2020 -- H 8011

========

LC005271

========

     STATE OF RHODE ISLAND

IN GENERAL ASSEMBLY

JANUARY SESSION, A.D. 2020

____________

A N   A C T

RELATING TO PUBLIC UTILITIES AND CARRIERS --DISTRIBUTED GENERATION

INTERCONNECTION

     

     Introduced By: Representatives McKiernan, Bennett, Almeida, Millea, and Serpa

     Date Introduced: March 13, 2020

     Referred To: House Corporations

     It is enacted by the General Assembly as follows:

1

     SECTION 1. Sections 39-26.3-4 and 39-26.3-4.1 of the General Laws in Chapter 39-26.3

2

entitled "Distributed Generation Interconnection" are hereby amended to read as follows:

3

     39-26.3-4. Study cost fees.

4

     (a) After thirty (30) days from the enactment of this chapter until the end of calendar year

5

2012, the feasibility study fee shall be in accordance with the schedule set forth below:

6

     (1) Residential applicants for interconnections of UL 1741.1 approved renewable

7

distributed generation that is twenty-five kilowatts (25 kw) or less: zero dollars ($0).

8

     (2) Residential applicants for interconnections of UL 1741.1 approved renewable

9

distributed generation that is greater than twenty-five kilowatts (25 kw): fifty dollars ($50.00).

10

     (3) Non-residential applicants for interconnections of UL 1741.1 approved renewable

11

distributed generation that is one hundred kilowatts (100 kw) or less: one hundred dollars ($100).

12

     (4) Non-residential applicants for interconnections of UL 1741.1 approved renewable

13

distributed generation that is two hundred fifty kilowatts (250 kw) or less: three hundred dollars

14

($300).

15

     (5) Non-residential applicants for interconnections of renewable distributed generation that

16

is greater than two hundred fifty kilowatts (250 kw), up to one megawatt: one thousand dollars

17

($1,000).

18

     (6) Non-residential applicants for interconnections of renewable distributed generation

 

1

greater than one megawatt: two thousand five hundred dollars ($2,500).

2

     Beginning January 1, 2013 and for every year thereafter, the commission shall set a new

3

fee schedule that is no less than what is specified herein. The purpose of the fee schedule is to

4

provide a disincentive to applicants contemplating a renewable distributed generation project from

5

requesting order of magnitude estimates unless they are serious about pursuing such projects, and

6

to prevent the electric distribution company from charging more than it actually costs to conduct

7

such studies with all due efficiency.

8

     (b) After thirty (30) days from the enactment of this chapter until the end of calendar year

9

2012, the impact study fee shall be in accordance with the schedule set forth below:

10

     (1) Residential applicants for interconnections of UL 1741.1 approved renewable

11

distributed generation that is twenty-five kilowatts (25 kw) or less: zero dollars ($0).

12

     (2) Residential applicants for interconnections of UL 1741.1 approved renewable

13

distributed generation that is greater than twenty-five kilowatts (25 kw): one hundred dollars

14

($100).

15

     (3) Non-residential applicants for interconnections of UL 1741.1 approved renewable

16

distributed generation that is one hundred kilowatts (100 kw) or less: five hundred dollars ($500)

17

     (4) Non-residential applicants for interconnections of UL 1741.1 approved renewable

18

distributed generation that is two hundred fifty kilowatts (250 kw) or less: one thousand five

19

hundred dollars ($1,500).

20

     (5) Non-residential applicants for interconnections of renewable distributed generation that

21

is greater than two hundred fifty kilowatts (250 kw), up to one megawatt: five thousand dollars

22

($5,000).

23

     (6) Non-residential applicants for interconnections of renewable distributed generation

24

greater than one megawatt: actual cost or ten thousand dollars ($10,000), whichever is less.

25

     Beginning January 1, 2013 and for every year thereafter, the commission shall set a new

26

fee schedule that is no less than what is specified herein. The purpose of the impact study fee

27

schedule is to assure that an applicant is responsible for paying a reasonable amount of the cost of

28

the study in advance of installing the distributed generation, but that the advance cost is justified

29

and is not so high as to discourage an applicant from pursuing a project.

30

     (c) To the extent that an impact study fee established under this section does not cover the

31

reasonable cost of an impact study for a given non-residential project that commences operation,

32

the balance of such costs shall be recovered from such applicant through billings after the project

33

is online. The electric distribution company may, at its sole election, offset net-metering credits or

34

any standard contract payments until the full fee(s) is reimbursed, if it finds it administratively

 

LC005271 - Page 2 of 8

1

convenient to use that means of billing for the balance of the fee for a given project.

2

     (d) The electric distribution company shall report the total number of interconnection

3

studies and its total charges to conduct feasibility and impact studies on each individual circuit in

4

Rhode Island to the independent interconnection ombudsman and to the division of public utilities

5

and carriers and to the public utilities commission no later than October 30, 2020, and update that

6

report every six (6) months. The electric distribution company shall not charge more than it cost to

7

conduct any interconnection studies, shall not charge for time spent studying feasibility or impact

8

that can be assessed based on prior studies, and shall not charge a customer for any time spent

9

responding to disputes related to its studies.

