2017 -- S 0758 | |
======== | |
LC002354 | |
======== | |
STATE OF RHODE ISLAND | |
IN GENERAL ASSEMBLY | |
JANUARY SESSION, A.D. 2017 | |
____________ | |
A N A C T | |
RELATING TO PUBLIC PROPERTY AND WORKS -- LABOR AND PAYMENT OF DEBTS | |
BY CONTRACTORS | |
| |
Introduced By: Senators Lombardi, and McCaffrey | |
Date Introduced: April 12, 2017 | |
Referred To: Senate Judiciary | |
It is enacted by the General Assembly as follows: | |
1 | SECTION 1. Chapter 37-13 of the General Laws entitled "Labor and Payment of Debts |
2 | by Contractors" is hereby amended by adding thereto the following section: |
3 | 37-13-5.1. Payments to subcontractors. |
4 | (a) Definitions: |
5 | (1) Subcontractor defined. For the purposes of this chapter, "subcontractor" means a |
6 | person or entity that has entered into a contract with a contractor as defined in §37-13-2 to |
7 | provide a portion of the work or service on a project which the contractor has agreed to perform, |
8 | and who has been approved by the awarding authority in writing as a person or entity performing |
9 | labor or furnishing of materials on a public works project as defined in §37-13-1. |
10 | (2) Substantial performance defined. For the purposes of this chapter, "substantial |
11 | performance" means an honest endeavor in good faith by one party to perform that party's |
12 | obligations under a contract, when the results of that party's endeavor are beneficial to and are |
13 | retained by the other party. |
14 | (b) Periodic payments to subcontractors. Upon receipt of a periodic payment from an |
15 | awarding authority, a contractor shall pay to each subcontractor any amount owed to the |
16 | subcontractor for labor performed or materials provided, less any amount specified in any court |
17 | proceeding barring such payment or any amount claimed due from the subcontractor to the |
18 | contractor. |
| |
1 | (c) Payment upon substantial completion. Not later than the sixty-five (65) days after |
2 | each subcontractor substantially completes its work in accordance with the plans and |
3 | specifications, the entire balance due under the subcontract, less amounts retained by the |
4 | awarding authority as the estimated cost of completing any incomplete or unsatisfactory items of |
5 | the subcontractor's work, shall be due to the subcontractor; and the awarding authority shall pay |
6 | that amount to the contractor, Upon receipt of payments for labor or materials provided by a |
7 | subcontractor, the contractor shall pay to that subcontractor the full amount received from the |
8 | awarding authority less any amount specified in any court proceedings barring such payment or |
9 | any amount claimed due from the subcontractor by the contractor. |
10 | (d) Demand for direct payment. If within seventy (70) days after the subcontractor has |
11 | substantially completed the subcontract work, the subcontractor has not received from the |
12 | contractor the balance due under the subcontract, including any amount due for extra labor and |
13 | materials furnished to the contractor pursuant to a change order, less any amount retained by the |
14 | awarding authority as the estimated cost of completing any incomplete and unsatisfactory items |
15 | of the subcontractor's work, the subcontractor may demand direct payment of that balance from |
16 | the awarding authority. The demand shall be by a sworn statement sent by certified mail to the |
17 | awarding authority, and a copy shall be sent by certified mail to the contractor at the same time. |
18 | The demand shall contain an itemized accounting of the balance due under the subcontract and a |
19 | statement of the status of completion of the subcontract work. Within ten (10) days after receipt |
20 | of the demand for direct payment, the contractor shall submit a reply to the demand by sworn |
21 | statement to the awarding authority by certified mail and a copy shall be sent by certified mail to |
22 | the subcontractor. The reply shall contain an itemized accounting of payments made to the |
23 | subcontractor, amounts owed to the subcontractor, including any amount due for extra labor and |
24 | materials furnished to the contractor, and the amount due for each claim made by the contractor |
25 | against the subcontractor. |
26 | (e) Direct payment by awarding authority. Within fifteen (15) days after receipt of the |
27 | demand by the awarding authority, but in no event prior to the seventieth day after substantial |
