2017 -- H 5640

========

LC001810

========

     STATE OF RHODE ISLAND

IN GENERAL ASSEMBLY

JANUARY SESSION, A.D. 2017

____________

A N   A C T

RELATING TO PUBLIC UTILITIES AND CARRIERS - PUBLIC UTILITIES COMMISSION

     

     Introduced By: Representatives Corvese, McNamara, and Azzinaro

     Date Introduced: March 01, 2017

     Referred To: House Corporations

     It is enacted by the General Assembly as follows:

1

     SECTION 1. Section 39-1-27.7 of the General Laws in Chapter 39-1 entitled "Public

2

Utilities Commission" is hereby amended to read as follows:

3

     39-1-27.7. System reliability and least-cost procurement.

4

     Least-cost procurement shall comprise system reliability and energy efficiency and

5

conservation procurement as provided for in this section and supply procurement as provided for

6

in ยง 39-1-27.8, as complementary but distinct activities that have as common purpose meeting

7

electrical and natural gas energy needs in Rhode Island, in a manner that is optimally cost-

8

effective, reliable, prudent and environmentally responsible.

9

     (a) The commission shall establish not later than June 1, 2008, standards for system

10

reliability and energy efficiency and conservation procurement, which shall include standards and

11

guidelines for:

12

     (1) System reliability procurement, including but not limited to:

13

     (i) Procurement of energy supply from diverse sources, including, but not limited to,

14

renewable energy resources as defined in chapter 26 of this title;

15

     (ii) Distributed generation, including, but not limited to, renewable energy resources and

16

thermally leading combined heat and power systems, which is reliable and is cost-effective, with

17

measurable, net system benefits;

18

     (iii) Demand response, including, but not limited to, distributed generation, back-up

19

generation and on-demand usage reduction, which shall be designed to facilitate electric customer

 

1

participation in regional demand response programs, including those administered by the

2

independent service operator of New England ("ISO-NE") and/or are designed to provide local

3

system reliability benefits through load control or using on-site generating capability;

4

     (iv) To effectuate the purposes of this division, the commission may establish standards

5

and/or rates:

6

     (A) For qualifying distributed generation, demand response, and renewable energy

7

resources;

8

     (B) For net-metering;

9

     (C) For back-up power and/or standby rates that reasonably facilitate the development of

10

distributed generation; and

11

     (D) For such other matters as the commission may find necessary or appropriate.

12

     (2) Least-cost procurement, which shall include procurement of energy efficiency and

13

energy conservation measures that are prudent, and reliable, and verifiable, and when such

14

measures are lower cost than acquisition of additional supply, including supply for periods of

15

high demand, and which when calculating least cost procurement energy efficiency and energy

16

conservation measures which shall factor in the results of the annual savings verification

17

conducted by the commission.

18

     (b) The standards and guidelines provided for by subsection (a) shall be subject to

19

periodic review and as appropriate amendment by the commission, which review will be

20

conducted not less frequently than every three (3) years after the adoption of the standards and

21

guidelines.

22

     (c) To implement the provisions of this section:

23

     (1) The commissioner of the office of energy resources and the energy efficiency and

24

resources management council, either or jointly or separately, shall provide the commission

25

findings and recommendations with regard to system reliability and energy efficiency and

26

conservation procurement on or before March 1, 2008, and triennially on or before March 1,

27

thereafter through March 1, 2024. The report shall be made public and be posted electronically on

28

the website to the office of energy resources.

29

     (2) The commission shall issue standards not later than June 1, 2008, with regard to plans

30

for system reliability and energy efficiency and conservation procurement, which standards may

31

be amended or revised by the commission as necessary and/or appropriate.

32

     (3) The energy efficiency and resources management council shall prepare by July 15,

33

2008, a reliability and efficiency procurement opportunity report which shall identify

34

opportunities to procure efficiency, distributed generation, demand response and renewables,

 

LC001810 - Page 2 of 6

1

which report shall be submitted to the electrical distribution company, the commission, the office

2

of energy resources and the joint committee on energy.

3

     (4) Each electrical and natural gas distribution company shall submit to the commission

4

on or before September 1, 2008, and triennially on or before September 1, thereafter through

5

September 1, 2024, a plan for system reliability and energy efficiency and conservation

6

procurement. In developing the plan, the distribution company may seek the advice of the

7

commissioner and the council. The plan shall include measurable goals verifiable by a third-party

8

expert and target percentages for each energy resource, pursuant to standards established by the

9

commission, including efficiency, distributed generation, demand response, combined heat and

10

power, and renewables. The plan shall be made public and be posted electronically on the website

11

to the office of energy resources, and shall also be submitted to the general assembly. The

12

commission shall include standards for annual verification of energy efficiency through a

13

representative sample of all the types of energy conservation measures for which energy savings

14

are claimed prior to and after their implementation. The results of this annual verification shall be

15

used to adjust goals and factored into the least cost procurement calculation. The annual

16

verification shall be conducted by the commission independent of the EERMC and the utilities,

17

and the cost of the independent verification shall be part of the system benefit charge.

