2020 -- H 8011 | |
======== | |
LC005271 | |
======== | |
STATE OF RHODE ISLAND | |
IN GENERAL ASSEMBLY | |
JANUARY SESSION, A.D. 2020 | |
____________ | |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS --DISTRIBUTED GENERATION | |
INTERCONNECTION | |
| |
Introduced By: Representatives McKiernan, Bennett, Almeida, Millea, and Serpa | |
Date Introduced: March 13, 2020 | |
Referred To: House Corporations | |
It is enacted by the General Assembly as follows: | |
1 | SECTION 1. Sections 39-26.3-4 and 39-26.3-4.1 of the General Laws in Chapter 39-26.3 |
2 | entitled "Distributed Generation Interconnection" are hereby amended to read as follows: |
3 | 39-26.3-4. Study cost fees. |
4 | (a) After thirty (30) days from the enactment of this chapter until the end of calendar year |
5 | 2012, the feasibility study fee shall be in accordance with the schedule set forth below: |
6 | (1) Residential applicants for interconnections of UL 1741.1 approved renewable |
7 | distributed generation that is twenty-five kilowatts (25 kw) or less: zero dollars ($0). |
8 | (2) Residential applicants for interconnections of UL 1741.1 approved renewable |
9 | distributed generation that is greater than twenty-five kilowatts (25 kw): fifty dollars ($50.00). |
10 | (3) Non-residential applicants for interconnections of UL 1741.1 approved renewable |
11 | distributed generation that is one hundred kilowatts (100 kw) or less: one hundred dollars ($100). |
12 | (4) Non-residential applicants for interconnections of UL 1741.1 approved renewable |
13 | distributed generation that is two hundred fifty kilowatts (250 kw) or less: three hundred dollars |
14 | ($300). |
15 | (5) Non-residential applicants for interconnections of renewable distributed generation that |
16 | is greater than two hundred fifty kilowatts (250 kw), up to one megawatt: one thousand dollars |
17 | ($1,000). |
18 | (6) Non-residential applicants for interconnections of renewable distributed generation |
| |
1 | greater than one megawatt: two thousand five hundred dollars ($2,500). |
2 | Beginning January 1, 2013 and for every year thereafter, the commission shall set a new |
3 | fee schedule that is no less than what is specified herein. The purpose of the fee schedule is to |
4 | provide a disincentive to applicants contemplating a renewable distributed generation project from |
5 | requesting order of magnitude estimates unless they are serious about pursuing such projects, and |
6 | to prevent the electric distribution company from charging more than it actually costs to conduct |
7 | such studies with all due efficiency. |
8 | (b) After thirty (30) days from the enactment of this chapter until the end of calendar year |
9 | 2012, the impact study fee shall be in accordance with the schedule set forth below: |
10 | (1) Residential applicants for interconnections of UL 1741.1 approved renewable |
11 | distributed generation that is twenty-five kilowatts (25 kw) or less: zero dollars ($0). |
12 | (2) Residential applicants for interconnections of UL 1741.1 approved renewable |
13 | distributed generation that is greater than twenty-five kilowatts (25 kw): one hundred dollars |
14 | ($100). |
15 | (3) Non-residential applicants for interconnections of UL 1741.1 approved renewable |
16 | distributed generation that is one hundred kilowatts (100 kw) or less: five hundred dollars ($500) |
17 | (4) Non-residential applicants for interconnections of UL 1741.1 approved renewable |
18 | distributed generation that is two hundred fifty kilowatts (250 kw) or less: one thousand five |
19 | hundred dollars ($1,500). |
20 | (5) Non-residential applicants for interconnections of renewable distributed generation that |
21 | is greater than two hundred fifty kilowatts (250 kw), up to one megawatt: five thousand dollars |
22 | ($5,000). |
23 | (6) Non-residential applicants for interconnections of renewable distributed generation |
24 | greater than one megawatt: actual cost or ten thousand dollars ($10,000), whichever is less. |
25 | Beginning January 1, 2013 and for every year thereafter, the commission shall set a new |
26 | fee schedule that is no less than what is specified herein. The purpose of the impact study fee |
27 | schedule is to assure that an applicant is responsible for paying a reasonable amount of the cost of |
28 | the study in advance of installing the distributed generation, but that the advance cost is justified |
29 | and is not so high as to discourage an applicant from pursuing a project. |
30 | (c) To the extent that an impact study fee established under this section does not cover the |
31 | reasonable cost of an impact study for a given non-residential project that commences operation, |
