art.004/3/004/2/004/1 | ||
======= | ||
1 | ARTICLE 4 | |
2 | RELATING TO DEBT MANAGEMENT ACT JOINT RESOLUTIONS | |
3 | SECTION 1. This Article shall serve as the joint resolution required pursuant to Rhode | |
4 | Island Laws § 35-18-1, et seq. | |
5 | SECTION 2. University of Rhode Island – Facilities Service Sector Upgrade. | |
6 | WHEREAS, the University of Rhode Island Board of Trustees and the University of Rhode | |
7 | Island are proposing a project which involves the design and construction to enhance and | |
8 | reorganize the facilities within the service sector for more efficient and effective operations; | |
9 | WHEREAS, the University has engaged qualified architectural and engineering firms to | |
10 | perform master planning for this purpose; | |
11 | WHEREAS, in the last few decades, the University has made significant improvements to | |
12 | the campus infrastructure and building inventory that house academic functions, student activities, | |
13 | and athletic events for the University’s faculty and students; | |
14 | WHEREAS, it is in the best interest of the State, University, and the students and faculty | |
15 | to have these improvements maintained and repaired; | |
16 | WHEREAS, the University’s facilities group has the responsibility for maintenance and | |
17 | repair of these 5.8 million square feet, comprising approximately 25% of the State’s real estate | |
18 | portfolio; | |
19 | WHEREAS, the buildings housing the facilities group were built in the 1950s through | |
20 | 1970s, have passed the end of their 40-year useful life, and are in need of substantial capital renewal | |
21 | or replacement; | |
22 | WHEREAS, such improvements to the facilities group’s buildings are necessary to allow | |
23 | for the ongoing support of the campus; and | |
24 | WHEREAS, the total project cost associated with completion of this phase of the project | |
25 | and proposed financing method is thirteen million dollars ($13,000,000), including cost of issuance, | |
26 | debt service payments would be supported by revenues derived from the University’s unrestricted | |
27 | general revenues, and total debt service on the bonds is not expected to exceed one million one | |
28 | hundred fifty thousand dollars ($1,150,000) annually and twenty-three million dollars | |
29 | ($23,000,000) in the aggregate based on an average interest rate of six (6%) percent; now, therefore | |
30 | be it | |
| ||
1 | RESOLVED, that this General Assembly hereby approves financing in an amount not to | |
2 | exceed thirteen million dollars ($13,000,000) for the facilities service sector upgrade project at the | |
3 | University of Rhode Island; and be it further | |
4 | RESOLVED, that, this Joint Resolution shall take effect upon passage by this General | |
5 | Assembly. | |
6 | SECTION 3. University of Rhode Island – Utility Infrastructure Upgrade Phase II. | |
7 | WHEREAS, the University of Rhode Island Board of Trustees and the University of Rhode | |
8 | Island are proposing a project which involves the engineering and construction of upgrades and | |
9 | component replacements to five municipal-level Kingston Campus utility systems; | |
10 | WHEREAS, the University has engaged qualified engineering firms to examine its major | |
11 | infrastructure systems; | |
12 | WHEREAS, based on the condition and capabilities of these systems, the studies have | |
13 | concluded that replacement of components and reconfiguration was advisable for each of these | |
14 | extensive systems to ensure necessary steam, water, sanitary, and electrical support for the | |
15 | University’s campuses for the next 20-40 years; | |
16 | WHEREAS, the University has also developed the required Storm Water Management | |
17 | Plan for the Kingston Campus, which provides guidelines that are being incorporated into new | |
18 | building projects under development and are driving stand-alone storm water infrastructure projects | |
19 | as well; | |
20 | WHEREAS, the University has successfully completed many extremely important | |
21 | individual utility infrastructure projects in its continuing progression of work to upgrade and | |
22 | replace infrastructure systems but now needs additional investments beyond annual capital | |
23 | resources; | |
24 | WHEREAS, this project is the second phase in a phased implementation plan to upgrade | |
25 | and improve the reliability of infrastructure on the University of Rhode Island’s campuses; and | |
26 | WHEREAS, the total project cost associated with completion of this phase of the project | |
27 | and proposed financing method is fifteen million four hundred fifty thousand dollars ($15,450,000), | |
28 | including cost of issuance, debt service payments would be supported by revenues derived from | |
29 | the University’s unrestricted general revenues, and total debt service on the bonds is not expected | |
30 | to exceed one million three hundred fifty thousand dollars ($1,350,000) annually and twenty-seven | |
31 | million dollars ($27,000,000) in the aggregate based on an average interest rate of six (6%) percent; | |
32 | now, therefore be it | |
33 | RESOLVED, that this General Assembly hereby approves financing in an amount not to | |
34 | exceed fifteen million four hundred fifty thousand dollars ($15,450,000) for the Utility | |
|
| |
1 | Infrastructure Upgrade Phase II project at the University of Rhode Island; and be it further | |
2 | RESOLVED, that this Joint Resolution shall take effect upon passage by this General | |
3 | Assembly. | |
4 | SECTION 4. This article shall take effect upon passage. | |
|
|