2023 -- H 5853

========

LC002218

========

     STATE OF RHODE ISLAND

IN GENERAL ASSEMBLY

JANUARY SESSION, A.D. 2023

____________

A N   A C T

RELATING TO PUBLIC UTILITIES AND CARRIES -- NET METERING

     

     Introduced By: Representatives Speakman, Boylan, Ajello, McGaw, Donovan, Tanzi,
Cortvriend, Knight, Kislak, and Potter

     Date Introduced: March 01, 2023

     Referred To: House Corporations

     It is enacted by the General Assembly as follows:

1

     SECTION 1. Sections 39-26.4-1, 39-26.4-2 and 39-26.4-3 of the General Laws in Chapter

2

39-26.4 entitled "Net Metering" are hereby amended to read as follows:

3

     39-26.4-1. Purpose.

4

     The purpose of this chapter is to facilitate and promote installation of customer-sited, grid-

5

connected generation of renewable energy; to support and encourage customer development of

6

renewable generation systems; to reduce environmental and siting impacts; to reduce carbon

7

emissions that contribute to climate change by encouraging the local siting of renewable energy

8

projects; to diversify the state’s energy generation sources; to stimulate economic development; to

9

improve distribution system resilience and reliability; and to reduce distribution system costs.

10

     39-26.4-2. Definitions.

11

     Terms not defined in this section herein shall have the same meaning as contained in

12

chapter 26 of this title. When used in this chapter:

13

     (1) “Community remote net-metering system” means a facility generating electricity using

14

an eligible net-metering resource that allocates net-metering credits to a minimum of one account

15

for a system associated with low- or moderate-income housing eligible credit recipients, or three

16

(3) eligible credit-recipient customer accounts, provided that no more than fifty percent (50%) of

17

the credits produced by the system are allocated to one eligible credit recipient, and provided further

18

at least fifty percent (50%) of the credits produced by the system are allocated to the remaining

19

eligible credit recipients in an amount not to exceed that which is produced annually by twenty-

 

1

five kilowatt (25 KW) AC capacity. The community remote net-metering system may transfer

2

credits to eligible credit recipients in an amount that is equal to or less than the sum of the usage of

3

the eligible credit recipient accounts measured by the three-year (3) average annual consumption

4

of energy over the previous three (3) years. A projected annual consumption of energy may be used

5

until the actual three-year (3) average annual consumption of energy over the previous three (3)

6

years at the eligible credit recipient accounts becomes available for use in determining eligibility

7

of the generating system. The community remote net-metering system may be owned by the same

8

entity that is the customer of record on the net-metered account or may be owned by a third party.

9

     (2) “Core forest” refers to unfragmented forest blocks of single or multiple parcels totaling

10

two hundred fifty (250) acres or greater unbroken by development and at least twenty-five yards

11

(25 yds.) from mapped roads, with eligibility questions to be resolved by the director of the

12

department of environmental management. Such determination shall constitute a contested case as

13

defined in § 42-35-1.

14

     (2)(3) “Electric distribution company” shall have the same meaning as § 39-1-2, but shall

15

not include Block Island Power Company or Pascoag Utility District, each of whom shall be

16

required to offer net metering to customers through a tariff approved by the public utilities

17

commission after a public hearing. Any tariff or policy on file with the public utilities commission

18

on the date of passage of this chapter shall remain in effect until the commission approves a new

19

tariff.

20

     (3)(4) “Eligible credit recipient” means one of the following eligible recipients in the

21

electric distribution company’s service territory whose electric service account or accounts may

22

receive net-metering credits from a community remote net-metering system. Eligible credit

23

recipients include the following definitions:

24

     (i) Residential accounts in good standing.

25

     (ii) “Low- or moderate-income housing eligible credit recipient” means an electric service

26

account or accounts in good standing associated with any housing development or developments

27

owned or operated by a public agency, nonprofit organization, limited-equity housing cooperative,

28

or private developer that receives assistance under any federal, state, or municipal government

29

program to assist the construction or rehabilitation of housing affordable to low- or moderate-

30

income households, as defined in the applicable federal or state statute, or local ordinance,

31

encumbered by a deed restriction or other covenant recorded in the land records of the municipality

32

in which the housing is located, that:

33

     (A) Restricts occupancy of no less than fifty percent (50%) of the housing to households

34

with a gross, annual income that does not exceed eighty percent (80%) of the area median income

 

LC002218 - Page 2 of 21

1

as defined annually by the United States Department of Housing and Urban Development (HUD);

2

     (B) Restricts the monthly rent, including a utility allowance, that may be charged to

3

residents, to an amount that does not exceed thirty percent (30%) of the gross, monthly income of

4

a household earning eighty percent (80%) of the area median income as defined annually by HUD;

5

     (C) Has an original term of not less than thirty (30) years from initial occupancy.