32 | the balance of such costs shall be recovered from such applicant through billings after the project |
33 | is online. The electric distribution company may, at its sole election, offset net-metering credits or |
34 | any standard contract payments until the full fee(s) is reimbursed, if it finds it administratively |
| LC005271 - Page 2 of 8 |
1 | convenient to use that means of billing for the balance of the fee for a given project. |
2 | (d) The electric distribution company shall report the total number of interconnection |
3 | studies and its total charges to conduct feasibility and impact studies on each individual circuit in |
4 | Rhode Island to the independent interconnection ombudsman and to the division of public utilities |
5 | and carriers and to the public utilities commission no later than October 30, 2020, and update that |
6 | report every six (6) months. The electric distribution company shall not charge more than it cost to |
7 | conduct any interconnection studies, shall not charge for time spent studying feasibility or impact |
8 | that can be assessed based on prior studies, and shall not charge a customer for any time spent |
9 | responding to disputes related to its studies. |
10 | 39-26.3-4.1. Interconnection standards. |
11 | (a) The electric distribution company may only charge an interconnecting, renewable- |
12 | energy customer for any system modifications to its electric power distribution system specifically |
13 | necessary for and directly related to the interconnection. Transmission system improvements are |
14 | administered by ISO-NE pursuant to Federal Energy Regulatory Commission requirements as |
15 | applicable to renewable energy customers subject to federal jurisdiction. The company will provide |
16 | an industry standard estimate-level detailed audit and line item budget account of its actual cost to |
17 | the interconnecting customer with every cost estimate it issues and within ninety days of |
18 | completing any system modifications, always including any and all supporting records and |
19 | documentation. |
20 | (b) If the public utilities commission determines that a specific system modification |
21 | benefiting other customers has been accelerated due to an interconnection request, it may order the |
22 | interconnecting customer to fund the modification subject to repayment of the depreciated value of |
23 | the modification as of the time the modification would have been necessary as determined by the |
24 | public utilities commission. Any system modifications benefiting other customers shall be included |
25 | in rates as determined by the public utilities commission. |
26 | (c) If an interconnecting, renewable-energy customer is required to pay for system |
27 | modifications and a subsequent renewable-energy or commercial customer relies on those |
28 | modifications to connect to the distribution system within ten (10) years of the earlier |
29 | interconnecting, renewable-energy customer's payment, the subsequent customer will make a |
30 | prorated contribution toward the cost of the system modifications that will be credited to the earlier |
31 | interconnecting, renewable-energy customer as determined by the public utilities commission. |
32 | (d) An electric distribution company shall acknowledge to the interconnecting, renewable- |
33 | energy customer receipt of an application to initiate the interconnection process within three (3) |
34 | business days of receipt. The electric distribution company shall notify the interconnecting, |
| LC005271 - Page 3 of 8 |
1 | renewable-energy customer in writing within ten (10) business days of receipt that the application |
2 | is or is not complete and, if not, advise what is missing. of any and all elements of the application |
3 | that are materially incomplete within the ten (10) business days. Once the incomplete items that are |
4 | material to the interconnection process are addressed, the electric distribution company will |
5 | conduct a supplemental completeness review and application screens within no more than five (5) |
6 | days, notifying the applicant which interconnection process will be followed and whether their |
7 | application is still materially incomplete or deficient and providing a complete and specific list of |
8 | any and all incomplete items or deficiencies and provide specific detailed instructions or |
9 | recommendations on why items are deficient and how to correct any remaining deficiencies in a |
10 | form that enables the applicant to fully address them. Once all materially deficient items are then |
11 | addressed, the electric distribution company will issue a final decision on all screens and on which |
