     SECTION 1. Chapter 39-1.2 of the General Laws entitled "Excavation Near

2

Underground Utility Facilities" is hereby amended by adding thereto the following section:

3

     39-1.2-15. Costs associated with relocation of public utility infrastructure during

4

public works construction projects. – Any and all costs incurred by any municipality as a result

5

of the temporary or permanent relocation of any public utility infrastructure, including, but not

6

limited to, public utility poles, during the repair, maintenance, construction or reconstruction or

7

any municipal right-of-way shall be borne exclusively by the public utility.

8

     SECTION 2. This act shall take effect upon passage.

========

LC004150

========

 

EXPLANATION

BY THE LEGISLATIVE COUNCIL

OF

A N   A C T

RELATING TO PUBLIC UTILITIES AND CARRIERS -- EXCAVATION NEAR

UNDERGROUND UTILITY FACILITIES -- COSTS

***

1

     This act would require that all costs incurred by municipal corporations associated with

2

the temporary or permanent relocation of utility infrastructure such as public utility poles during

3

public works projects within municipal rights-of-way be borne by the public utility.

4

     This act would take effect upon passage.

========