2017 -- H 5483 SUBSTITUTE A AS AMENDED

========

LC000960/SUB A

========

     STATE OF RHODE ISLAND

IN GENERAL ASSEMBLY

JANUARY SESSION, A.D. 2017

____________

A N   A C T

RELATING TO PUBLIC UTILITIES AND CARRIERS

     

     Introduced By: Representatives Marshall, Regunberg, Ruggiero, McKiernan, and

     Date Introduced: February 15, 2017

     Referred To: House Corporations

     It is enacted by the General Assembly as follows:

1

     SECTION 1. Section 39-26.3-2 of the General Laws in Chapter 39-26.3 entitled

2

"Distributed Generation Interconnection" is hereby amended to read as follows:

3

     39-26.3-2. Definitions.

4

     The following terms shall have the meanings given below for purposes of this chapter:

5

     (1) "Applicant" means an electric distribution customer or distributed generation

6

developer who submits an application to the electric distribution company for the installation of a

7

renewable distributed generation interconnection to the distribution system for a renewable

8

distributed generation project that, as contemplated, meets the eligibility requirements for net

9

metering contained within title 39 or the eligibility requirements for a standard contract contained

10

within title 39.

11

     (2) "Impact study" means an engineering study that includes an estimate of the cost of

12

interconnecting to the distribution system that would be assessed on the applicant for an

13

interconnection that is based on an engineering study of the details of the proposed generation

14

project. Such estimate generally will have a probability of accuracy of plus or minus twenty five

15

percent (25%). Such an estimate may be relied upon by the applicant for purposes of determining

16

the expected cost of interconnection, but the distribution company may not be held liable or

17

responsible if the actual costs exceed the estimate as long as the estimate was provided in good

18

faith and the interconnection was implemented prudently by the electric distribution company.

19

     (3) "Impact study fee" means a fee that shall be charged to the applicant to obtain an

 

1

impact study as specified in § 39-26.2-4 of this chapter.

2

     (4) "Feasibility study" means a high-level project assessment that includes an estimate of

3

the cost of interconnecting to the distribution system that would be assessed on the applicant for

4

an interconnection. Such estimate is not based on any engineering study, but is based on past

5

experience and judgment of the electric distribution company, taking into account the information

6

in the application, the location of the interconnection, and general knowledge of the distribution

7

and transmission system. Such estimate cannot be relied upon by the applicant for purposes of

8

holding the electric distribution company liable or responsible for its accuracy as long as the

9

electric distribution company has provided the estimate in good faith. The feasibility study

10

estimate shall be a range within which the electric distribution company believes the

11

interconnection costs are likely to be and shall include a disclaimer that explains the nature of the

12

estimate.

13

     (5) "Feasibility study fee" means a fee that shall be charged to the applicant to obtain a

14

feasibility study as specified in § 39-26.2-4 of this chapter.

15

     (6) "Renewable energy resource" as defined pursuant to §39-26-5.

16

     SECTION 2. Chapter 39-26.3 of the General Laws entitled "Distributed Generation

17

Interconnection" is hereby amended by adding thereto the following section:

18

     39-26.3-7. Interconnection standards.

19

     (a) The electric distribution company may only charge an interconnecting renewable

20

energy customer for any system modifications to its electric power system specifically necessary

21

for and directly related to its interconnection.

22

     (b) If the public utilities commission determines that a specific system modification

23

benefiting other customers has been accelerated due to an interconnection request, it may order

24

the interconnecting customer to fund the modification subject to repayment of the depreciated

25

value of the modification as of the time the modification would have been necessary as

26

determined by the public utilities commission. Any system modifications benefiting other

27

customers shall be included in rates as determined by the public utilities commission.

28

     (c) If an interconnecting renewable energy customer is required to pay for system

29

modifications and a subsequent renewable energy or commercial customer relies on those

30

modifications to connect to the distribution system within ten (10) years of the earlier

31

interconnecting renewable energy customer's payment, the subsequent customer will make a

32

prorated contribution toward the cost of the system modifications which will be credited to the

33

earlier interconnecting renewable energy customer as determined by the public utilities

34

commission.

