It is enacted by the General Assembly as follows: | |
1 | SECTION 1. Chapter 39-1 of the General Laws entitled "Public Utilities Commission" is |
2 | hereby amended by adding thereto the following section: |
3 | 39-1-63. Burying of electric transmission power lines. |
4 | (a) Whenever a residential customer of an electric transmission company loses electrical |
5 | power for a period of ninety-six (96) consecutive hours or more, the electric transmission company, |
6 | at their sole expense, shall formulate and execute a plan to bury the electric transmission lines |
7 | servicing that adversely affected residential customer, within two (2) years of the customer's ninety- |
8 | six (96) hours loss of electrical power. |
9 | (b) The provisions of this section shall not apply if the experienced loss of electrical power |
10 | was caused by the action or inaction of the affected residential customer, or if the electrical power |
11 | to the residence was terminated by the customer or the electric transmission company. |
12 | SECTION 2. This act shall take effect upon passage. |
======== | |
LC003531 | |
======== | |
| |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO PUBLIC UTILITIES AND CARRIERS -- PUBLIC UTILITIES COMMISSION | |
*** | |
1 | This act would require an electric utility company to bury power lines for all residential |
2 | customers who have experienced ninety-six (96) or more consecutive hours of power outage, unless |
3 | the outage was caused by the resident. |
4 | This act would take effect upon passage. |
======== | |