2022 -- H 8147 | |
======== | |
LC005784 | |
======== | |
STATE OF RHODE ISLAND | |
IN GENERAL ASSEMBLY | |
JANUARY SESSION, A.D. 2022 | |
____________ | |
A N A C T | |
RELATING TO STATE AFFAIRS AND GOVERNMENT -- ENERGY FACILITY SITING | |
ACT | |
| |
Introduced By: Representatives Place, and Newberry | |
Date Introduced: April 14, 2022 | |
Referred To: House Corporations | |
It is enacted by the General Assembly as follows: | |
1 | SECTION 1. Sections 42-98-1, 42-98-2, 42-98-3, 42-98-5, 42-98-7, 42-98-8, 42-98-9, 42- |
2 | 98-9.1, 42-98-10, 42-98-11 and 42-98-16 of the General Laws in Chapter 42-98 entitled "Energy |
3 | Facility Siting Act" are hereby amended to read as follows: |
4 | 42-98-1. Legislative findings. |
5 | (a) The general assembly recognizes that reasonably priced, reliable sources of energy are |
6 | vital to the well-being and prosperity of the people of this state; that there are major issues of public |
7 | health and safety and impact upon the environment related to the technologies and energy sources |
8 | used in some facilities; that some energy facilities require a major commitment of funds and |
9 | resources and require many years to build that the decision to permit or deny their construction will |
10 | have long term impact on the economy of the state; that these decisions will affect the availability |
11 | and cost of the energy; and that the evaluation of proposals must recognize and consider the need |
12 | for these facilities in relation to the overall impact of the facilities upon public health and safety, |
13 | the environment and the economy of the state; |
14 | (b) The general assembly further finds that the authority to regulate many aspects of the |
15 | issues involved in the siting of major energy facilities currently exists in a variety of agencies within |
16 | the government of the state and the political subdivisions of the state; that there is overlapping |
17 | jurisdiction among several state agencies in the siting of energy facilities; and that there is the |
18 | potential for conflicting decisions being issued by the various agencies having authority over the |
| |
1 | different aspects of the siting of a major energy facility; |
2 | (c) The jurisdiction of each state agency should be defined, and the role of each agency in |
3 | energy siting should be delineated, to eliminate overlap and duplication and to insure that |
4 | expeditious decisions are made within a time frame to be determined by law; and that in addition |
5 | to the existing regulation, statewide and regional planning for energy resources and the assessment |
6 | of our state's need for energy should be on-going activities within Rhode Island; |
7 | (d) There is need for a coordinated decision on any major energy facility; the technical |
8 | expertise for this evaluation is available within existing agencies involved with the siting process; |
9 | and |
10 | (e) There is a need for coordinating and expediting the review of each state agency and that |
11 | the authority and responsibility to perform that function should be established; and |
12 | (f) The general assembly recognizes that a host community for a proposed or existing major |
13 | generating facility is uniquely affected by the energy facility siting process. |
14 | 42-98-2. Declaration of policy. |
15 | It shall be the policy of this state to assure that: |
16 | (1) The facilities required to meet the energy needs of this and succeeding generations of |
17 | Rhode Islanders are planned for, considered, and built in a timely and orderly fashion; |
18 | (2) Construction, operation, and/or alteration of major energy facilities shall only be |
19 | undertaken when those actions are justified by long term state and/or regional energy need |
20 | forecasts; |
21 | (3) The energy shall be produced at the least possible cost to the consumer consistent with |
22 | the objective of ensuring that the construction, operation, and decommissioning of the facility shall |
23 | produce the fewest possible adverse effects on the quality of the state's environment; most |
24 | particularly, its land and its wildlife and resources, the health and safety of its citizens, the purity |
25 | of its air and water, its aquatic and marine life, and its esthetic and recreational value to the public; |
26 | (4) The licensure and regulatory authority of the state be consolidated in a single body, |
27 | which will render the final licensing decision concerning the siting, construction, operation and/or |
28 | alteration of major energy facilities; |
29 | (5) An energy facility planning process shall be created through which the statewide |
30 | planning program, in conjunction with the division of public utilities and carriers, will be |
31 | empowered to undertake evaluations and projections of long and short term energy needs, and any |
32 | other matters that are necessary to establish the state energy plans, goals, and policies. The state |
33 | planning council shall be authorized and empowered to adopt a long term plan assessing the state's |
