2017 -- H 5483 SUBSTITUTE A AS AMENDED | |
======== | |
LC000960/SUB A | |
======== | |
STATE OF RHODE ISLAND | |
IN GENERAL ASSEMBLY | |
JANUARY SESSION, A.D. 2017 | |
____________ | |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS | |
| |
Introduced By: Representatives Marshall, Regunberg, Ruggiero, McKiernan, and | |
Date Introduced: February 15, 2017 | |
Referred To: House Corporations | |
It is enacted by the General Assembly as follows: | |
1 | SECTION 1. Section 39-26.3-2 of the General Laws in Chapter 39-26.3 entitled |
2 | "Distributed Generation Interconnection" is hereby amended to read as follows: |
3 | 39-26.3-2. Definitions. |
4 | The following terms shall have the meanings given below for purposes of this chapter: |
5 | (1) "Applicant" means an electric distribution customer or distributed generation |
6 | developer who submits an application to the electric distribution company for the installation of a |
7 | renewable distributed generation interconnection to the distribution system for a renewable |
8 | distributed generation project that, as contemplated, meets the eligibility requirements for net |
9 | metering contained within title 39 or the eligibility requirements for a standard contract contained |
10 | within title 39. |
11 | (2) "Impact study" means an engineering study that includes an estimate of the cost of |
12 | interconnecting to the distribution system that would be assessed on the applicant for an |
13 | interconnection that is based on an engineering study of the details of the proposed generation |
14 | project. Such estimate generally will have a probability of accuracy of plus or minus twenty five |
15 | percent (25%). Such an estimate may be relied upon by the applicant for purposes of determining |
16 | the expected cost of interconnection, but the distribution company may not be held liable or |
17 | responsible if the actual costs exceed the estimate as long as the estimate was provided in good |
18 | faith and the interconnection was implemented prudently by the electric distribution company. |
19 | (3) "Impact study fee" means a fee that shall be charged to the applicant to obtain an |
| |
1 | impact study as specified in § 39-26.2-4 of this chapter. |
2 | (4) "Feasibility study" means a high-level project assessment that includes an estimate of |
3 | the cost of interconnecting to the distribution system that would be assessed on the applicant for |
4 | an interconnection. Such estimate is not based on any engineering study, but is based on past |
5 | experience and judgment of the electric distribution company, taking into account the information |
6 | in the application, the location of the interconnection, and general knowledge of the distribution |
7 | and transmission system. Such estimate cannot be relied upon by the applicant for purposes of |
8 | holding the electric distribution company liable or responsible for its accuracy as long as the |
9 | electric distribution company has provided the estimate in good faith. The feasibility study |
10 | estimate shall be a range within which the electric distribution company believes the |
11 | interconnection costs are likely to be and shall include a disclaimer that explains the nature of the |
12 | estimate. |
13 | (5) "Feasibility study fee" means a fee that shall be charged to the applicant to obtain a |
14 | feasibility study as specified in § 39-26.2-4 of this chapter. |
15 | (6) "Renewable energy resource" as defined pursuant to §39-26-5. |
16 | SECTION 2. Chapter 39-26.3 of the General Laws entitled "Distributed Generation |
17 | Interconnection" is hereby amended by adding thereto the following section: |
18 | 39-26.3-7. Interconnection standards. |
19 | (a) The electric distribution company may only charge an interconnecting renewable |
20 | energy customer for any system modifications to its electric power system specifically necessary |
21 | for and directly related to its interconnection. |
22 | (b) If the public utilities commission determines that a specific system modification |
23 | benefiting other customers has been accelerated due to an interconnection request, it may order |
24 | the interconnecting customer to fund the modification subject to repayment of the depreciated |
25 | value of the modification as of the time the modification would have been necessary as |
26 | determined by the public utilities commission. Any system modifications benefiting other |
27 | customers shall be included in rates as determined by the public utilities commission. |
28 | (c) If an interconnecting renewable energy customer is required to pay for system |
29 | modifications and a subsequent renewable energy or commercial customer relies on those |
30 | modifications to connect to the distribution system within ten (10) years of the earlier |
31 | interconnecting renewable energy customer's payment, the subsequent customer will make a |
32 | prorated contribution toward the cost of the system modifications which will be credited to the |
33 | earlier interconnecting renewable energy customer as determined by the public utilities |
34 | commission. |
| LC000960/SUB A - Page 2 of 5 |
1 | (d) An electric distribution company shall acknowledge to the interconnecting renewable |
2 | energy customer receipt of an application to initiate the interconnection process within three (3) |
3 | business days of receipt. The electric distribution company shall notify the interconnecting |
4 | renewable energy customer in writing within ten (10) business days of receipt that the application |
5 | is or is not complete and, if not, advise what is missing. Any disputes regarding whether and |
6 | when an application to initiate the interconnection process is complete shall be resolved |
7 | expeditiously at the public utilities commission. The maximum time allowed between the date of |
