1 | SECTION 1. Section 16-7-40 of the General Laws in Chapter 16-7 entitled "Foundation |
2 | Level School Support [See Title 16 Chapter 97 - The Rhode Island Board of Education Act]" is |
3 | hereby amended to read as follows: |
4 | 16-7-40. Increased school housing ratio. |
5 | (a)(1) In the case of regional school districts, the school housing aid ratio shall be increased |
6 | by two percent (2%) for each grade so consolidated. |
7 | (2) Regional school districts undertaking renovation project(s) shall receive an increased |
8 | share ratio of four percent (4%) for those specific project(s) only, in addition to the combined share |
9 | ratio calculated in ยง 16-7-39 and this subsection. |
10 | (b) In the case of projects undertaken by districts specifically for the purposes of school |
11 | safety and security, the school housing aid share ratio shall be increased by five percent (5%) for |
12 | these specific projects only, in the calculation of school housing aid. The increased share ratio shall |
13 | continue to be applied for as long as the project(s) receives state housing aid. In order to qualify for |
14 | the increased share ratio, seventy-five percent (75%) of the project costs must be specifically |
15 | directed to school safety and security measures. The council on elementary and secondary |
16 | education shall promulgate rules and regulations for the administration and operation of this |
17 | section. |
18 | (c) For purposes of addressing health and safety deficiencies as defined by the school |
| |
1 | building authority, including the remediation of hazardous materials, the school housing aid ratio |
2 | shall be increased by five percent (5%) so long as the construction of the project commences by |
3 | December 30, 2022 2023, is completed by December 30 31, 2027, and a two hundred fifty million |
4 | dollar ($250,000,000) general obligation bond is approved on the November 2018 ballot. In order |
5 | to qualify for the increased share ratio, twenty-five percent (25%) of the project costs or a minimum |
6 | of five hundred thousand dollars ($500,000) must be specifically directed to this purpose. |
7 | (d) For purposes of educational enhancement, including projects devoted to the |
8 | enhancement of early childhood education and career and technical education, the school housing |
9 | aid ratio shall be increased by five percent (5%) so long as construction of the project commences |
10 | by December 30, 2022 2023, is completed by December 30, 2027, and a two hundred fifty million |
11 | dollar ($250,000,000) general obligation bond is approved on the November 2018 ballot. In order |
12 | to qualify for the increased share ratio, twenty-five percent (25%) of the project costs or a minimum |
13 | of five hundred thousand dollars ($500,000) must be specifically directed to these purposes. |
14 | (e) For replacement of a facility that has a facilities condition index of sixty-five percent |
15 | (65%) or higher, the school housing ratio shall be increased by five percent (5%) so long as |
16 | construction of the project commences by December 30, 2023, is completed by December 30, 2028, |
17 | does not receive a bonus pursuant to subsection (f) or subsection (g), and a two hundred fifty million |
18 | dollar ($250,000,000) general obligation bond is approved on the November 2018 ballot. In order |
19 | to qualify for the increased share ratio, twenty-five percent (25%) of the project costs or a minimum |
20 | of five hundred thousand dollars ($500,000) must be specifically directed to this purpose. |
21 | (f) For any new construction or renovation that increases the functional utilization of any |
22 | facility from less than sixty percent (60%) to more than eighty percent (80%), including the |
23 | consolidation of school buildings within or across districts, the school housing aid ratio shall be |
24 | increased by five percent (5%) so long as construction of the project commences by December 30, |
25 | 2023, is completed by December 30, 2028, and a two hundred fifty million dollar ($250,000,000) |
26 | general obligation bond is approved on the November 2018 ballot. In order to qualify for the |
27 | increased share ratio, twenty-five percent (25%) of the project costs or a minimum of five hundred |
28 | thousand dollars ($500,000) must be specifically directed to this purpose. |
29 | (g) For any new construction or renovation that decreases the functional utilization of any |
30 | facility from more than one hundred twenty percent (120%) to between eighty-five percent (85%) |
31 | to one hundred five percent (105%), the school housing ratio shall be increased by five percent |
32 | (5%) so long as construction of the project commences by December 30, 2023, is completed by |
33 | December 30, 2028, and a two hundred fifty million dollar ($250,000,000) general obligation bond |
34 | is approved on the November 2018 ballot. In order to qualify for the increased share ratio, twenty- |
| LC003375 - Page 2 of 4 |
1 | five percent (25%) of the project costs or a minimum of five hundred thousand dollars ($500,000) |
2 | must be specifically directed to this purpose. |
3 | (h) For consolidation of two (2) or more school buildings, within or across districts into |
4 | one school building, the school housing aid ratio shall be increased by five percent (5%) so long as |
5 | construction of the project commences by December 30, 2023, is completed by December 30, 2028, |
6 | a two hundred fifty million dollar ($250,000,000) general obligation bond is approved on the |
7 | November 2018 ballot, and does not receive a bonus pursuant to subsection (f) or subsection (g). |
8 | In order to qualify for the increased share ratio, twenty-five percent (25%) of the project costs or a |
9 | minimum of five hundred thousand dollars ($500,000) must be specifically directed to this purpose. |
10 | (i) Any regionalized and/or non-regionalized school district receiving an increased share |
11 | ratio for a project approved prior to July 1, 2018, shall continue to receive the increased share ratio |
12 | for as long as the project receives state housing aid. |
13 | SECTION 2. This act shall take effect upon passage. |
======== | |
LC003375 | |
======== | |
| LC003375 - Page 3 of 4 |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO EDUCATION -- FOUNDATION LEVEL SCHOOL SUPPORT (SEE TITLE | |
16 CHAPTER 97 -- THE RHODE ISLAND BOARD OF EDUCATION ACT) | |
*** | |
1 | This act would extend the date of commencement of construction projects for health and |
2 | safety deficiencies and educational enhancement to December 30, 2023. |
3 | This act would take effect upon passage. |
======== | |