34 | future energy needs and the best strategy for meeting them, as part of the state guide plan by January |
| LC005784 - Page 2 of 15 |
1 | 1, 1991. |
2 | (6) The construction, operation and/or alteration of major energy facilities shall be |
3 | consistent with the state's established energy plans, goals, and policy. |
4 | (7) Before approving the construction, operation and/or alteration of major energy |
5 | facilities, the board shall determine whether cost effective efficiency and conservation |
6 | opportunities provide an appropriate alternative to the proposed facility. |
7 | (8) The energy facilities siting board shall give priority to energy generation projects based |
8 | on the degree to which such projects meet, criteria including, but not limited to: |
9 | (i) Using renewable fuels, or natural gas, or coal processed by "clean coal technology" as |
10 | their primary fuel; |
11 | (ii) Maximizing efficiency; |
12 | (iii) Using low levels of high quality water; |
13 | (iv) Using existing energy-generation facilities and sites; |
14 | (v) Producing low levels of potentially harmful air emissions; |
15 | (vi) Producing low levels of wastewater discharge; |
16 | (vii) Producing low levels of waste into the solid waste stream; and |
17 | (viii) Having dual fuel capacity. |
18 | The board shall, within its rules and regulations, provide guidelines and definitions of |
19 | appropriate standards for the criteria designated in this subsection by January 1, 1991. |
20 | 42-98-3. Definitions. |
21 | As used in this chapter: |
22 | (1) "Advisory agencies" means the agencies, councils, boards, departments, and officials |
23 | of state or political subdivisions of the state which, absent this chapter, would have statutory |
24 | authority to grant or deny a permit, license, variance, or assent, and which shall function at the |
25 | direction of the board for hearing an issue and rendering an advisory opinion thereon, including, |
26 | but not limited to, the public utilities commission, department of transportation, department of |
27 | environmental management, historical preservation and heritage commission, division of planning, |
28 | department of health, office of energy resources, municipal zoning board, municipal planning |
29 | board, municipal building inspector, and municipal tax assessor. |
30 | (a)(2) "Agency" means any agency, council, board, or commission of the state or political |
31 | subdivision of the state. |
32 | (b)(3) "Alteration" means a significant modification to a major energy facility, which, as |
33 | determined by the board, will result in a significant impact on the environment, or the public health, |
34 | safety, and welfare. Conversion from one type of fuel to another to biofuel shall not be considered |
| LC005784 - Page 3 of 15 |
1 | to be an "alteration." |
2 | (c)(4) "Board" for purposes of this chapter refers to the siting board. |
3 | (5) "Host community" means any municipality in the state in which all or the majority of |
4 | a major energy facility is or shall be located. For the purpose of defining "located", linear aspects |
5 | of a major energy facility that transit through multiple municipalities, to include electric |
6 | transmission lines as used in this section and pipelines as used in this section shall not be considered |
7 | in determining where "the majority" of a major energy facility is or shall be located. |
8 | (6) For purpose of this chapter, there shall be two (2) types of "major energy facilities": |
9 | (i) "Major generating facility" means facilities for the generation of electricity designed or |
10 | capable of operating at a gross capacity of forty megawatts (40mw) or more. |
11 | (d)(ii) "Major energy non-generating facility" means: |
12 | (A) Facilities facilities for the extraction, production, conversion, and processing of coal; |
13 | facilities for the generation of electricity designed or capable of operating at a gross capacity of |
14 | forty (40) megawatts or more; |
15 | (B) Electric transmission lines of sixty-nine (69) Kv or over; |
16 | (C) Facilities facilities for the conversion, gasification, treatment, transfer, or storage of |
17 | liquefied natural and liquefied petroleum gases, except natural gas pipelines that have a maximum |
18 | allowable operation pressure (MOAP) greater than two hundred pounds per square inch gauge (200 |
19 | psig); |
20 | (D) Facilities facilities for the processing, enrichment, storage, or disposal of nuclear fuels |
21 | or nuclear byproducts; |
22 | (E) Facilities facilities for the refining of oil, gas, or other petroleum products; facilities of |
23 | ten (10) megawatts or greater capacity for the generation of electricity by water power, and |
24 | (F) Facilities facilities associated with the transfer of oil, gas, and coal via pipeline; any |
25 | energy facility project of the Rhode Island economic development corporation; the board may |
26 | promulgate regulations to further define "major energy facility" to the extent further definition is |
