2018 -- H 7677 | |
======== | |
LC004622 | |
======== | |
STATE OF RHODE ISLAND | |
IN GENERAL ASSEMBLY | |
JANUARY SESSION, A.D. 2018 | |
____________ | |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS -- DISTRIBUTED GENERATION | |
INTERCONNECTION | |
| |
Introduced By: Representatives Solomon, Johnston, Shanley, Casey, and Coughlin | |
Date Introduced: February 15, 2018 | |
Referred To: House Corporations | |
It is enacted by the General Assembly as follows: | |
1 | SECTION 1. Sections 39-26.3-3 and 39-26.3-4.1 of the General Laws in Chapter 39-26.3 |
2 | entitled "Distributed Generation Interconnection" are hereby amended to read as follows: |
3 | 39-26.3-3. Application process. |
4 | (a) The application process set out in this section shall be applicable to electric |
5 | distribution companies thirty (30) days after the enactment of this chapter. |
6 | (b) An applicant for a renewable distributed generation interconnection must submit an |
7 | application to the electric distribution company for an impact study, including a request for an |
8 | estimate of the cost of interconnecting the renewable distributed generation resource to the |
9 | distribution system. The applicant may request a feasibility study prior to requesting an impact |
10 | study, but the applicant is not required to do so and may submit an application for an impact |
11 | study without having obtained a feasibility study. The distribution company shall follow the |
12 | schedule below for all applications. |
13 | (c) Upon receipt of a completed application requesting a feasibility study and receipt of |
14 | the applicable feasibility study fee, the electric distribution company shall provide a feasibility |
15 | study to the applicant within thirty (30) days. |
16 | (d) Upon receipt of a completed application requesting an impact study and receipt of the |
17 | applicable impact study fee, the electric distribution company shall provide an impact study |
18 | within ninety (90) sixty (60) days. |
| |
1 | (e) In anticipation of the electric distribution company needing to add resources that are |
2 | not currently in Rhode Island or covered in rates, to provide the necessary services to advance the |
3 | aggressive goals and objectives set forth in title 39, the electric distribution company shall be |
4 | authorized to add up to two (2) five (5) incremental employee and/or subcontracted consultant |
5 | resources located in Rhode Island that shall be primarily dedicated to servicing Rhode Island |
6 | applicants and customers in connection with net metering and the development of distributed |
7 | generation resources, including the requisite resources to perform impact and feasibility studies |
8 | for distributed generation interconnections and to assure that feasibility studies and impact |
9 | studies, as well as other engineering activity necessary to facilitate the completion of distributed |
10 | generation projects in Rhode Island are implemented and delivered on a timely basis. Prior to new |
11 | rates going into effect following the company's next general rate case filing, the cost of such |
12 | incremental employee resources shall be recovered through rates on an annual basis through an |
13 | annual reconciliation mechanism, provided that the total amount of fees collected from impact |
14 | studies and feasibility studies shall be netted against such costs. Only the cost of time and work |
15 | actually spent on Rhode Island renewable energy project matters shall be included in such annual |
16 | reconciliation. The commission shall have the authority to review these positions in the electric |
17 | distribution company's next general rate case as a cost of service in the same manner as it reviews |
18 | all other expenses in a rate case to determine whether they should continue. Nothing contained in |
19 | this section shall preclude the electric distribution company from adding additional resources, |
20 | subject to commission approval. |
21 | (f) Notwithstanding any other provision of this chapter, the application process and fees |
22 | set forth in this chapter apply only to interconnections to the distribution system by renewable |
23 | distributed generation resources. To the extent that a renewable generation resource seeks an |
24 | interconnection to the transmission system and such interconnection request is governed by rules |
25 | and regulations under the exclusive jurisdiction of the federal energy regulatory commission, the |
26 | provisions of this chapter shall not apply. |
27 | (g) The rules and fees established in this chapter shall be incorporated within the |
28 | applicable "Standards for Interconnection of Distributed Generation" approved by the |
29 | commission. |
30 | 39-26.3-4.1. Interconnection standards. |
31 | (a) The electric distribution company may only charge an interconnecting, renewable- |
