2018 -- H 7677

========

LC004622

========

     STATE OF RHODE ISLAND

IN GENERAL ASSEMBLY

JANUARY SESSION, A.D. 2018

____________

A N   A C T

RELATING TO PUBLIC UTILITIES AND CARRIERS -- DISTRIBUTED GENERATION

INTERCONNECTION

     

     Introduced By: Representatives Solomon, Johnston, Shanley, Casey, and Coughlin

     Date Introduced: February 15, 2018

     Referred To: House Corporations

     It is enacted by the General Assembly as follows:

1

     SECTION 1. Sections 39-26.3-3 and 39-26.3-4.1 of the General Laws in Chapter 39-26.3

2

entitled "Distributed Generation Interconnection" are hereby amended to read as follows:

3

     39-26.3-3. Application process.

4

     (a) The application process set out in this section shall be applicable to electric

5

distribution companies thirty (30) days after the enactment of this chapter.

6

     (b) An applicant for a renewable distributed generation interconnection must submit an

7

application to the electric distribution company for an impact study, including a request for an

8

estimate of the cost of interconnecting the renewable distributed generation resource to the

9

distribution system. The applicant may request a feasibility study prior to requesting an impact

10

study, but the applicant is not required to do so and may submit an application for an impact

11

study without having obtained a feasibility study. The distribution company shall follow the

12

schedule below for all applications.

13

     (c) Upon receipt of a completed application requesting a feasibility study and receipt of

14

the applicable feasibility study fee, the electric distribution company shall provide a feasibility

15

study to the applicant within thirty (30) days.

16

     (d) Upon receipt of a completed application requesting an impact study and receipt of the

17

applicable impact study fee, the electric distribution company shall provide an impact study

18

within ninety (90) sixty (60) days.

 

1

     (e) In anticipation of the electric distribution company needing to add resources that are

2

not currently in Rhode Island or covered in rates, to provide the necessary services to advance the

3

aggressive goals and objectives set forth in title 39, the electric distribution company shall be

4

authorized to add up to two (2) five (5) incremental employee and/or subcontracted consultant

5

resources located in Rhode Island that shall be primarily dedicated to servicing Rhode Island

6

applicants and customers in connection with net metering and the development of distributed

7

generation resources, including the requisite resources to perform impact and feasibility studies

8

for distributed generation interconnections and to assure that feasibility studies and impact

9

studies, as well as other engineering activity necessary to facilitate the completion of distributed

10

generation projects in Rhode Island are implemented and delivered on a timely basis. Prior to new

11

rates going into effect following the company's next general rate case filing, the cost of such

12

incremental employee resources shall be recovered through rates on an annual basis through an

13

annual reconciliation mechanism, provided that the total amount of fees collected from impact

14

studies and feasibility studies shall be netted against such costs. Only the cost of time and work

15

actually spent on Rhode Island renewable energy project matters shall be included in such annual

16

reconciliation. The commission shall have the authority to review these positions in the electric

17

distribution company's next general rate case as a cost of service in the same manner as it reviews

18

all other expenses in a rate case to determine whether they should continue. Nothing contained in

19

this section shall preclude the electric distribution company from adding additional resources,

20

subject to commission approval.

21

     (f) Notwithstanding any other provision of this chapter, the application process and fees

22

set forth in this chapter apply only to interconnections to the distribution system by renewable

23

distributed generation resources. To the extent that a renewable generation resource seeks an

24

interconnection to the transmission system and such interconnection request is governed by rules

25

and regulations under the exclusive jurisdiction of the federal energy regulatory commission, the

26

provisions of this chapter shall not apply.

27

     (g) The rules and fees established in this chapter shall be incorporated within the

28

applicable "Standards for Interconnection of Distributed Generation" approved by the

29

commission.

30

     39-26.3-4.1. Interconnection standards.

31

     (a) The electric distribution company may only charge an interconnecting, renewable-

32

energy customer for any system modifications to its electric power system specifically necessary

33

for and directly related to the interconnection. The electric distribution company shall provide a

34

final accounting to the renewable energy customer within sixty (60) days after permission to

 

LC004622 - Page 2 of 6

1

operate has been received from the electric distribution company that includes the following:

2

     (1) A detailed accounting ledger for all costs, line item charges, including, but not limited

3

to, wages and benefits, consultants, materials, equipment, overhead allocations, and any and all

4

other charges that are funded by the renewable energy customer;

5

     (2) Costs, line item charges and support documents that provide clear verification for

6

each charge (third-party invoices; wages and benefit reports; overhead allocation reports;

7

consultant invoices; material and equipment invoices; and the like).

8

     (b) If the public utilities commission determines that a specific system modification

9

benefiting other customers has been accelerated due to an interconnection request, it may order

10

the interconnecting customer to fund the modification subject to repayment of the depreciated

11

value of the modification as of the time the modification would have been necessary as

12

determined by the public utilities commission. Any system modifications benefiting other

13

customers shall be included in rates as determined by the public utilities commission.

14

     (c) If an interconnecting, renewable-energy customer is required to pay for system

15

modifications and a subsequent renewable-energy or commercial customer relies on those

16

modifications to connect to the distribution system within ten (10) years of the earlier

17

interconnecting, renewable-energy customer's payment, the subsequent customer will make a

18

prorated contribution toward the cost of the system modifications that will be credited to the

19

earlier interconnecting, renewable-energy customer as determined by the public utilities

20

commission.