27 | required to carry out the purpose of this chapter, provided that any waste to energy facility shall |
28 | not be deemed a major energy facility for the purposes of this chapter. |
29 | (e) "Clean coal technology" means one of the technologies developed in the clean coal |
30 | technology program of the United States Department of Energy, and shown to produce emissions |
31 | levels substantially equal to those of natural gas fired power plants. |
32 | 42-98-5. Board established. |
33 | (a) There is established the siting board which shall be a part of state government. |
34 | (1) The siting board shall consist of three (3) five (5) members, as follows: the chairperson |
| LC005784 - Page 4 of 15 |
1 | of the public utilities commission, or designee, who shall serve as chairperson of the siting board; |
2 | the director of the department of environmental management, or designee; and the associate |
3 | director of administration for planning, or designee; the secretary of commerce, or designee; and a |
4 | public member appointed in accordance with § 42-98-5.1. Any member of the board who recuses |
5 | him or herself shall designate his or her own successor from his or her respective agency. |
6 | (2) Any member of the board, other than a public member, may select their own designee |
7 | from their respective agency who shall serve until a final determination is made in the proceeding |
8 | for which they were designated. |
9 | (b) Each member of the board, including designees, shall take an oath to administer the |
10 | duties of office faithfully and impartially and that oath shall be filed in the office of the secretary |
11 | of state. |
12 | (c) The members of the board shall serve without compensation, but shall be reimbursed |
13 | for their actual expenses necessarily incurred in the performance of their duties. The board may |
14 | engage any consultants or expert witnesses that it deems necessary to implement its statutory |
15 | responsibilities; provided, however, that to the maximum extent possible, board staff be drawn |
16 | from existing state agencies. The board shall select a coordinator to be responsible for the |
17 | publication and distribution of all official minutes, reports, and documents and to further serve as |
18 | director of the board staff, which shall be located at the division of public utilities and common |
19 | carriers. The coordinator, under the direction of the chairperson, shall coordinate and expedite the |
20 | work of the various agencies to ensure that decisions are made within the time frame established |
21 | by this chapter. The board may appoint hearing officers to conduct hearings in accordance with § |
22 | 42-98-5.2. Any individual designated as board staff shall be bound to comply with the ex parte |
23 | provisions of § 42-35-13. |
24 | (d) A quorum shall consist of a majority of the board. A majority vote of the board shall be |
25 | required for all actions, including licensing decisions; provided, however, one member of the board |
26 | may conduct any hearings the board is authorized to conduct pursuant to this chapter. |
27 | (e) The board shall maintain and grant free access to records and reports in its files to |
28 | members of the public during normal working hours and shall permit copies of those records and |
29 | reports to be made by interested members of the public at their expense; provided, however, that |
30 | the board shall not permit disclosure, other than to another government agency for the sole purpose |
31 | of rendering an advisory opinion, of any information obtained by or submitted to the board pursuant |
32 | to the provisions of this chapter, upon a showing, satisfactory to the board, that the information is |
33 | entitled to protection as trade secrets or as privileged, confidential, or proprietary information. No |
34 | other governmental agency shall disclose any trade secrets or privileged, confidential, or |
| LC005784 - Page 5 of 15 |
1 | proprietary information. |
2 | 42-98-7. Powers and duties. |
3 | (a)(1) The siting board is the licensing and permitting authority for all licenses, permits, |
4 | assents, or variances which, under any statute of the state or ordinance of any political subdivision |
5 | of the state, would be required for siting, construction or alteration of a major energy facility in the |
6 | state. |
7 | (2) Any agency, board, council, or commission of the state or political subdivision of the |
8 | state which, absent this chapter, would be required to issue a permit, license, assent, or variance in |
9 | order for the siting, construction, or alteration of a major energy facility to proceed, shall sit and |
10 | function at the direction of the siting board. These agencies shall follow the procedures established |
11 | by statute, ordinance, and/or regulation provided for determining the permit, license, assent, or |
12 | variance, but, instead of issuing the permit, license, assent, or variance, shall forward its findings |