32 | energy customer for any system modifications to its electric power system specifically necessary |
33 | for and directly related to the interconnection. The electric distribution company shall provide a |
34 | final accounting to the renewable energy customer within sixty (60) days after permission to |
| LC004622 - Page 2 of 6 |
1 | operate has been received from the electric distribution company that includes the following: |
2 | (1) A detailed accounting ledger for all costs, line item charges, including, but not limited |
3 | to, wages and benefits, consultants, materials, equipment, overhead allocations, and any and all |
4 | other charges that are funded by the renewable energy customer; |
5 | (2) Costs, line item charges and support documents that provide clear verification for |
6 | each charge (third-party invoices; wages and benefit reports; overhead allocation reports; |
7 | consultant invoices; material and equipment invoices; and the like). |
8 | (b) If the public utilities commission determines that a specific system modification |
9 | benefiting other customers has been accelerated due to an interconnection request, it may order |
10 | the interconnecting customer to fund the modification subject to repayment of the depreciated |
11 | value of the modification as of the time the modification would have been necessary as |
12 | determined by the public utilities commission. Any system modifications benefiting other |
13 | customers shall be included in rates as determined by the public utilities commission. |
14 | (c) If an interconnecting, renewable-energy customer is required to pay for system |
15 | modifications and a subsequent renewable-energy or commercial customer relies on those |
16 | modifications to connect to the distribution system within ten (10) years of the earlier |
17 | interconnecting, renewable-energy customer's payment, the subsequent customer will make a |
18 | prorated contribution toward the cost of the system modifications that will be credited to the |
19 | earlier interconnecting, renewable-energy customer as determined by the public utilities |
20 | commission. |
21 | (d) An electric distribution company shall acknowledge to the interconnecting, |
22 | renewable-energy customer receipt of an application to initiate the interconnection process within |
23 | three (3) business days of receipt. The electric distribution company shall notify the |
24 | interconnecting, renewable-energy customer in writing within ten (10) business days of receipt |
25 | that the application is or is not complete and, if not, advise what is missing. Any disputes |
26 | regarding whether and when an application to initiate the interconnection process is complete |
27 | shall be resolved expeditiously at the public utilities commission. The maximum time allowed |
28 | between the date of the completed application and delivery of an executable interconnection |
29 | service agreement shall be one hundred seventy-five (175) ninety (90) calendar days or two |
30 | hundred (200) one hundred twenty (120) calendar days if a detailed study is required. All electric |
31 | distribution company system modifications must be completed by the date which is the later of: |
32 | (1) No longer than two hundred seventy (270) calendar days, or three hundred sixty (360) |
33 | calendar days if substation work is necessary, from the date of the electric distribution company's |
34 | receipt of the interconnecting, renewable-energy customer's executed interconnection service |
| LC004622 - Page 3 of 6 |
1 | agreement; or (2) The interconnecting, renewable-energy customer's agreed upon extension of the |
2 | time between the execution of the interconnection service agreement and interconnection as set |
3 | forth in writing. All deadlines herein are subject to all payments being made in accordance with |
4 | the distributed generation interconnection tariff on file with the public utilities commission and |
5 | the interconnection service agreement. These system modification deadlines cannot be extended |
6 | due to customer delays in providing required information, all of which must be requested and |
7 | obtained before completion of the impact study. The deadlines for completion of system |
8 | modifications will be extended only to the extent of events that are clearly not under the control |
9 | of the electric distribution company, such as extended prohibitive weather, union work stoppage |
10 | or force majeure, or third-party delays, including, without limitation, delays due to ISO-NE |
11 | requirements not attributable to electric distribution company actions, and which cannot be |
12 | resolved despite commercially reasonable efforts. The electric distribution company shall notify |
13 | the customer of the start of any claimed deadline extension as soon as practicable, its cause and |
