2016 -- S 2164 | |
======== | |
LC003369 | |
======== | |
STATE OF RHODE ISLAND | |
IN GENERAL ASSEMBLY | |
JANUARY SESSION, A.D. 2016 | |
____________ | |
A N A C T | |
RELATING TO STATE AFFAIRS AND GOVERNMENT -- CAPITAL CITY | |
UNDERGROUND UTILITY INITIATIVE | |
| |
Introduced By: Senators Conley, Goldin, DaPonte, Ruggerio, and Goodwin | |
Date Introduced: January 27, 2016 | |
Referred To: Senate Commerce | |
It is enacted by the General Assembly as follows: | |
1 | SECTION 1. Section 42-98-1.1 of the General Laws in Chapter 42-98 entitled "Energy |
2 | Facility Siting Act" is hereby amended to read as follows: |
3 | 42-98-1.1. Capital city underground utility initiative. -- (a) The public utilities |
4 | commission shall permit the city of Providence or the city of East Providence, upon petition by a |
5 | duly authorized representative of such municipality, to forego some or all of the respective |
6 | municipality's pro rata share of the refund accruing to the ratepayers of the respective |
7 | municipality as computed under section 11(c) of the 3rd Amended Settlement Agreement in |
8 | Docket No. 2930; provided, however, that the city council of each petitioning ratifies such action |
9 | by passage of a resolution. |
10 | (b) The public utilities commission shall permit, upon petition by the attorney general, |
11 | for the use of up to two million dollars ($2,000,000) from Narragansett Electric Company's Storm |
12 | Contingency Fund for purposes of under grounding that portion of the E-183 transmission line |
13 | under consideration in Energy Facility Siting Board Docket 2003-01. |
14 | (c) Narragansett Electric Company shall be required to apply to the regional grid |
15 | operator or its successor organization for approval to charge New England regional network |
16 | service customers for the capital costs associated with the construction of Phase II overhead |
17 | configuration labeled the "North Bridge Alignment" as defined by the Settlement Agreement that |
18 | was approved by the Energy Facility Siting Board in Docket 2003-1. On or before September 1, |
| |
1 | 2016, Narragansett Electric Company shall be required to update the 2004 estimate of the cost of |
2 | the North Bridge Alignment for the purpose of updating any approval charge to New England |
3 | regional network service customers for capital costs. |
4 | (d) The Narragansett Electric Company ("company") shall be authorized required to |
5 | proceed with the construction of the underground alignment of the E-183 line referenced in the |
6 | Settlement Agreement that was approved by the Energy Facility Siting Board in Docket 2003-01 |
7 | ("Underground alignment Alignment"), including the acquisition of any property rights needed to |
8 | implement the underground alignment Underground Alignment subject to the passage of |
9 | resolutions by both city councils of the cities of Providence and East Providence agreeing that |
10 | any incremental costs above existing funding may be included in electric rates of electric |
11 | customers in those cities. Such resolutions must be delivered to the public utilities commission no |
12 | later than July 1, 2009. Notwithstanding the terms of the Settlement, to the extent the actual costs |
13 | for the underground alignment Underground Alignment exceed the funding obtained for the |
14 | project pursuant to this section and from federal and other sources, the company is authorized to |
15 | include the incremental costs that exceed two million dollars ($2,000,000) above those funding |
16 | levels actually available at the time of construction in its distribution rate base and reflect the |
17 | revenue requirement in rates to the electric distribution customers within the State of Rhode |
18 | Island cities of Providence and East Providence, subject to the timely passage and delivery of the |
19 | resolution specified above. Such rate adjustment shall be made within six (6) months from project |
20 | completion, applying the same ratemaking principles as ordinarily applied to distribution capital |
21 | projects when they are allowed in its distribution rate base by the public utilities commission. |
22 | After completion of the underground alignment Underground Alignment, the public utilities |
23 | commission shall conduct a review of costs incurred to construct the underground alignment |
24 | Underground Alignment in order to verify that the company's calculation and implementation of |
25 | rates are in compliance with this section; provided, further, the auditor general shall perform a |
26 | performance audit of state costs. |
27 | (e) If the underground alignment Underground Alignment goes forward, the company |
28 | shall retain such portions of the properties acquired to implement the underground alignment |
29 | Underground Alignment as may be necessary and prudent, and shall transfer any remaining |
30 | portions of said properties to the redevelopment authority of the city in which the property is |
31 | located after the completion of the project, at the city's request and at no additional cost to the |
32 | city. Any easements no longer being used by the company for utility purposes after the |
33 | underground alignment Underground Alignment is completed also shall be transferred to the city |
34 | after the completion of the project, at the city's request and at no additional cost to the city. If |
| LC003369 - Page 2 of 5 |