6

     Electric service account or accounts in good standing associated with housing

7

developments that are under common ownership or control may be considered a single low- or

8

moderate-income housing eligible credit recipient for purposes of this section. The value of the

9

credits shall be used to provide benefits to tenants.

10

     (iii) “Educational institutions” means public and private schools at the primary, secondary,

11

and postsecondary levels.

12

     (iv) “Commercial and industrial customers” means any commercial or business entity that

13

is charged by the distribution company at the C-06 small commercial and industrial rate, the G-02

14

general commercial and industrial rate, the G-32 large demand rate or the G-62 optional large

15

demand rate.

16

     (4)(5) “Eligible net-metering resource” means eligible renewable energy resource, as

17

defined in § 39-26-5 including biogas created as a result of anaerobic digestion, but, specifically

18

excluding all other listed eligible biomass fuels.

19

     (5)(6) “Eligible net-metering system” means a facility generating electricity using an

20

eligible net-metering resource that is reasonably designed and sized to annually produce electricity

21

in an amount that is equal to, or less than, the renewable self-generator’s usage at the eligible net-

22

metering system site measured by the three-year (3) average annual consumption of energy over

23

the previous three (3) years at the electric distribution account(s) located at the eligible net-metering

24

system site. A projected annual consumption of energy may be used until the actual three-year (3)

25

average annual consumption of energy over the previous three (3) years at the electric distribution

26

account(s) located at the eligible net-metering system site becomes available for use in determining

27

eligibility of the generating system. The eligible net-metering system may be owned by the same

28

entity that is the customer of record on the net-metered accounts or may be owned by a third party

29

that is not the customer of record at the eligible net-metering system site and which may offer a

30

third-party, net-metering financing arrangement or net-metering financing arrangement, as

31

applicable. Notwithstanding any other provisions of this chapter, any eligible net-metering

32

resource: (i) Owned by a public entity, educational institution, hospital, nonprofit, or multi-

33

municipal collaborative or (ii) Owned and operated by a renewable-generation developer on behalf

34

of a public entity, educational institution, hospital, nonprofit, or multi-municipal collaborative

 

LC002218 - Page 3 of 21

1

through a net-metering financing arrangement shall be treated as an eligible net-metering system

2

and all accounts designated by the public entity, educational institution, hospital, nonprofit, or

3

multi-municipal collaborative for net metering shall be treated as accounts eligible for net metering

4

within an eligible net-metering system site. Any net-metering resource owned by a commercial or

5

industrial customer or owned and operated by a renewable generation developer on behalf of a

6

commercial or industrial customer shall be treated as an eligible net-metering system.

7

     (6)(7) “Eligible net-metering system site” means the site where the eligible net-metering

8

system or community remote net-metering system is located or is part of the same campus or

9

complex of sites contiguous to one another and the site where the eligible net-metering system or

10

community remote net-metering system is located or a farm in which the eligible net-metering

11

system or community remote net-metering system is located. Except for an eligible net-metering

12

system owned by or operated on behalf of a public entity, educational institution, hospital,

13

nonprofit, or multi-municipal collaborative through a net-metering financing arrangement or for an

14

eligible commercial and industrial customer through a net-metering financing arrangement, the

15

purpose of this definition is to reasonably assure that energy generated by the eligible net-metering

16

system is consumed by net-metered electric service account(s) that are actually located in the same

17

geographical location as the eligible net-metering system. All energy generated from any eligible

18

net-metering system is, and will be considered, consumed at the meter where the renewable energy

19

resource is interconnected for valuation purposes. Except for an eligible net-metering system

20

owned by, or operated on behalf of, a public entity, educational institution, hospital, nonprofit, or

21

multi-municipal collaborative or for an eligible commercial and industrial customer through a net-

22

metering financing arrangement, or except for a community remote net-metering system, all of the

23

net-metered accounts at the eligible net-metering system site must be the accounts of the same

24

customer of record and customers are not permitted to enter into agreements or arrangements to

25

change the name on accounts for the purpose of artificially expanding the eligible net-metering

26

system site to contiguous sites in an attempt to avoid this restriction. However, a property owner

27

may change the nature of the metered service at the accounts at the site to be master metered in the

28

owner’s name, or become the customer of record for each of the accounts, provided that the owner

29

becoming the customer of record actually owns the property at which the account is located. As

30

long as the net-metered accounts meet the requirements set forth in this definition, there is no limit

31

on the number of accounts that may be net metered within the eligible net-metering system site.

32

     (7)(8) “Excess renewable net-metering credit” means a credit that applies to an eligible net-

33

metering system or community remote net-metering system for that portion of the production of

34

electrical energy beyond one hundred percent (100%) and no greater than one hundred twenty-five

 

LC002218 - Page 4 of 21

1

percent (125%) of the renewable self-generator’s own consumption at the eligible net-metering

2

system site or the sum of the usage of the eligible credit recipient accounts associated with the

3

community remote net-metering system during the applicable billing period. Such excess

4

renewable net-metering credit shall be equal to the electric distribution company’s avoided cost

5

rate, which is hereby declared to be the electric distribution company’s standard-offer service

6

kilowatt hour (KWh) charge for the rate class and time-of-use billing period (if applicable)

7

applicable to the customer of record for the eligible net-metering system or applicable to the

8

customer of record for the community remote net-metering system. The commission shall have the

9

authority to make determinations as to the applicability of this credit to specific generation facilities

10

to the extent there is any uncertainty or disagreement.