14 | when it concludes, all in writing. Any actual or indirect, incidental, special, consequential, or |
15 | punitive damages of any kind whatsoever that a court of competent jurisdiction orders the electric |
16 | distribution company to pay to an interconnecting, renewable-energy customer as a direct or |
17 | indirect result of the electric distribution company's failure to comply with the requirements of |
18 | this subsection shall be payable by its shareholders and may not be recovered from customers. , |
19 | provided that the total amount of damages awarded for any and all such claims shall not exceed, |
20 | in the aggregate, an amount equal to the amount of the incentive the electric distribution company |
21 | would have earned as provided for in §§ 39-26.6-12(j)(3) and 39-26.1-4 in the year in which the |
22 | system modifications were required to be completed. In no event shall the The electric |
23 | distribution company shall be liable to the interconnecting, renewable-energy customer for any |
24 | indirect, incidental, special, consequential, or punitive damages of any kind whatsoever as a result |
25 | of the electric distribution company's failure to comply with this section. In addition to the |
26 | electric distribution company's liability to the interconnecting renewable energy customer the |
27 | division of public utilities and carriers shall open a full investigation for each event of non- |
28 | compliance with the policy objective herein and determine to levy a penalty for delays consistent |
29 | with §§ 39-2-27 and 39-2-28. |
30 | (e) When an applicant (distributed generation developer) has two (2) or more |
31 | interconnection applications under assessment for separate renewable distributed generation |
32 | interconnection points by the electric distribution company at the same time and there are |
33 | redundant system upgrade costs listed on the impact study (Section 9.0 "Cost Estimate") the |
34 | redundant costs shall be apportioned to each application based on the AC weighted average size |
| LC004622 - Page 4 of 6 |
1 | of each application. If, for any reason, one or more of the applicant's interconnections |
2 | applications are withdrawn or terminated, the remaining interconnection applications under |
3 | assessment shall be assessed the costs attributable to the terminated or withdrawn application and |
4 | be required to pay the cost difference within thirty (30) days. A withdrawal or termination of one |
5 | or more applications shall not extend the timetable set forth in § 39-26.3-4.1(d). |
6 | (f) On or before September 1, 2017, the public utilities commission shall initiate a docket |
7 | to establish metrics for the electric distribution company's performance in meeting the time |
8 | frames set forth herein and in the distributed generation interconnection standards approved by |
9 | the public utilities commission. The public utilities commission may include incentives and |
10 | penalties in the performance metrics. |
11 | (f)(g) The proposed interconnection of any new renewable energy resource that replaces |
12 | the same existing renewable energy resource of the same or less nameplate capacity that has been |
13 | in operation in the twelve (12) months preceding notification of such replacement shall be subject |
14 | to a sixty-day (60) review. The purpose of such sixty-day (60) review is to allow the electric |
15 | distribution company to determine whether any system modifications are required to support the |
16 | interconnection of the replacement renewable energy resource. If there is a need for system |
17 | modifications because of an interconnection policy change implemented by the electric |
18 | distribution company, then the system modification may be included in rates as determined by the |
19 | public utilities commission. If there is a need for system modifications only because of a change |
20 | in the rating or utility disturbance response that adversely affects the impact of the facility on the |
21 | distribution system, then the interconnecting, renewable-energy customer shall be responsible for |
22 | the cost of the system modifications. |
23 | SECTION 2. This act shall take effect upon passage. |
======== | |
LC004622 | |
======== | |
| LC004622 - Page 5 of 6 |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS -- DISTRIBUTED GENERATION | |
INTERCONNECTION | |
*** | |
1 | This act would reduce the time that an electric distribution company has to provide an |
2 | applicant for a renewable distributed generation interconnection impact study from ninety (90) to |
3 | sixty (60) days, authorize additional study to better serve applicants, and provide renewable |
4 | energy customers a final accounting of changes and costs. |
5 | This act would take effect upon passage. |
======== | |
LC004622 | |
======== | |
| LC004622 - Page 6 of 6 |