10

     39-26.3-4.1. Interconnection standards.

11

     (a) The electric distribution company may only charge an interconnecting, renewable-

12

energy customer for any system modifications to its electric power distribution system specifically

13

necessary for and directly related to the interconnection. Transmission system improvements are

14

administered by ISO-NE pursuant to Federal Energy Regulatory Commission requirements as

15

applicable to renewable energy customers subject to federal jurisdiction. The company will provide

16

an industry standard estimate-level detailed audit and line item budget account of its actual cost to

17

the interconnecting customer with every cost estimate it issues and within ninety days of

18

completing any system modifications, always including any and all supporting records and

19

documentation.

20

     (b) If the public utilities commission determines that a specific system modification

21

benefiting other customers has been accelerated due to an interconnection request, it may order the

22

interconnecting customer to fund the modification subject to repayment of the depreciated value of

23

the modification as of the time the modification would have been necessary as determined by the

24

public utilities commission. Any system modifications benefiting other customers shall be included

25

in rates as determined by the public utilities commission.

26

     (c) If an interconnecting, renewable-energy customer is required to pay for system

27

modifications and a subsequent renewable-energy or commercial customer relies on those

28

modifications to connect to the distribution system within ten (10) years of the earlier

29

interconnecting, renewable-energy customer's payment, the subsequent customer will make a

30

prorated contribution toward the cost of the system modifications that will be credited to the earlier

31

interconnecting, renewable-energy customer as determined by the public utilities commission.

32

     (d) An electric distribution company shall acknowledge to the interconnecting, renewable-

33

energy customer receipt of an application to initiate the interconnection process within three (3)

34

business days of receipt. The electric distribution company shall notify the interconnecting,

 

LC005271 - Page 3 of 8

1

renewable-energy customer in writing within ten (10) business days of receipt that the application

2

is or is not complete and, if not, advise what is missing. of any and all elements of the application

3

that are materially incomplete within the ten (10) business days. Once the incomplete items that are

4

material to the interconnection process are addressed, the electric distribution company will

5

conduct a supplemental completeness review and application screens within no more than five (5)

6

days, notifying the applicant which interconnection process will be followed and whether their

7

application is still materially incomplete or deficient and providing a complete and specific list of

8

any and all incomplete items or deficiencies and provide specific detailed instructions or

9

recommendations on why items are deficient and how to correct any remaining deficiencies in a

10

form that enables the applicant to fully address them. Once all materially deficient items are then

11

addressed, the electric distribution company will issue a final decision on all screens and on which

12

interconnection process will be followed within two (2) days. As long as the interconnecting

13

customer provides all requested information within ten (10) days of the request, the interconnection

14

deadlines in this section will not be extended. The electric distribution company shall maintain an

15

example of a complete and current model interconnection application with all required attachments

16

and supplemental information in an easily accessible location on its website for ease of reference,

17

which shall be updated within five (5) calendar days of any update to any of the electric distribution

18

company’s technical standards or specifications for interconnection as addressed in subsection (h)

19

of this section. Any disputes regarding whether and when an application to initiate the

20

interconnection process is complete shall be resolved expeditiously at the public utilities

21

commission. The maximum time allowed between the date of the completed application and

22

delivery of an executable interconnection service agreement shall be one hundred seventy-five

23

(175) calendar days or two hundred (200) calendar days if a detailed study is required. All electric

24

distribution company system modifications must be completed by the date which is the later of:

25

     (1) No longer than two hundred seventy (270) calendar days, or three hundred sixty (360)

26

calendar days if substation work is necessary, from the date of the electric distribution company's

27

receipt of the interconnecting, renewable-energy customer's executed interconnection service

28

agreement; or

29

     (2) The interconnecting, renewable-energy customer's agreed upon written request for

30

extension of the time between the execution of the interconnection service agreement and

31

interconnection, as set forth agreed to by the electric distribution company in writing. All deadlines

32

herein are subject to all payments being made in accordance with the distributed generation

33

interconnection tariff on file with the public utilities commission and the interconnection service

34

agreement. These system modification deadlines cannot be extended due to customer delays in

 

LC005271 - Page 4 of 8

1

providing required information, all of which must be requested and obtained within the time period

2

required before completion of the impact study. The deadlines for completion of system

3

modifications will be extended only to the extent of events that are clearly not under the control of

4

the electric distribution company, such as extended prohibitive weather, union work stoppage or

5

force majeure, or delays directly attributable to third-party delays, including, without limitation,

6

delays due to parties other than ISO-NE, requirements documented in writing, that are not

7

attributable to electric distribution company actions, and which cannot be resolved despite

8

commercially reasonable efforts. ISO-NE administers its own interconnection studies and