28 | completion of the subcontract work, the awarding authority shall make direct payment to the |
29 | subcontractor of the balance due under the subcontract including any amount due for extra labor |
30 | and materials furnished to the contractor pursuant to a change order, less any amount: |
31 | (1) Retained by the awarding authority as the estimated cost of completing any |
32 | outstanding work or unsatisfactory items of work; |
33 | (2) Specified in any court proceedings barring such payment; or |
34 | (3) Disputed by the contractor in the sworn reply; provided, however, that the awarding |
| LC002354 - Page 2 of 6 |
1 | authority shall not deduct from a direct payment any amount as provided in this section if the |
2 | reply is not work to or for which the sworn reply does not contain an itemized accounting as |
3 | required by 37-13-5.1(d). The awarding authority shall make further direct payments to the |
4 | subcontractor after the removal of the basis for deductions from direct payments made as |
5 | provided in subsections (e)(i) and (e)(ii) of this section. |
6 | (f) Deposit of deducted amount. The awarding authority shall withhold an amount equal |
7 | to the disputed amount as determined by 37-13-5.1(g) unless both parties agree to release the |
8 | disputed amount to a mutually agreed upon escrow agent. If the monies are released to an escrow |
9 | agent, the agent shall keep an accounting of said monies and shall not release the monies to either |
10 | party until directed by a court of competent jurisdiction or until a signed settlement agreement is |
11 | provided to the agent including a release from liability from all parties. The agent shall send a |
12 | copy of the court order or the settlement agreement to the awarding authority. |
13 | (g) Authority discharged. All direct payments and all deductions from demands for direct |
14 | payments deposited in an interest bearing account pursuant to §37-13-5.1(f) shall be deducted |
15 | from amounts payable to the contractor at the time of receipt of a demand for direct payment |
16 | from a subcontractor and out of amounts which later become payable to the contractor and in the |
17 | order of receipt of such demands from subcontractors. All direct payments shall discharge the |
18 | obligation of the awarding authority to the contractor to the extent of such payment. |
19 | (h) Priority over creditors. The awarding authority shall deduct from payments to a |
20 | contractor amounts which, together with the deposits pursuant to §37-13-5.1(f) are sufficient to |
21 | satisfy all unpaid balances of demands for direct payment received from subcontractors. All such |
22 | amounts shall be earmarked for such direct payments, and the subcontractors shall have a right in |
23 | such deductions prior to any claims against such amounts by creditors of the contractor. |
24 | (i) Demand for unpaid periodic payments. If the subcontractor does not receive periodic |
25 | payment as provided in §37-13-5.1(b), or if the contractor does not submit a periodic estimate for |
26 | the value of the labor or materials performed or furnished by the subcontractor and the |
27 | subcontractor does not receive payment for same when due less the deductions provided for in |
28 | §37-13-5.1(b), the subcontractor may demand direct payment by following the procedure set forth |
29 | in §37-13-5.1(d) and the contractor may file a sworn statement as provided in that subsection. A |
30 | demand, made after the first day of the month following that for which the subcontractor |
31 | performed or furnished the labor and materials, for which the subcontractor seeks payment shall |
32 | be valid even if mailed prior to the time payment was due on a periodic estimate from the |
33 | contractor. Thereafter the awarding authority shall proceed as provided in §37-13-5.1(e). |
34 | (j) No assignment of rights. Any assignment by a subcontractor of the rights under this |
| LC002354 - Page 3 of 6 |
1 | section to a surety company furnishing a bond under the provisions of §37-13-14 shall be invalid. |
2 | The assignment or subrogation rights of the surety to amounts included in a demand for direct |
3 | payment which are in the possession of the awarding authority or which are on deposit pursuant |
4 | §37-13-5.1(h) shall be subordinate to the rights of all subcontractors who are entitled to be paid |
5 | under this section and who have not been paid in full. |
