2017 -- S 0637 | |
======== | |
LC001675 | |
======== | |
STATE OF RHODE ISLAND | |
IN GENERAL ASSEMBLY | |
JANUARY SESSION, A.D. 2017 | |
____________ | |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS | |
| |
Introduced By: Senators DiPalma, Seveney, Miller, Satchell, and Kettle | |
Date Introduced: March 29, 2017 | |
Referred To: Senate Environment & Agriculture | |
It is enacted by the General Assembly as follows: | |
1 | SECTION 1. Section 39-26.3-2 of the General Laws in Chapter 39-26.3 entitled |
2 | "Distributed Generation Interconnection" is hereby amended to read as follows: |
3 | 39-26.3-2. Definitions. |
4 | The following terms shall have the meanings given below for purposes of this chapter: |
5 | (1) "Applicant" means an electric distribution customer or distributed generation |
6 | developer who submits an application to the electric distribution company for the installation of a |
7 | renewable distributed generation interconnection to the distribution system for a renewable |
8 | distributed generation project that, as contemplated, meets the eligibility requirements for net |
9 | metering contained within title 39 or the eligibility requirements for a standard contract contained |
10 | within title 39. |
11 | (2) "Impact study" means an engineering study that includes an estimate of the cost of |
12 | interconnecting to the distribution system that would be assessed on the applicant for an |
13 | interconnection that is based on an engineering study of the details of the proposed generation |
14 | project. Such estimate generally will have a probability of accuracy of plus or minus twenty five |
15 | percent (25%). Such an estimate may be relied upon by the applicant for purposes of determining |
16 | the expected cost of interconnection, but the distribution company may not be held liable or |
17 | responsible if the actual costs exceed the estimate as long as the estimate was provided in good |
18 | faith and the interconnection was implemented prudently by the electric distribution company. |
19 | (3) "Impact study fee" means a fee that shall be charged to the applicant to obtain an |
| |
1 | impact study as specified in § 39-26.2-4 of this chapter. |
2 | (4) "Feasibility study" means a high-level project assessment that includes an estimate of |
3 | the cost of interconnecting to the distribution system that would be assessed on the applicant for |
4 | an interconnection. Such estimate is not based on any engineering study, but is based on past |
5 | experience and judgment of the electric distribution company, taking into account the information |
6 | in the application, the location of the interconnection, and general knowledge of the distribution |
7 | and transmission system. Such estimate cannot be relied upon by the applicant for purposes of |
8 | holding the electric distribution company liable or responsible for its accuracy as long as the |
9 | electric distribution company has provided the estimate in good faith. The feasibility study |
10 | estimate shall be a range within which the electric distribution company believes the |
11 | interconnection costs are likely to be and shall include a disclaimer that explains the nature of the |
12 | estimate. |
13 | (5) "Feasibility study fee" means a fee that shall be charged to the applicant to obtain a |
14 | feasibility study as specified in § 39-26.2-4 of this chapter. |
15 | (6) "Renewable energy resource" shall have the same meaning as defined in §39-26-5. |
16 | SECTION 2. Chapter 39-26.3 of the General Laws entitled "Distributed Generation |
17 | Interconnection" is hereby amended by adding thereto the following section: |
18 | 39-26.3-7. Interconnection standards. |
19 | (a) The electric distribution company may only charge an interconnecting renewable |
20 | energy customer for any system modifications to its electric power system specifically necessary |
21 | for and directly related to its interconnection. Any system modifications benefiting other |
22 | customers shall be included in rates as determined by the public utilities commission. |
23 | (b) If the public utilities commission determines that a specific system modification |
24 | benefiting other customers has been accelerated due to an interconnection request, it may order |
25 | the interconnecting customer to fund the modification subject to repayment of the depreciated |
26 | value of the modification as of the time the modification would have been necessary as |
27 | determined by the public utilities commission. |
28 | (c) If an interconnecting renewable energy customer is required to pay for system |
29 | modifications and a subsequent renewable energy or commercial customer relies on those |
30 | modifications to connect to the distribution system within ten (10) years of the earlier |