8 | the completed application and delivery of an executable interconnection service agreement shall |
9 | be one hundred seventy-five (175) calendar days or two hundred (200) calendar days if a detailed |
10 | study is required. All electric distribution company system modifications must be completed by |
11 | the date which is the later of: |
12 | (1) No longer than two hundred seventy (270) calendar days, or three hundred sixty (360) |
13 | calendar days if substation work is necessary, from the effective date of the electric distribution |
14 | company's receipt of the interconnecting renewable energy customer's executed interconnection |
15 | service agreement; or |
16 | (2) The interconnecting renewable energy customer's agreed upon extension of the time |
17 | between the execution of the interconnection service agreement and interconnection as set forth |
18 | in writing. All deadlines herein are subject to all payments being made in accordance with the |
19 | distributed generation interconnection tariff on file with the public utilities commission and the |
20 | interconnection service agreement. These system modification deadlines cannot be extended due |
21 | to customer delays in providing required information, all of which must be requested and |
22 | obtained before completion of the impact study. The deadlines for completion of system |
23 | modifications will be extended only to the extent of events that are clearly not under the control |
24 | of the electric distribution company, such as extended prohibitive weather, union work stoppage |
25 | or force majeure, or third party delays, including, without limitation, delays due to ISO-NE |
26 | requirements not attributable to electric distribution company actions, and which cannot be |
27 | resolved despite commercially reasonable efforts. The electric distribution company shall notify |
28 | the customer of the start of any claimed deadline extension as soon as practicable, its cause and |
29 | when it concludes, all in writing. Any actual damages that a court of competent jurisdiction |
30 | orders the electric distribution company to pay to an interconnecting renewable energy customer |
31 | as a direct result of the electric distribution company's failure to comply with the requirements of |
32 | this subsection shall be payable by its shareholders and may not be recovered from customers, |
33 | provided that the total amount of damages awarded for any and all such claims shall not exceed, |
34 | in the aggregate, an amount equal to the amount of the incentive the electric distribution company |
| LC000960/SUB A - Page 3 of 5 |
1 | would have earned as provided for in §§39-26.6-12(j)(3) and 39-26.1-4 in the year in which the |
2 | system modifications were required to be completed. In no event shall the electric distribution |
3 | company be liable to the interconnecting renewable energy customer for any indirect, incidental, |
4 | special, consequential, or punitive damages of any kind whatsoever as a result of the electric |
5 | distribution company's failure to comply with this section. |
6 | (e) On or before September 1, 2017, the public utilities commission shall initiate a docket |
7 | to establish metrics for the electric distribution company's performance in meeting the time |
8 | frames set forth herein and in the distributed generation interconnection standards approved by |
9 | the public utilities commission. The public utilities commission may include incentives and |
10 | penalties in the performance metrics. |
11 | (f) The proposed interconnection of any new renewable energy resource that replaces the |
12 | same existing renewable energy resource of the same or less nameplate capacity that has been in |
13 | operation in the twelve (12) months preceding notifications of such replacement shall be subject |
14 | to a sixty (60) day review. The purpose of such sixty (60) day review is to allow the electric |
15 | distribution company to determine whether any system modifications are required to support the |
16 | interconnection of the replacement renewable energy resource. If there is a need for system |
17 | modifications because of an interconnection policy change implemented by the electric |
18 | distribution company then the system modification may be included in rates as determined by the |
19 | public utilities commission. If there is a need for system modifications only because of a change |
20 | in the rating or utility distribution response that adversely affects the impact of the facility on the |
21 | distribution system then the interconnecting renewable energy customer shall be responsible for |
22 | the cost of the system modifications. |
23 | SECTION 3. This act shall take effect upon passage. |
======== | |
LC000960/SUB A | |
======== | |
| LC000960/SUB A - Page 4 of 5 |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS | |
*** | |
1 | This act would prohibit electrical distribution companies from charging an |
2 | interconnecting renewable energy customer for system modifications that are not directly related |
3 | to the interconnection, except accelerated modifications for which the developer is repaid when |
4 | the modification would have otherwise been made. It would also require that any system |
5 | modifications be completed no later than: |
6 | (1) Fourteen (14) calendar months from the effective date of the interconnecting |
7 | renewable energy customer's interconnection service agreement subject to all payments being |
8 | made in accordance with the interconnection service agreement; or |
9 | (2) The renewable energy customer's agreed upon expected interconnection date as set |
10 | forth in the executed interconnection service agreement and full payment for all required system |
11 | modifications. |
12 | This act would take effect upon passage. |
======== | |
LC000960/SUB A | |
======== | |
| LC000960/SUB A - Page 5 of 5 |