13 | from the proceeding, together with the record supporting the findings and a recommendation for |
14 | final action, to the siting board. |
15 | (3) Notwithstanding any provision in this chapter to the contrary, in those instances in |
16 | which the department of environmental management exercises a permitting or licensing function |
17 | under the delegated authority of federal law, including, but not limited to, the Federal Clean Water |
18 | Act (33 U.S.C. § 1251 et seq.), the Resource Conservation and Recovery Act (42 U.S.C. § 6901 et |
19 | seq.), the Clean Air Act (42 U.S.C. § 7401 et seq.), and those state laws and regulations which |
20 | implement those federal laws, the department of environmental management shall be the licensing |
21 | and permitting authority. Moreover, the authority to issue licenses and permits delegated to the |
22 | department of environmental management pursuant to chapter 1 of title 2 and to the coastal |
23 | resources management council pursuant to chapter 23 of title 46, shall remain with those agencies, |
24 | but in all other respects the department of environmental management and the coastal resources |
25 | management council shall follow the procedures set forth in this chapter. |
26 | (b) The siting board is authorized and empowered to summon and examine witnesses and |
27 | to compel the production and examination of papers, books, accounts, documents, records, |
28 | certificates, and other legal evidence that may be necessary for the determination of its jurisdiction |
29 | and decision of any question before, or the discharge of any duty required by law of, the board. |
30 | (c) The siting board is empowered to issue any orders, rules, or regulations as may be |
31 | required to effectuate the purposes of this chapter. The board shall review its rules and regulations |
32 | from time to time and shall modify, amend or repeal any rules or regulations as may be required to |
33 | effectuate the purposes of this chapter. |
34 | (d) The siting board shall, by regulation, determine the standards for intervention. Each |
| LC005784 - Page 6 of 15 |
1 | host community shall be granted intervenor status as of right. |
2 | (e) The siting board's proceedings shall in all respects comply with the requirements of the |
3 | Administrative Procedures Act, chapter 35 of this title, except where otherwise explicitly provided. |
4 | 42-98-8. Applications -- Contents -- Acceptance for filing. |
5 | (a) The rules and regulations promulgated by the board pursuant to § 42-98-7(c) shall |
6 | prescribe the form and contents of applications under this chapter. The applications shall contain |
7 | at least the following, where applicable: |
8 | (1) Identification of the proposed owner(s) of the facility, including identification of all |
9 | affiliates of the proposed owners, as the term is defined in § 39-3-27. |
10 | (2) Detailed description of the proposed facility, including its function and operating |
11 | characteristics, and complete plans as to all structures, including underground construction and |
12 | transmission facilities, underground or aerial, associated with the proposed facility. |
13 | The complete plans shall be the basis for determining jurisdiction under the energy facility |
14 | siting act and shall be the plans submitted to all advisory agencies whose permit is required under |
15 | the law. |
16 | (3) A detailed description and analysis of the impact of the proposed facility on its physical |
17 | and social environment together with a detailed description of all environmental characteristics of |
18 | the proposed site, including, but not limited to, the types of fuels and waste products used, stored, |
19 | and produced by the facility, and a summary of all studies prepared and relied upon in connection |
20 | therewith. |
21 | Where applicable these descriptions and analysis shall include a review of current |
22 | independent, scientific research pertaining to electric and magnetic fields (EMF). The review shall |
23 | provide data assessing potential health risks associated with EMF exposure. For the purposes of |
24 | this chapter "prudent avoidance" shall refer to measures to be implemented in order to protect the |
25 | public from EMF exposure. |
26 | (4) All studies and forecasts, complete with the information, data, methodology, and |
27 | assumptions on which they are based, on which the applicant intends to rely in showing the need |
28 | for the proposed facility under the statewide master construction plan submitted annually. |
29 | (5) Complete detail as to the estimated construction cost of the proposed facility, the |
30 | projected maintenance and operation costs, estimated costs to the community such as safety and |
31 | public health issues, storm damage and power outages, estimated costs to businesses and |
32 | homeowners due to power outages, the estimated unit cost of energy to be produced by the proposed |
33 | facility, and expected methods of financing the facility. |
34 |
|