6 | (k) Petition in equity. A contractor or a subcontractor shall enforce a claim to any portion |
7 | of the amount of a demand for direct payment deposited in accordance with §37-13-5.1(f) by a |
8 | petition in equity in the superior court against the other, and the awarding authority shall be a |
9 | necessary party. A subcontractor shall enforce a claim for direct payment or a right to require a |
10 | deposit as provided in §37-13-5.1(f) by a petition in equity in the superior court against the |
11 | awarding authority, and the contractor shall not be a necessary party. Upon motion of any party, |
12 | the court shall advance for speedy trial any petition filed as provided for in this section. The court |
13 | shall enter an interlocutory decree upon which execution shall issue for any part of a claim found |
14 | due and, upon motion of any party, shall advance for speedy trial the petition to collect the |
15 | remainder of the claim. Any party aggrieved by such interlocutory decree shall have the right to |
16 | appeal therefrom as from a final decree. The court shall not consolidate for trial the petition of |
17 | any subcontractor with the petition of one or more subcontractors on the same general contract |
18 | unless the court finds that a substantial portion of the evidence of the same events during the |
19 | course of construction (other than the fact that the claims sought to be consolidated arise under |
20 | the same general contract) is applicable to the petitions sought to be consolidated and that such |
21 | consolidation will prevent unnecessary duplication of evidence. A decree in any such proceeding |
22 | shall not include interest on the disputed amount deposited in excess of the interest earned for the |
23 | period of any such deposit. |
24 | SECTION 2. Section 37-12-2 of the General Laws in Chapter 37-12 entitled |
25 | "Contractors' Bonds" is hereby amended to read as follows: |
26 | 37-12-2. Rights of persons furnishing labor and materials. |
27 | (a) Right of action. Every person who shall have performed labor and every person who |
28 | shall have furnished or supplied labor, material, or equipment in the prosecution of the work |
29 | provided for in the contract, in respect of which a payment bond is furnished under § 37-12-1, |
30 | and who has not been paid in full therefor before the expiration of a period of ninety (90) days |
31 | after the day on which the last of the labor was performed or furnished by him or her, or material |
32 | or equipment furnished or supplied by him or her for which a claim is made, shall have the right |
33 | to sue on the payment bond for the amount, or the balance thereof, unpaid at the time of |
34 | institution of the suit and to prosecute the action to final execution and judgment for the sum or |
| LC002354 - Page 4 of 6 |
1 | sums justly due him or her; provided, however, that any person having direct contractual |
2 | relationship with a subcontractor but no contractual relationship express or implied with the |
3 | contractor furnishing the payment bond shall have a right of action upon the payment bond upon |
4 | giving written notice to the contractor within ninety (90) days from the date on which the person |
5 | furnished or performed the last of the labor, or furnished or supplied the last of the material or |
6 | equipment for which the claim is made, stating with substantial accuracy the amount claimed and |
7 | the name of the party to whom the labor was furnished or performed or the material or equipment |
8 | was furnished or supplied. The notice shall be served by mailing the same by certified mail, |
9 | postage prepaid, in an envelope addressed to the contractor at any place he or she maintains an |
10 | office, conducts his or her business, or his or her residence. |
11 | (b) Attorneys' fees and costs. A judgment, decree or other award in favor of any claimant |
12 | under this section shall include reasonable attorneys' fees and costs. |
13 | SECTION 3. This act shall take effect upon passage. |
======== | |
LC002354 | |
======== | |
| LC002354 - Page 5 of 6 |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO PUBLIC PROPERTY AND WORKS -- LABOR AND PAYMENT OF DEBTS | |
BY CONTRACTORS | |
*** | |
1 | This act would add to the protection afforded to subcontractors on public work contracts, |
2 | and would provide for the award of reasonable attorneys' fees and costs. |
3 | This act would take effect upon passage. |
======== | |
LC002354 | |
======== | |
| LC002354 - Page 6 of 6 |