18

     (5) The commission shall issue an order approving all energy efficiency measures that are

19

cost effective and lower cost than acquisition of additional supply, with regard to the plan from

20

the electrical and natural gas distribution company, and reviewed and approved by the energy

21

efficiency and resources management council, and any related annual plans, and shall approve a

22

fully reconciling funding mechanism to fund investments in all efficiency measures that are cost

23

effective and lower cost than acquisition of additional supply, not greater than sixty (60) days

24

after it is filed with the commission. Provided, however, any system benefit charge provided

25

pursuant to title 39 used to support programs under this subsection shall be capped at the year

26

2017 charge level for a period of five (5) years.

27

     (6) (i) Each electrical and natural gas distribution company shall provide a status report,

28

which shall be public, on the implementation of least cost procurement on or before December

29

15, 2008, and on or before February 1, 2009, to the commission, the division, the commissioner

30

of the office of energy resources and the energy efficiency and resources management council

31

which may provide the distribution company recommendations with regard to effective

32

implementation of least cost procurement. The report shall include the targets for each energy

33

resource included in the order approving the plan and the achieved percentage for energy

34

resource, including the achieved percentages for efficiency, distributed generation, demand

 

LC001810 - Page 3 of 6

1

response, combined heat and power, and renewables as well as the current funding allocations for

2

each eligible energy resource and the businesses and vendors in Rhode Island participating in the

3

programs. The report shall be posted electronically on the website of the office of energy

4

resources.

5

     (ii) Beginning on November 1, 2012 or before, each electric distribution company shall

6

support the installation and investment in clean and efficient combined heat and power

7

installations at commercial, institutional, municipal, and industrial facilities. This support shall be

8

documented annually in the electric distribution company's energy efficiency program plans. In

9

order to effectuate this provision, the energy efficiency and resource management council shall

10

seek input from the public, the gas and electric distribution company, the economic development

11

corporation, and commercial and industrial users, and make recommendations regarding services

12

to support the development of combined heat and power installations in the electric distribution

13

company's annual and triennial energy efficiency program plans.

14

     (iii) The energy efficiency annual plan shall include, but not be limited to, a plan for

15

identifying and recruiting qualified combined heat and power projects, incentive levels, contract

16

terms and guidelines, and achievable megawatt targets for investments in combined heat and

17

power systems. In the development of the plan, the energy efficiency and resource management

18

council and the electric distribution company shall factor into the combined heat and power plan

19

and program, the following criteria:

20

     (A) Economic development benefits in Rhode Island, including direct and indirect job

21

creation and retention from investments in combined heat and power systems;

22

     (B) Energy and cost savings for customers;

23

     (C) Energy supply costs;

24

     (D) Greenhouse gas emissions standards and air quality benefits; and (E) System

25

reliability benefits.

26

     (iv) The energy efficiency and resource management council shall conduct at least one

27

public review meeting annually, to discuss and review the combined heat and power program,

28

with at least seven (7) business day's notice, prior to the electric and gas distribution utility

29

submitting the plan to the commission. The commission shall evaluate the submitted combined

30

heat and power program as part of the annual energy efficiency plan. The commission shall issue

31

an order approving the energy efficiency plan and programs within sixty (60) days of the filing.

32

     (d) If the commission shall determine that the implementation of system reliability and

33

energy efficiency and conservation procurement has caused or is likely to cause under or over-

34

recovery of overhead and fixed costs of the company implementing said procurement, the

 

LC001810 - Page 4 of 6

1

commission may establish a mandatory rate adjustment clause for the company so affected in

2

order to provide for full recovery of reasonable and prudent overhead and fixed costs.

3

     (e) The commission shall conduct a contested case proceeding to establish a performance

4

based incentive plan which allows for additional compensation for each electric distribution

5

company and each company providing gas to end-users and/or retail customers based on the level

6

of its success in mitigating the cost and variability of electric and gas services through

7

procurement portfolios.

8

     SECTION 2. This act shall take effect upon passage.

========

LC001810

========

 

LC001810 - Page 5 of 6

EXPLANATION

BY THE LEGISLATIVE COUNCIL

OF

A N   A C T

RELATING TO PUBLIC UTILITIES AND CARRIERS - PUBLIC UTILITIES COMMISSION

***

1

     This act would require verifiable least cost energy procurements and standards for annual

2

verification of energy efficiency.

3

     This act would take effect upon passage.

========

LC001810

========

 

LC001810 - Page 6 of 6