| LC005784 - Page 7 of 15 |
1 | (6) A complete life-cycle management plan for the proposed facility, including measures |
2 | for protecting the public health and safety and the environment during the facility's normal and off- |
3 | normal operations, including, but not limited to, plans for the handling and disposal of wastes from |
4 | the facility, and plans for the decommissioning of the facility at the end of its useful life. |
5 | (7) A study of alternatives to the proposed facility, including alternatives as to energy |
6 | sources, methods of energy production, and sites for the facility, together with reasons for the |
7 | applicant's rejection of these alternatives. The study shall include estimates of facility cost and unit |
8 | energy costs of alternatives considered. |
9 | (8) A detailed description of the short-term and long-term economic impacts associated |
10 | with constructing and operating the proposed project. |
11 | (b) Each application shall be reviewed prior to docketing. The board shall conduct a |
12 | preliminary review to determine whether the application contains each item as required by |
13 | subsection (a) of this section. Within thirty (30) days of the filing of an applicant application under |
14 | this chapter, the board shall notify the applicant whether the application is in the form and addresses |
15 | the matters that are required by this section and the rules and regulations as are promulgated |
16 | pursuant to § 42-98-7. An application meeting these requirements shall then be docketed. Any |
17 | application deemed to be deficient shall be returned to the applicant, together with a concise and |
18 | explicit statement of the application's deficiencies. Within fifteen (15) days of the resubmission of |
19 | an application following a rejection for deficiency, the board shall either docket the application |
20 | together with specification of continuing deficiencies noted by the board, if any, or shall issue a |
21 | decision rejecting the application due to continuing deficiencies. |
22 | 42-98-9. Applications -- Procedures for review -- Preliminary hearing. |
23 | (a) Within sixty (60) days following the board's docketing of an application the board shall, |
24 | on not less than forty-five (45) days' notice to all agencies, subdivisions of the state, and the public, |
25 | convene a preliminary hearing on the application to determine the issues to be considered by the |
26 | board in evaluating the application, and to designate those agencies of state government and of |
27 | political subdivisions of the state which shall act at the direction of the board for the purpose of |
28 | rendering advisory opinions on these issues, and to determine petitions for intervention. |
29 | (b) The board shall consider as issues in every proceeding the ability of the proposed |
30 | facility to meet the requirements of the laws, rules, regulations, and ordinances under which, absent |
31 | this chapter, the applicant would be required to obtain a permit, license, variance, or assent. The |
32 | agency of state government or of a political subdivision of the state which, absent this chapter, |
33 | would have statutory authority to grant or deny the permit, license, variance, or assent, shall |
34 | function at the direction of the board for hearing the issue and rendering an advisory opinion |
| LC005784 - Page 8 of 15 |
1 | thereon. |
2 | (c) The board shall may limit the scope of any agency's investigation where it finds that |
3 | more than one agency has jurisdiction over a matter at issue in the licensing process. In these |
4 | instances, the board shall may determine which agency shall make the necessary findings on the |
5 | issue after giving proper consideration to the expertise and resources available to each of the |
6 | agencies involved. |
7 | (d) The public utilities commission shall conduct an investigation in which the division of |
8 | planning of the department of administration, the governor's office of energy assistance resources |
9 | and the division of public utilities and carriers shall participate and render an advisory opinion as |
10 | to the need for the proposed facility. |
11 | (e) The statewide planning program within the department of administration shall conduct |
12 | an investigation and render an advisory opinion as to the socio-economic impact of the proposed |
13 | facility and its construction and consistency with the state guide plan. |
14 | (f) A decision of the board under this section shall be issued within thirty (30) days |
15 | following the conclusion of the preliminary hearing and in any event within forty-five (45) days of |
16 | the commencement of the hearing. |
17 | 42-98-9.1. Public notice and hearings on construction projects in cities and towns |
18 | affected. |
19 | (a) Upon receiving a utility company application the board shall immediately notify, in |
20 | writing, the councils of the towns and cities affected by the construction. |
