontract work. Within ten (10) days after the |
20 | subcontractor has delivered or so mailed the demand to the awarding authority and delivered or |
21 | so mailed a copy to the general contractor, the general contractor shall reply to the demand. The |
22 | reply shall be by a sworn statement to or sent by certified mail to the awarding authority and a |
23 | copy shall be delivered to or sent by certified mail to the subcontractor at the same time. The |
24 | reply shall contain a detailed breakdown of the balance due under the subcontract including any |
25 | amount due for extra labor and materials furnished to the general contractor and of the amount |
26 | due for each claim made by the general contractor against the subcontractor. |
27 | (e) Within fifteen (15) days after receipt of the demand by the awarding authority, but in |
28 | no event prior to seventy (70) days after substantial completion of the subcontract work, the |
29 | awarding authority shall make direct payment to the subcontractor of the balance due under the |
30 | subcontract including any amount due for extra labor and materials furnished to the general |
31 | contractor, less any amount: |
32 | (1) Retained by the awarding authority as the estimated cost of completing the |
33 | incomplete or unsatisfactory items of work; |
34 | (2) Specified in any court proceedings barring such payment; or |
| LC004581 - Page 6 of 10 |
1 | (3) Disputed by the general contractor in the sworn reply; provided that the awarding |
2 | authority shall not deduct from a direct payment any amount if the reply is not sworn to, or for |
3 | which the sworn reply does not contain the detailed breakdown required. The awarding authority |
4 | shall make further direct payments to the subcontractor after the removal of the basis for |
5 | deduction from direct payments within five (5) business days. |
6 | (f) The awarding authority shall forthwith deposit the amount deducted from a direct |
7 | payment in an interest-bearing joint account in the names of the general contractor and the |
8 | subcontractor in a bank in Rhode Island selected by the awarding authority or agreed upon by the |
9 | general contractor and the subcontractor, and shall notify the general contractor and the |
10 | subcontractor of the date of the deposit and the bank receiving the deposit. The bank shall pay the |
11 | amount in the account, including accrued interest, as provided in an agreement between the |
12 | general contractor and the subcontractor or as determined by decree of a court of competent |
13 | jurisdiction. |
14 | (g) All direct payments and all deductions from demands for direct payments deposited in |
15 | an interest-bearing account or accounts in a bank shall be made out of amounts payable to the |
16 | general contractor at the time of receipt of a demand for direct payment from a subcontractor and |
17 | out of amounts which later become payable to the general contractor and in the order of receipt of |
18 | such demands from subcontractors. All direct payments shall discharge the obligation of the |
19 | awarding authority to the general contractor to the extent of such payment. |
20 | (h) The awarding authority shall deduct from payments to a general contractor amounts |
21 | which, together with the deposits in interest-bearing accounts, are sufficient to satisfy all unpaid |
22 | balances of demands for direct payment received from subcontractors. All such amounts shall be |
23 | earmarked for direct payments, and the subcontractors shall have a right to such deductions prior |
24 | to any claims against such amounts by creditors of the general contractor. |
25 | (i) If the subcontractor does not receive payment or if the general contractor does not |
26 | submit a periodic estimate for the value of the labor or materials performed or furnished by the |
27 | subcontractor and the subcontractor does not receive payment for same when due less the |
28 | deductions, the subcontractor may demand direct payment by following the procedure herein and |
29 | the general contractor may file a sworn reply. A demand made after the first day of the month |
30 | following that for which the subcontractor performed or furnished the labor and materials for |
31 | which the subcontractor seeks payment shall be valid even if delivered or mailed prior to the time |
32 | payment was due on a periodic estimate from the general contractor. Thereafter the awarding |
33 | authority shall proceed. |
34 | (j) Any assignment by a subcontractor of the rights under this section to a surety |
| LC004581 - Page 7 of 10 |
1 | company furnishing a bond shall be invalid. The assignment and subrogation rights of the surety |
2 | to amounts included in a demand for direct payment which are in the possession of the awarding |
3 | authority or which are on deposit pursuant to subsection (f) of this section shall be subordinate to |
4 | the rights of all subcontractors who are entitled to be paid under this section and who have not |
5 | been paid in full. |
6 | (k)(1) "Subcontractor" as used herein means a person who files a sub-bid and received a |
7 | subcontract as a result of that filed sub-bid or who is approved by the awarding authority in |
8 | writing as a person performing labor or both performing labor and furnishing materials pursuant |
9 | to a contract with the general contractor; |
10 | (2) "Contracts awarded" means a person approved by the awarding authority in writing as |
11 | a person performing labor or both performing labor and furnishing materials pursuant to a |
12 | contract with the general contractor, and |
13 | (3) "Contracts with the state not awarded" means a person contracting with the general |
14 | contractor to supply materials used or employed in a public works project for a price in excess of |
15 | five thousand dollars ($5,000). |
16 | (l) A general contractor or a subcontractor shall enforce a claim to any portion of the |
17 | amount of a demand for direct payment deposit as provided in subsection (f) of this section by a |
18 | petition in the superior court against the other and the bank shall not be a necessary party. A |
19 | subcontractor shall enforce a claim for direct payment or a right to require a deposit as provided |
20 | in subsection (f) of this section by a petition in the superior court against the awarding authority |
21 | and the general contractor shall not be a necessary party. Upon motion of any party the court shall |
22 | advance for speedy trial any petition filed. The court shall enter an interlocutory decree upon |
23 | which execution shall issue for any part of a claim found due, upon motion of any party, and shall |
24 | advance for speedy trial the petition to collect the remainder of the claim. Any party aggrieved by |
25 | such interlocutory decree shall have the right to appeal therefrom. The court shall not consolidate |
26 | for trial the petition of any subcontractor with the petition of one or more subcontractors or the |
27 | same general contract unless the court finds that a substantial portion of the evidence is applicable |
28 | to the petitions sought to be consolidated and that such consolidation will prevent unnecessary |
29 | duplication of evidence. A decree in any such proceeding shall not include interest on the |
30 | disputed amount deposited in excess of the interest earned for the period of any such deposit. No |
31 | person except a subcontractor filing a demand for direct payment for which no funds due the |
32 | general contractor are available for direct payment shall have a right to file a petition against the |
33 | awarding authority claiming a demand for direct payment is premature and such subcontractor |
34 | must file the petition before the awarding authority has made a direct payment to the |
| LC004581 - Page 8 of 10 |
1 | subcontractor and has made a deposit of the disputed portion. In any petition to collect any claim |
2 | for which a subcontractor has filed a demand for direct payment the court shall, upon motion of |
3 | the general contractor, reduce by the amount of any deposit of a disputed amount by the awarding |
4 | authority any amount held under a writ of attachment or pursuant to a restraining order or |
5 | injunction. |
6 | SECTION 2. This act shall take effect upon passage. |
======== | |
LC004581 | |
======== | |
| LC004581 - Page 9 of 10 |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO PUBLIC PROPERTY AND WORKS | |
*** | |
1 | This act would establish a procedure for the timely payment to contractors and |
2 | subcontractors in connection with state contracts. The act would provide for an awarding |
3 | authority to make a direct deposit into an interest-bearing joint account in the names of both the |
4 | general contractor and the subcontractor. The act also would authorize a subcontractor to enforce |
5 | a claim for a direct deposit directly against the awarding authority through an action in superior |
6 | court. |
7 | This act would take effect upon passage. |
======== | |
LC004581 | |
======== | |
| LC004581 - Page 10 of 10 |