31 | interconnecting renewable energy customer's payment, the subsequent customer will make a |
32 | prorated contribution toward the cost of the system modifications which will be credited to the |
33 | earlier interconnecting renewable energy customer as determined by the public utilities |
34 | commission. |
| LC001675 - Page 2 of 5 |
1 | (d) All interconnection work must be performed no longer than two hundred seventy |
2 | (270) calendar days from completion of the renewable energy customer's interconnection impact |
3 | study pursuant to §39-26.3-3, if required, or else no more than three hundred sixty (360) calendar |
4 | days from the customer's completed application for interconnection. Any disputes regarding |
5 | whether and when an application is complete shall be resolved expeditiously by the public |
6 | utilities commission. Deadlines shall not be extended due to customer delays in providing |
7 | required information, all of which must be requested and obtained before completion of the |
8 | impact study. Within thirty (30) days after receipt of an initial application for interconnection, the |
9 | distribution company shall advise the customer, in writing, whether the application is complete, |
10 | and, if not, shall specify all additional information the customer is required to provide. The |
11 | customer must then complete the application within thirty (30) working days. The electric |
12 | distribution company will then have ten (10) working days to determine and inform the applicant |
13 | whether the application is complete. The deadlines for completion of interconnection will be |
14 | extended only to the extent of events that are clearly not under the control of the electric |
15 | distribution company, such as extended prohibitive weather, union work stoppage or force |
16 | majeure, and cannot be resolved despite commercially reasonable, diligent efforts. The electric |
17 | distribution company shall clearly notify the customer of the start of any claimed deadline |
18 | extension at the time it begins, its cause and when it concludes in writing. The electric |
19 | distribution company will be liable to the interconnecting customer for all actual and |
20 | consequential damages resulting from the noncompliant interconnection delay including, but not |
21 | limited to, the full value of any lost energy production, and any reasonable legal fees and costs |
22 | associated with the recovery of those damages. The public utilities commission shall hold a |
23 | hearing to determine whether any penalties and damages are due to developer under this section. |
24 | No later than thirty (30) days from the date of the commission’s written decision, the electric |
25 | distribution company shall remit to the interconnecting renewable energy customer an amount |
26 | equal to such reasonable compensation as determined by the commission. The compensation shall |
27 | be paid out of the incentive amount earned by the electric distribution company as provided for in |
28 | §39-26.6-12(j)(3) and, until January 1, 2022, as provided for in §39-26.1-4. |
29 | (e) The interconnection of any new renewable energy resource that replaces the same |
30 | existing renewable energy resource of the same or less nameplate capacity shall not be considered |
31 | a material modification requiring interconnection study or approval other than a review to |
32 | determine consistency with this section and to establish any costs specifically necessary to |
33 | interconnect the replacement renewable energy resource, which shall not include any system |
34 | modifications or system improvements. This review shall take no longer than sixty (60) days |
| LC001675 - Page 3 of 5 |
1 | subject to the penalties provided in subsection (d) of this section. |
2 | SECTION 3. This act shall take effect upon passage. |
======== | |
LC001675 | |
======== | |
| LC001675 - Page 4 of 5 |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS | |
*** | |
1 | This act would prohibit electrical distribution companies from charging an |
2 | interconnecting renewable energy customer for system modifications that are not directly related |
3 | to the interconnection, except accelerated modifications for which the developer is repaid when |
4 | the modification would have otherwise been made. It would require that any interconnection |
5 | work must be completed no later than two hundred seventy (270) days from the applicant's |
6 | impact study or three hundred sixty (360) days from its initial applications. The act would enable |
7 | replacement of a renewable energy resource without study or system improvement. |
8 | This act would take effect upon passage. |
======== | |
LC001675 | |
======== | |
| LC001675 - Page 5 of 5 |