21 | (b)(1) The When the subject of the application is a major non-generating facility, the board |
22 | shall have at least one public hearing in each town or city affected the host community prior to |
23 | holding its own hearings and prior to taking final action on the application. All details of acceptance |
24 | for filing in § 42-98-8(a)(1) -- (a)(6) shall be presented at town or city hearings for public comment. |
25 | When the subject of the application is a facility for the generation of electricity, or are new facilities |
26 | for the transmission of electricity, the town or city where the proposed facility would be located |
27 | may request funding from the applicant to perform studies of the local environmental effects of the |
28 | proposed facility. The expense of those studies shall not exceed the lesser of one hundred thousand |
29 | dollars ($100,000) or one-tenth percent (.1%) of the estimated capital cost of the proposed facility |
30 | located in such city or town. If the applicant contests the relevance of the requested study, or |
31 | believes it to be redundant with studies already performed, the applicant may request a ruling from |
32 | the board whether the study is necessary and reasonably expected to produce relevant information. |
33 | The board's ruling shall be conclusive and final, and shall not be the basis for an interlocutory |
34 | appeal, injunction or otherwise delay the board's processing of the application. |
| LC005784 - Page 9 of 15 |
1 | (2) When the subject of the application is a major generating facility, the board shall have |
2 | at least three (3) public hearings in the host community prior to holding its own hearings and prior |
3 | to taking final action on the application. All details of acceptance for filing in § 42-98-8(a) shall be |
4 | presented at public hearings for public comment. The host community where the proposed |
5 | generating facility would be located may request funding from the applicant to perform studies of |
6 | the local environmental effects of the proposed facility. The expense of those studies shall not |
7 | exceed the greater of one hundred fifty thousand dollars ($150,000) or one-tenth percent (.1%) of |
8 | the estimated capital cost of the proposed facility, whichever is less. The applicant shall also pay |
9 | any and all fees and expenses reasonably incurred by the host community to fully participate in the |
10 | facility siting process and local review, including, but not limited to, fees and expenses for legal |
11 | counsel, expert evaluations, transcripts and other costs associated with the energy facility siting |
12 | process. If the applicant contests any fee or expense as unrelated or unreasonable, the applicant |
13 | may request a ruling from the board whether the fee or expense is related and reasonable. The |
14 | board's ruling shall be conclusive and final and shall not be the basis for an interlocutory appeal, |
15 | injunction or otherwise delay the board's processing of the application. |
16 | (c) The applicant shall notify the citizens in towns and cities affected thirty (30) days prior |
17 | to public meetings through local papers. |
18 | (d) The applicant shall notify abutting land the following property owners individually, in |
19 | writing, thirty (30) days prior to the hearings, by certified mail, postage prepaid: |
20 | (1) For applications related to major non-generating facilities, applicants shall notify all |
21 | property owners whose property is located within three hundred feet (300’) from the limit of |
22 | disturbance of the proposed project or the centerline of a proposed linear project. |
23 | (2) For applications related to major generating facilities, applicants shall notify all |
24 | property owners whose property is located within two (2) miles from the proposed site boundaries. |
25 | (e) Public input shall be a part of the decision making process. |
26 | 42-98-10. Agency procedures -- Advisory opinion. |
27 | (a) Each agency of the state or political subdivision of the state designated under § 42-98- |
28 | 9 shall proceed to consider the issue or issues consigned to it for review. Each advisory agency |
29 | shall conclude its consideration and issue its advisory opinion not more than six (6) months |
30 | following its designation under § 42-98-9 and receipt of all application materials, or any lesser time |
31 | that the board may require, or the right to exercise the function shall be forfeited to the board. The |
32 | board may suspend an application proceeding where an applicant fails to provide requested relevant |
33 | information or materials to an advisory agency in a timely manner. |
34 | (b) Advisory opinions issued by agencies designated under § 42-98-9 shall not be |
| LC005784 - Page 10 of 15 |
1 | considered as final decisions of the agencies making the opinions, and shall not be subject to |
2 | judicial review under § 42-35-15, or any other provision of the general laws. |
3 | (c) Advisory opinions issued by zoning boards of review, building inspectors, or any other |