12 | interconnection process will be followed within two (2) days. As long as the interconnecting |
13 | customer provides all requested information within ten (10) days of the request, the interconnection |
14 | deadlines in this section will not be extended. The electric distribution company shall maintain an |
15 | example of a complete and current model interconnection application with all required attachments |
16 | and supplemental information in an easily accessible location on its website for ease of reference, |
17 | which shall be updated within five (5) calendar days of any update to any of the electric distribution |
18 | company’s technical standards or specifications for interconnection as addressed in subsection (h) |
19 | of this section. Any disputes regarding whether and when an application to initiate the |
20 | interconnection process is complete shall be resolved expeditiously at the public utilities |
21 | commission. The maximum time allowed between the date of the completed application and |
22 | delivery of an executable interconnection service agreement shall be one hundred seventy-five |
23 | (175) calendar days or two hundred (200) calendar days if a detailed study is required. All electric |
24 | distribution company system modifications must be completed by the date which is the later of: |
25 | (1) No longer than two hundred seventy (270) calendar days, or three hundred sixty (360) |
26 | calendar days if substation work is necessary, from the date of the electric distribution company's |
27 | receipt of the interconnecting, renewable-energy customer's executed interconnection service |
28 | agreement; or |
29 | (2) The interconnecting, renewable-energy customer's agreed upon written request for |
30 | extension of the time between the execution of the interconnection service agreement and |
31 | interconnection, as set forth agreed to by the electric distribution company in writing. All deadlines |
32 | herein are subject to all payments being made in accordance with the distributed generation |
33 | interconnection tariff on file with the public utilities commission and the interconnection service |
34 | agreement. These system modification deadlines cannot be extended due to customer delays in |
| LC005271 - Page 4 of 8 |
1 | providing required information, all of which must be requested and obtained within the time period |
2 | required before completion of the impact study. The deadlines for completion of system |
3 | modifications will be extended only to the extent of events that are clearly not under the control of |
4 | the electric distribution company, such as extended prohibitive weather, union work stoppage or |
5 | force majeure, or delays directly attributable to third-party delays, including, without limitation, |
6 | delays due to parties other than ISO-NE, requirements documented in writing, that are not |
7 | attributable to electric distribution company actions, and which cannot be resolved despite |
8 | commercially reasonable efforts. ISO-NE administers its own interconnection studies and |
9 | requirements for its jurisdictional facilities and its requirements are not cause for delay of a |
10 | distribution system interconnection. The electric distribution company shall notify the customer in |
11 | writing of the start of any claimed deadline extension as soon as practicable, its cause and when it |
12 | concludes, all in writing. and within five (5) calendar days of occurrence, to allow for customer |
13 | intervention and involvement, shall inform the customer of the cause and expected length of the |
14 | delay, and shall provide a detailed written explanation and documentation of such cause. The |
15 | electric distribution company shall respond within five (5) calendar days in writing to a customer’s |
16 | request for additional information and documents relating to the cause of the delay and the expected |
17 | length of the delay. Any actual, consequential, indirect, incidental or special damages that a court |
18 | of competent jurisdiction orders the electric distribution company to pay to incurred by an |
19 | interconnecting, renewable-energy customer as a direct result of the electric distribution company's |
20 | failure to comply with the requirements of this subsection shall be payable to the customer by it’s |
21 | the electric distribution company shareholders and may not be recovered from customers, provided |
22 | that the total amount of damages awarded for any and all such claims shall not exceed, in the |
23 | aggregate, an amount equal to the amount of the incentive the electric distribution company would |
24 | have earned as provided for in §§ 39-26.6-12(j)(3) and 39-26.1-4 in the year in which the system |
