1 | SECTION 1. Chapter 39-1 of the General Laws entitled "Public Utilities Commission" is |
2 | hereby amended by adding thereto the following section: |
3 | 39-1-63. Burying of electric transmission power lines. |
4 | (a) Whenever a residential customer of an electric transmission company loses electrical |
5 | power for a period of ninety-six (96) consecutive hours or more, the electric transmission |
6 | company shall create and execute a plan to bury the electric transmission lines servicing that |
7 | residential customer within two (2) years of the loss of electrical power. |
8 | (b) The provisions of this section shall not apply if the loss of electrical power was |
9 | caused by the action or inaction of the residential customer, or if the electrical power to the |
10 | residence was terminated by the customer or the electric transmission company. |
11 | SECTION 2. This act shall take effect upon passage. |
======== | |
LC004291 | |
======== | |
| |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS - PUBLIC UTILITIES COMMISSION | |
*** | |
1 | This act would require an electric utility to bury power lines in the event of a residential |
2 | power outage lasting ninety-six (96) consecutive hours or more, unless the outage was caused by |
3 | the resident. |
4 | This act would take effect upon passage. |
======== | |