4 | agency of a municipality designated under § 42-98-9 shall not be reviewable by the public utilities |
5 | commission under § 39-1-30. |
6 | (d) Failure or refusal of the applicant to provide requested information may be considered |
7 | as grounds for recommending denial. |
8 | (e) At the request of the siting board, the director of environmental management and the |
9 | coastal resources management council shall give priority to the review of permits for energy |
10 | facilities. |
11 | 42-98-11. Final hearing -- Standards -- Decisions. |
12 | (a) Within forty-five (45) days after the final date for submission of advisory opinions |
13 | pursuant to § 42-98-10, the board shall convene the final hearing on the application. The purpose |
14 | of this the final hearing shall not be to rehear the evidence which was presented previously in |
15 | hearings before agencies designated under § 42-98-9, but rather to provide the applicant, |
16 | intervenors, the public, and all other parties in the proceeding, the opportunity to address in a single |
17 | forum, and from a consolidated, statewide prospective, the issues reviewed, and the |
18 | recommendations made in the proceedings before the agencies designated under § 42-98-9. The |
19 | board at this hearing may, at its discretion, allow the presentation of new evidence by any party as |
20 | to the issues considered by the agencies designated under § 42-98-9. The board may limit the |
21 | presentation of repetitive or cumulative evidence. The final hearing shall proceed on not less than |
22 | thirty (30) days' notice to the parties and the public, shall be concluded not more than sixty (60) |
23 | days following its initiation, and shall be conducted expeditiously. |
24 | (b) The board shall issue a decision granting a license only upon finding that the applicant |
25 | has shown that: |
26 | (1) Construction of the proposed facility is necessary to meet the needs of the state and/or |
27 | region for energy of the type to be produced by the proposed facility. |
28 | (2) The proposed facility is cost-justified, and can be expected to produce energy at the |
29 | lowest reasonable cost to the consumer consistent with the objective of ensuring that the |
30 | construction and operation of the proposed facility will be accomplished in compliance with all of |
31 | the requirements of the laws, rules, regulations, and ordinances, under which, absent this chapter, |
32 | a permit, license, variance, or assent would be required, or that consideration of the public health, |
33 | safety, welfare, security and need for the proposed facility justifies a waiver of some part of the |
34 | requirements when compliance cannot be assured. |
| LC005784 - Page 11 of 15 |
1 | (3) The proposed facility will not cause unacceptable harm to the environment and will |
2 | enhance the socio-economic fabric of the state. |
3 | (c) For multiple applications related to a single project, the board shall consider the |
4 | cumulative impacts of the related applications. |
5 | (c)(d) Within sixty (60) days of the conclusion of the final hearing the board shall issue its |
6 | final decision on the application. A decision in favor of the application shall constitute a granting |
7 | of all permits, licenses, variances, or assents, which under any law, rule, regulation, or ordinance |
8 | of the state or of a political subdivision thereof which would, absent this chapter, be required for |
9 | the proposed facility. The decision may be issued requiring any modification or alteration of the |
10 | proposed facility, and may be issued on any condition the board deems warranted by the record, |
11 | and may be issued conditional upon the applicant's receipt of permits required by federal law. The |
12 | board's decision shall explicitly address each of the advisory opinions received from agencies, and |
13 | the board's reasons for accepting, rejecting, or modifying, in whole or in part, any of those advisory |
14 | opinions. The board shall, within ten (10) days of granting a license, with or without conditions, |
15 | deliver the decision to the governor, the speaker of the Rhode Island house of representatives, and |
16 | the president of the Rhode Island senate. |
17 | 42-98-16. Violations. |
18 | (a) Failure to comply with any promulgated board rule, regulation, requirement or |
19 | procedure for the licensing of energy facilities shall constitute grounds for suspension or dismissal, |
20 | with or without prejudice in its discretion, of licensing proceedings, provided that the applicant |
21 | shall have a reasonable opportunity to show cause for and remedy the lack of compliance. |
22 | (b) Failure to comply with any provision, condition or limitation contained in a board |
23 | license to site, build, or alter a major energy facility and/or failure to comply with a board cease |
24 | and desist order and/or a board order to remedy a non-complying action shall be grounds for |
25 | suspension or revocation of the license, and/or shall be punishable by a fine of not more than twenty |