25 | modifications were required to be completed. In no event shall the electric distribution company be |
26 | liable to the interconnecting, renewable-energy customer for any indirect, incidental, special, |
27 | consequential, or punitive damages of any kind whatsoever as a result of the electric distribution |
28 | company's failure to comply with this section. |
29 | (e) On or before September 1, 2017, the public utilities commission shall initiate a docket |
30 | to establish metrics for the electric distribution company's performance in meeting the time frames |
31 | set forth herein and in the distributed generation interconnection standards approved by the public |
32 | utilities commission. The public utilities commission may include incentives and penalties in the |
33 | performance metrics. |
34 | (f) The proposed interconnection of any new renewable energy resource that replaces the |
| LC005271 - Page 5 of 8 |
1 | same existing renewable energy resource of the same or less nameplate capacity that has been in |
2 | operation in the twelve (12) months preceding notification of such replacement shall be subject to |
3 | a sixty-day (60) review. The purpose of such sixty-day (60) review is to allow the electric |
4 | distribution company to determine whether any system modifications are required to support the |
5 | interconnection of the replacement renewable energy resource. If there is a need for system |
6 | modifications because of an interconnection policy change implemented by the electric distribution |
7 | company, then the system modification may be included in rates as determined by the public |
8 | utilities commission. If there is a need for system modifications only because of a change in the |
9 | rating or utility disturbance response that adversely affects the impact of the facility on the |
10 | distribution system, then the interconnecting, renewable-energy customer shall be responsible for |
11 | the cost of the system modifications. |
12 | (g) The public utilities commission, in consultation with the office of energy resources, |
13 | shall appoint an independent ombudsman to oversee the distribution company’s administration of |
14 | interconnection to ensure that the interconnection process works efficiently to serve the purposes |
15 | of Rhode Island’s energy plan and policy. The appointed ombudsman shall oversee and supervise |
16 | any and all elements of the interconnection process including, but not limited to: providing dispute |
17 | resolution assistance upon written request by a party to a dispute under the interconnection tariff, |
18 | planning and management of infrastructure safety and reliability investments and all other |
19 | investments to ensure and facilitate access to the distribution system; processing of applications; |
20 | management of queue position; interactions with ISO-NE; implementation of system |
21 | modifications; and administration and exemptions to the interconnection tax. This position shall be |
22 | funded out of the electric distribution company’s interconnection study fees assessed to |
23 | interconnecting customers. |
24 | (h) The electric distribution company may not change its technical standards or |
25 | specifications for interconnection, as addressed in the Company’s ESB 756 where applicable to |
26 | Rhode Island “Requirements for Parallel Generation Connected to a National Grid owned EPS” or |
27 | otherwise, without approval of the public utilities commission and without properly publishing any |
28 | such changes to customers no less than thirty (30) days before implementation. Any changed |
29 | interconnection standards will not apply to interconnecting customers with complete |
30 | interconnection applications. |
31 | (i) The electric distribution company shall ensure that its interconnection application |
32 | process adequately informs its customers of the procedure to certify qualification and pursue the |
33 | Internal Revenue Service’s safe-harbor against the contribution in aid of construction tax, |
34 | exempting interconnections designed to send electricity to the electric distribution company. |
| LC005271 - Page 6 of 8 |
1 | SECTION 2. This act shall take effect thirty (30) days after passage. |
======== | |
LC005271 | |
======== | |
| LC005271 - Page 7 of 8 |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS --DISTRIBUTED GENERATION | |
INTERCONNECTION | |
*** | |
1 | This act would require the electric distribution company to report interconnection studies |
2 | and not charge more than actual costs for the studies. |
3 | This act would take effect thirty (30) days after passage. |
======== | |
LC005271 | |
======== | |
| LC005271 - Page 8 of 8 |