9

requirements for its jurisdictional facilities and its requirements are not cause for delay of a

10

distribution system interconnection. The electric distribution company shall notify the customer in

11

writing of the start of any claimed deadline extension as soon as practicable, its cause and when it

12

concludes, all in writing. and within five (5) calendar days of occurrence, to allow for customer

13

intervention and involvement, shall inform the customer of the cause and expected length of the

14

delay, and shall provide a detailed written explanation and documentation of such cause. The

15

electric distribution company shall respond within five (5) calendar days in writing to a customer’s

16

request for additional information and documents relating to the cause of the delay and the expected

17

length of the delay. Any actual, consequential, indirect, incidental or special damages that a court

18

of competent jurisdiction orders the electric distribution company to pay to incurred by an

19

interconnecting, renewable-energy customer as a direct result of the electric distribution company's

20

failure to comply with the requirements of this subsection shall be payable to the customer by it’s

21

the electric distribution company shareholders and may not be recovered from customers, provided

22

that the total amount of damages awarded for any and all such claims shall not exceed, in the

23

aggregate, an amount equal to the amount of the incentive the electric distribution company would

24

have earned as provided for in §§ 39-26.6-12(j)(3) and 39-26.1-4 in the year in which the system

25

modifications were required to be completed. In no event shall the electric distribution company be

26

liable to the interconnecting, renewable-energy customer for any indirect, incidental, special,

27

consequential, or punitive damages of any kind whatsoever as a result of the electric distribution

28

company's failure to comply with this section.

29

     (e) On or before September 1, 2017, the public utilities commission shall initiate a docket

30

to establish metrics for the electric distribution company's performance in meeting the time frames

31

set forth herein and in the distributed generation interconnection standards approved by the public

32

utilities commission. The public utilities commission may include incentives and penalties in the

33

performance metrics.

34

     (f) The proposed interconnection of any new renewable energy resource that replaces the

 

LC005271 - Page 5 of 8

1

same existing renewable energy resource of the same or less nameplate capacity that has been in

2

operation in the twelve (12) months preceding notification of such replacement shall be subject to

3

a sixty-day (60) review. The purpose of such sixty-day (60) review is to allow the electric

4

distribution company to determine whether any system modifications are required to support the

5

interconnection of the replacement renewable energy resource. If there is a need for system

6

modifications because of an interconnection policy change implemented by the electric distribution

7

company, then the system modification may be included in rates as determined by the public

8

utilities commission. If there is a need for system modifications only because of a change in the

9

rating or utility disturbance response that adversely affects the impact of the facility on the

10

distribution system, then the interconnecting, renewable-energy customer shall be responsible for

11

the cost of the system modifications.

12

     (g) The public utilities commission, in consultation with the office of energy resources,

13

shall appoint an independent ombudsman to oversee the distribution company’s administration of

14

interconnection to ensure that the interconnection process works efficiently to serve the purposes

15

of Rhode Island’s energy plan and policy. The appointed ombudsman shall oversee and supervise

16

any and all elements of the interconnection process including, but not limited to: providing dispute

17

resolution assistance upon written request by a party to a dispute under the interconnection tariff,

18

planning and management of infrastructure safety and reliability investments and all other

19

investments to ensure and facilitate access to the distribution system; processing of applications;

20

management of queue position; interactions with ISO-NE; implementation of system

21

modifications; and administration and exemptions to the interconnection tax. This position shall be

22

funded out of the electric distribution company’s interconnection study fees assessed to

23

interconnecting customers.

24

     (h) The electric distribution company may not change its technical standards or

25

specifications for interconnection, as addressed in the Company’s ESB 756 where applicable to

26

Rhode Island “Requirements for Parallel Generation Connected to a National Grid owned EPS” or

27

otherwise, without approval of the public utilities commission and without properly publishing any

28

such changes to customers no less than thirty (30) days before implementation. Any changed

29

interconnection standards will not apply to interconnecting customers with complete

30

interconnection applications.

31

     (i) The electric distribution company shall ensure that its interconnection application

32

process adequately informs its customers of the procedure to certify qualification and pursue the

33

Internal Revenue Service’s safe-harbor against the contribution in aid of construction tax,

34

exempting interconnections designed to send electricity to the electric distribution company.

 

LC005271 - Page 6 of 8

1

     SECTION 2. This act shall take effect thirty (30) days after passage.

========

LC005271

========

 

LC005271 - Page 7 of 8

EXPLANATION

BY THE LEGISLATIVE COUNCIL

OF

A N   A C T

RELATING TO PUBLIC UTILITIES AND CARRIERS --DISTRIBUTED GENERATION

INTERCONNECTION

***

1

     This act would require the electric distribution company to report interconnection studies

2

and not charge more than actual costs for the studies.

3

     This act would take effect thirty (30) days after passage.

========

LC005271

========

 

LC005271 - Page 8 of 8