1 | there is any dispute about the extent to which property or easements are needed and therefore |
2 | should not be transferred, the public utilities commission shall decide the issue upon petition by |
3 | the affected city. |
4 | SECTION 2. Chapter 42-98 of the General Laws entitled "Energy Facility Siting Act" is |
5 | hereby amended by adding thereto the following section: |
6 | 42-98-1.2. Schedule for capital city underground utility initiative. -- (a) The general |
7 | assembly finds that the Settlement Agreement in Docket No. 2930, that provides for this initiative |
8 | was entered and approved by the energy facility siting board on October 29, 2004. The general |
9 | assembly finds that the deadlines with the settlement agreement have not been enforced. |
10 | Therefore, the general assembly finds it necessary to direct and authorize the energy facility siting |
11 | board to establish an enforceable schedule ("project schedule") to complete the initiative on or |
12 | before July 30, 2017. Furthermore, the general assembly finds that the benefit of the Underground |
13 | Alignment or an alternative alignment as set forth in the settlement agreement is statewide and |
14 | electrical customers statewide, as pursuant to the amendment to §42-98-1.1(d) should absorb a |
15 | certain amount of the incremental costs that have now increased with the passage of over eleven |
16 | (11) years since the settlement was reached. |
17 | (b) The project schedule shall include milestone dates for the following: |
18 | (1) Reconstructing the Philipsdale Tap Line out of sequence and forthwith, to advance |
19 | economic development within the East Providence Waterfront District; |
20 | (2) Completion of detailed engineering of the Underground Alignment; |
21 | (3) Commencement and targeted completion of permitting of the Underground |
22 | Alignment by and before, but not limited to: the Energy Facility Siting Board, the Rhode Island |
23 | Department of Environmental Management, the Rhode Island Coastal Resources Management |
24 | Council, the United States Army Corps of Engineers and, if required, the host municipalities; |
25 | (4) Acquiring a drilling landing site in the city of Providence; |
26 | (5) Acquiring other easements and rights, including, but limited to, an underground |
27 | easement through India Point Park, a landing site in the city of East Providence, a transition |
28 | station site and associated transmission line easements in the city of East Providence; |
29 | (6) Soliciting bids for the construction of the Underground Alignment; |
30 | (7) Reviewing construction estimates for the Underground Alignment based upon bid |
31 | results; |
32 | (8) Constructing the Underground Alignment; and |
33 | (9) Removing existing overhead lines and structures. |
34 | (c) The reasonable fees and costs incurred by the cities to establish, monitor and ensure |
| LC003369 - Page 3 of 5 |
1 | compliance with the project schedule shall be a reimbursable cost of the project. |
2 | (d) In the event the parties to the settlement agreement are aggrieved by an order of the |
3 | Energy Facility Siting Board to establish an enforceable project schedule, such aggrieved party |
4 | may seek review of said order by the Providence County Superior Court, Business Calendar |
5 | under the standards embodied in §42-35-15. |
6 | (e) On or before August 15, 2016, in an effort to curb incremental costs relating to the |
7 | Underground Alignment, the Rhode Island Department of Transportation shall engage an |
8 | independent consultant whose qualifications are deemed acceptable to the parties to the |
9 | Settlement Agreement to opine in writing whether it is possible and if so, to estimate the cost of |
10 | having the electric transmission lines utilize existing bridge structures to effectuate the river |
11 | crossings necessitated by the Underground Alignment. |
12 | (f) If the City Councils for East Providence and Providence determine by resolution not |
13 | to pursue the Underground Alignment then the parties to the Settlement Agreement in Docket No. |
14 | 2930 are directed to undertake and complete the North Bridge Alignment as defined in said |
15 | Settlement Agreement within the schedule deadlines set forth above in this section. The cities |
16 | must so resolve on or before October 30, 2016. In the event of such resolution, an enforceable |
17 | schedule shall be established as pursuant to subsection (b) of this section. The relocation of the |
18 | Philipsdale Tap Line shall be likewise completed out of sequence, so as to expedite that facet of |
19 | the Project. Subsections (c) and (d), of this section shall likewise be applicable to the North |
20 | Bridge Alignment, if it is to be constructed pursuant to this subsection. |
21 | SECTION 3. This act shall take effect upon passage. |
======== | |
LC003369 | |
======== | |
| LC003369 - Page 4 of 5 |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO STATE AFFAIRS AND GOVERNMENT -- CAPITAL CITY | |
UNDERGROUND UTILITY INITIATIVE | |
*** | |
1 | This act would authorize the Energy Facility Siting Board to establish an enforceable |
2 | schedule for Narragansett Electric Company's completion of the construction of the Capital City |
3 | Underground Utility Alignment Initiative on or before July 30, 2017. |
4 | This act would take effect upon passage. |
======== | |
LC003369 | |
======== | |
| LC003369 - Page 5 of 5 |