 

LC000960/SUB A - Page 2 of 5

1

     (d) An electric distribution company shall acknowledge to the interconnecting renewable

2

energy customer receipt of an application to initiate the interconnection process within three (3)

3

business days of receipt. The electric distribution company shall notify the interconnecting

4

renewable energy customer in writing within ten (10) business days of receipt that the application

5

is or is not complete and, if not, advise what is missing. Any disputes regarding whether and

6

when an application to initiate the interconnection process is complete shall be resolved

7

expeditiously at the public utilities commission. The maximum time allowed between the date of

8

the completed application and delivery of an executable interconnection service agreement shall

9

be one hundred seventy-five (175) calendar days or two hundred (200) calendar days if a detailed

10

study is required. All electric distribution company system modifications must be completed by

11

the date which is the later of:

12

     (1) No longer than two hundred seventy (270) calendar days, or three hundred sixty (360)

13

calendar days if substation work is necessary, from the effective date of the electric distribution

14

company's receipt of the interconnecting renewable energy customer's executed interconnection

15

service agreement; or

16

     (2) The interconnecting renewable energy customer's agreed upon extension of the time

17

between the execution of the interconnection service agreement and interconnection as set forth

18

in writing. All deadlines herein are subject to all payments being made in accordance with the

19

distributed generation interconnection tariff on file with the public utilities commission and the

20

interconnection service agreement. These system modification deadlines cannot be extended due

21

to customer delays in providing required information, all of which must be requested and

22

obtained before completion of the impact study. The deadlines for completion of system

23

modifications will be extended only to the extent of events that are clearly not under the control

24

of the electric distribution company, such as extended prohibitive weather, union work stoppage

25

or force majeure, or third party delays, including, without limitation, delays due to ISO-NE

26

requirements not attributable to electric distribution company actions, and which cannot be

27

resolved despite commercially reasonable efforts. The electric distribution company shall notify

28

the customer of the start of any claimed deadline extension as soon as practicable, its cause and

29

when it concludes, all in writing. Any actual damages that a court of competent jurisdiction

30

orders the electric distribution company to pay to an interconnecting renewable energy customer

31

as a direct result of the electric distribution company's failure to comply with the requirements of

32

this subsection shall be payable by its shareholders and may not be recovered from customers,

33

provided that the total amount of damages awarded for any and all such claims shall not exceed,

34

in the aggregate, an amount equal to the amount of the incentive the electric distribution company

 

LC000960/SUB A - Page 3 of 5

1

would have earned as provided for in §§39-26.6-12(j)(3) and 39-26.1-4 in the year in which the

2

system modifications were required to be completed. In no event shall the electric distribution

3

company be liable to the interconnecting renewable energy customer for any indirect, incidental,

4

special, consequential, or punitive damages of any kind whatsoever as a result of the electric

5

distribution company's failure to comply with this section.

6

     (e) On or before September 1, 2017, the public utilities commission shall initiate a docket

7

to establish metrics for the electric distribution company's performance in meeting the time

8

frames set forth herein and in the distributed generation interconnection standards approved by

9

the public utilities commission. The public utilities commission may include incentives and

10

penalties in the performance metrics.

11

     (f) The proposed interconnection of any new renewable energy resource that replaces the

12

same existing renewable energy resource of the same or less nameplate capacity that has been in

13

operation in the twelve (12) months preceding notifications of such replacement shall be subject

14

to a sixty (60) day review. The purpose of such sixty (60) day review is to allow the electric

15

distribution company to determine whether any system modifications are required to support the

16

interconnection of the replacement renewable energy resource. If there is a need for system

17

modifications because of an interconnection policy change implemented by the electric

18

distribution company then the system modification may be included in rates as determined by the

19

public utilities commission. If there is a need for system modifications only because of a change

20

in the rating or utility distribution response that adversely affects the impact of the facility on the

21

distribution system then the interconnecting renewable energy customer shall be responsible for

22

the cost of the system modifications.

23

     SECTION 3. This act shall take effect upon passage.

========

LC000960/SUB A

========

 

LC000960/SUB A - Page 4 of 5

EXPLANATION

BY THE LEGISLATIVE COUNCIL

OF

A N   A C T

RELATING TO PUBLIC UTILITIES AND CARRIERS

***

1

     This act would prohibit electrical distribution companies from charging an

2

interconnecting renewable energy customer for system modifications that are not directly related

3

to the interconnection, except accelerated modifications for which the developer is repaid when

4

the modification would have otherwise been made. It would also require that any system

5

modifications be completed no later than:

6

     (1) Fourteen (14) calendar months from the effective date of the interconnecting

7

renewable energy customer's interconnection service agreement subject to all payments being

8

made in accordance with the interconnection service agreement; or

9

     (2) The renewable energy customer's agreed upon expected interconnection date as set

10

forth in the executed interconnection service agreement and full payment for all required system

11

modifications.

12

     This act would take effect upon passage.

========

LC000960/SUB A

========

 

LC000960/SUB A - Page 5 of 5