26 | thousand dollars ($20,000). Each day of continuing noncompliance shall be considered a separate |
27 | violation and so punished. |
28 | (c) The board may require the licensee to maintain those records as are reasonable and |
29 | necessary to monitor compliance with license provisions, and shall have the authority to enter onto |
30 | the property of licensees to investigate complaints of noncompliance and to perform routine |
31 | inspections. |
32 | (d) The board may designate officials or staff of any state agencies as its agents for the |
33 | purposes of investigating complaints, performing routine maintenance functions and issuing |
34 | written cease and desist orders. |
| LC005784 - Page 12 of 15 |
1 | (e) Nothing in this chapter shall preclude a host community from enforcing municipal |
2 | ordinances, levying fines, or pursuing any other legally available enforcement remedies, unless |
3 | such ordinances are in direct conflict with a certificate or license issued by the board. |
4 | SECTION 2. Chapter 42-98 of the General Laws entitled "Energy Facility Siting Act" is |
5 | hereby amended by adding thereto the following sections: |
6 | 42-98-5.1. Public members. |
7 | (a) A public member shall be appointed to the board by the governor with the advice and |
8 | consent of the senate for a term of two (2) years. |
9 | (b) A public member shall be a member of the general public with experience or training |
10 | in the areas of energy, engineering, consumer protection, or municipal government. |
11 | (c) A public member shall not hold another state or local office and shall not receive nor |
12 | have received within the previous five (5) years any income directly or indirectly from an electric, |
13 | gas, or oil company or from an energy facility developer. |
14 | (d) If a public member recuses or withdraws from a proceeding for any reason, a substitute |
15 | member shall be appointed in accordance with this section. |
16 | 42-98-5.2. Hearing officers. |
17 | (a) The board may appoint a hearing officer to conduct hearings related to a major non- |
18 | generating facility. Hearing officers shall not be appointed to conduct hearings related to a major |
19 | generating facility. |
20 | (b) A hearing officer shall be an attorney licensed to practice law in this state with |
21 | experience in regulatory matters dealing with energy production and/or transmission. |
22 | (c) A hearing officer shall be reasonably compensated by the board for their services to the |
23 | board, either through contract or, if the hearing officer is a state employee, through a transfer to the |
24 | state agency or department by whom the attorney is normally employed. |
25 | (d) Following the completion of the hearing, the hearing officer shall file their findings and |
26 | recommended decision in writing with the board. Upon review of the findings and |
27 | recommendations, the board may accept, reject, or modify, in whole or in part, the hearing officer’s |
28 | findings and recommended decision. The hearing officer’s findings and recommended decision |
29 | shall become effective and shall have the same force and effect as a decision of the board. If the |
30 | board rejects or modifies the hearing officer’s findings or recommended decision, then the board |
31 | shall decide the matter independently and issue an order of the board with its findings and decision. |
32 | (e) No hearing officer shall be assigned to a hearing relating to a project or proposed project |
33 | by an applicant from whom they have directly or indirectly received compensation from in the last |
34 | five (5) years. |
| LC005784 - Page 13 of 15 |
1 | (f) The board shall establish within two (2) months of enactment of this section and |
2 | maintain, at least on a biannual basis, a list of qualified hearing officers, the number of which the |
3 | board shall set, to draw from. |
4 | (g) The list shall be composed with an equal number of officers with primary professional |
5 | experience as advocates for government and an equal number of officers with primary professional |
6 | experience as advocates for the private sector. |
7 | SECTION 3. This act shall take effect upon passage. |
======== | |
LC005784 | |
======== | |
| LC005784 - Page 14 of 15 |
EXPLANATION | |
BY THE LEGISLATIVE COUNCIL | |
OF | |
A N A C T | |
RELATING TO STATE AFFAIRS AND GOVERNMENT -- ENERGY FACILITY SITING | |
ACT | |
*** | |
1 | This act would recognize that a host community for a proposed or existing major generating |
2 | facility is uniquely affected by the facility siting process. It would increase the membership of the |
3 | siting board from three (3) to five (5) members and would mandate inclusion and participation of |
4 | the public in the affected cities and towns. This act would spell out requirements for hearing officers |
5 | and public members of the board. |
6 | This act would take effect upon passage. |
======== | |
LC005784 | |
======== | |
| LC005784 - Page 15 of 15 |