21

     (d) An electric distribution company shall acknowledge to the interconnecting,

22

renewable-energy customer receipt of an application to initiate the interconnection process within

23

three (3) business days of receipt. The electric distribution company shall notify the

24

interconnecting, renewable-energy customer in writing within ten (10) business days of receipt

25

that the application is or is not complete and, if not, advise what is missing. Any disputes

26

regarding whether and when an application to initiate the interconnection process is complete

27

shall be resolved expeditiously at the public utilities commission. The maximum time allowed

28

between the date of the completed application and delivery of an executable interconnection

29

service agreement shall be one hundred seventy-five (175) ninety (90) calendar days or two

30

hundred (200) one hundred twenty (120) calendar days if a detailed study is required. All electric

31

distribution company system modifications must be completed by the date which is the later of:

32

(1) No longer than two hundred seventy (270) calendar days, or three hundred sixty (360)

33

calendar days if substation work is necessary, from the date of the electric distribution company's

34

receipt of the interconnecting, renewable-energy customer's executed interconnection service

 

LC004622 - Page 3 of 6

1

agreement; or (2) The interconnecting, renewable-energy customer's agreed upon extension of the

2

time between the execution of the interconnection service agreement and interconnection as set

3

forth in writing. All deadlines herein are subject to all payments being made in accordance with

4

the distributed generation interconnection tariff on file with the public utilities commission and

5

the interconnection service agreement. These system modification deadlines cannot be extended

6

due to customer delays in providing required information, all of which must be requested and

7

obtained before completion of the impact study. The deadlines for completion of system

8

modifications will be extended only to the extent of events that are clearly not under the control

9

of the electric distribution company, such as extended prohibitive weather, union work stoppage

10

or force majeure, or third-party delays, including, without limitation, delays due to ISO-NE

11

requirements not attributable to electric distribution company actions, and which cannot be

12

resolved despite commercially reasonable efforts. The electric distribution company shall notify

13

the customer of the start of any claimed deadline extension as soon as practicable, its cause and

14

when it concludes, all in writing. Any actual or indirect, incidental, special, consequential, or

15

punitive damages of any kind whatsoever that a court of competent jurisdiction orders the electric

16

distribution company to pay to an interconnecting, renewable-energy customer as a direct or

17

indirect result of the electric distribution company's failure to comply with the requirements of

18

this subsection shall be payable by its shareholders and may not be recovered from customers. ,

19

provided that the total amount of damages awarded for any and all such claims shall not exceed,

20

in the aggregate, an amount equal to the amount of the incentive the electric distribution company

21

would have earned as provided for in §§ 39-26.6-12(j)(3) and 39-26.1-4 in the year in which the

22

system modifications were required to be completed. In no event shall the The electric

23

distribution company shall be liable to the interconnecting, renewable-energy customer for any

24

indirect, incidental, special, consequential, or punitive damages of any kind whatsoever as a result

25

of the electric distribution company's failure to comply with this section. In addition to the

26

electric distribution company's liability to the interconnecting renewable energy customer the

27

division of public utilities and carriers shall open a full investigation for each event of non-

28

compliance with the policy objective herein and determine to levy a penalty for delays consistent

29

with §§ 39-2-27 and 39-2-28.

30

     (e) When an applicant (distributed generation developer) has two (2) or more

31

interconnection applications under assessment for separate renewable distributed generation

32

interconnection points by the electric distribution company at the same time and there are

33

redundant system upgrade costs listed on the impact study (Section 9.0 "Cost Estimate") the

34

redundant costs shall be apportioned to each application based on the AC weighted average size

 

LC004622 - Page 4 of 6

1

of each application. If, for any reason, one or more of the applicant's interconnections

2

applications are withdrawn or terminated, the remaining interconnection applications under

3

assessment shall be assessed the costs attributable to the terminated or withdrawn application and

4

be required to pay the cost difference within thirty (30) days. A withdrawal or termination of one

5

or more applications shall not extend the timetable set forth in § 39-26.3-4.1(d).

6

     (f) On or before September 1, 2017, the public utilities commission shall initiate a docket

7

to establish metrics for the electric distribution company's performance in meeting the time

8

frames set forth herein and in the distributed generation interconnection standards approved by

9

the public utilities commission. The public utilities commission may include incentives and

10

penalties in the performance metrics.

11

     (f)(g) The proposed interconnection of any new renewable energy resource that replaces

12

the same existing renewable energy resource of the same or less nameplate capacity that has been

13

in operation in the twelve (12) months preceding notification of such replacement shall be subject

14

to a sixty-day (60) review. The purpose of such sixty-day (60) review is to allow the electric

15

distribution company to determine whether any system modifications are required to support the

16

interconnection of the replacement renewable energy resource. If there is a need for system

17

modifications because of an interconnection policy change implemented by the electric

18

distribution company, then the system modification may be included in rates as determined by the

19

public utilities commission. If there is a need for system modifications only because of a change

20

in the rating or utility disturbance response that adversely affects the impact of the facility on the

21

distribution system, then the interconnecting, renewable-energy customer shall be responsible for

22

the cost of the system modifications.

23

     SECTION 2. This act shall take effect upon passage.

========

LC004622

========

 

LC004622 - Page 5 of 6

EXPLANATION

BY THE LEGISLATIVE COUNCIL

OF

A N   A C T

RELATING TO PUBLIC UTILITIES AND CARRIERS -- DISTRIBUTED GENERATION

INTERCONNECTION

***

1

     This act would reduce the time that an electric distribution company has to provide an

2

applicant for a renewable distributed generation interconnection impact study from ninety (90) to

3

sixty (60) days, authorize additional study to better serve applicants, and provide renewable

4

energy customers a final accounting of changes and costs.

5

     This act would take effect upon passage.

========

LC004622

========

 

LC004622 - Page 6 of 6