11

     (8)(9) “Farm” shall be defined in accordance with § 44-27-2, except that all buildings

12

associated with the farm shall be eligible for net-metering credits as long as: (i) The buildings are

13

owned by the same entity operating the farm or persons associated with operating the farm; and (ii)

14

The buildings are on the same farmland as the project on either a tract of land contiguous with, or

15

reasonably proximate to, such farmland or across a public way from such farmland.

16

     (9)(10) “Hospital” means and shall be defined and established as set forth in chapter 17 of

17

title 23.

18

     (10)(11) “Multi-municipal collaborative” means a group of towns and/or cities that enter

19

into an agreement for the purpose of co-owning a renewable-generation facility or entering into a

20

financing arrangement pursuant to subsection (14).

21

     (11)(12) “Municipality” means any Rhode Island town or city, including any agency or

22

instrumentality thereof, with the powers set forth in title 45.

23

     (12)(13) “Net metering” means using electrical energy generated by an eligible net-

24

metering system for the purpose of self-supplying electrical energy and power at the eligible net-

25

metering system site, or with respect to a community remote net-metering system, for the purpose

26

of generating net-metering credits to be applied to the electric bills of the eligible credit recipients

27

associated with the community net-metering system. The amount so generated will thereby offset

28

consumption at the eligible net-metering system site through the netting process established in this

29

chapter, or with respect to a community remote net-metering system, the amounts generated in

30

excess of that amount will result in credits being applied to the eligible credit-recipient accounts

31

associated with the community remote net-metering system.

32

     (13)(14) “Net-metering customer” means a customer of the electric distribution company

33

receiving and being billed for distribution service whose distribution account(s) are being net

34

metered.

 

LC002218 - Page 5 of 21

1

     (14)(15) “Net-metering financing arrangement” means arrangements entered into by a

2

public entity, educational institution, hospital, nonprofit, or multi-municipal collaborative or a

3

commercial and industrial customer with a private entity to facilitate the financing and operation

4

of a net-metering resource, in which the private entity owns and operates an eligible net-metering

5

resource on behalf of a public entity, educational institution, hospital, nonprofit, or multi-municipal

6

collaborative or commercial or industrial customer, where: (i) The eligible net-metering resource

7

is located on property owned or controlled by the public entity, educational institution, hospital, or

8

one of the municipalities, municipality, multi-municipal collaborative or commercial and industrial

9

customer as applicable; and (ii) The production from the eligible net-metering resource and primary

10

compensation paid by the public entity, educational institution, hospital, nonprofit, or multi-

11

municipal collaborative or commercial and industrial customer to the private entity for such

12

production is directly tied to the consumption of electricity occurring at the designated net-metered

13

accounts.

14

     (15)(16) “Nonprofit” means a nonprofit corporation as defined and established through

15

chapter 6 of title 7, and shall include religious organizations that are tax exempt pursuant to 26

16

U.S.C. § 501(d).

17

     (16)(17) “Person” means an individual, firm, corporation, association, partnership, farm,

18

town or city of the state of Rhode Island, multi-municipal collaborative, or the state of Rhode Island

19

or any department of the state government, governmental agency, or public instrumentality of the

20

state.

21

     (18) “Preferred site” means a location for a renewable energy system that has had prior

22

development, including, but not limited to, landfills, gravel pits and quarries, highway and major

23

road median strips, brownfields, superfund sites, parking lots or sites that are designated

24

appropriate for carports, and all rooftops including, but not limited to, residential, commercial,

25

industrial and municipal buildings.

26

     (17)(19) “Project” means a distinct installation of an eligible net-metering system or a

27

community remote net-metering system. An installation will be considered distinct if it is installed

28

in a different location, or at a different time, or involves a different type of renewable energy.

29

Subject to the safe-harbor provisions in § 39-26.4-3(a)(1), new and distinct projects cannot be

30

located on adjoining parcels of land within core forests.

31

     (18)(20) “Public entity” means the federal government, the state of Rhode Island,

32

municipalities, wastewater treatment facilities, public transit agencies, or any water distributing

33

plant or system employed for the distribution of water to the consuming public within this state

34

including the water supply board of the city of Providence.

 

LC002218 - Page 6 of 21

1

     (19)(21) “Renewable net-metering credit” means a credit that applies to an eligible net-

2

metering system or a community remote net-metering system up to one hundred percent (100%) of

3

either the renewable self-generator’s usage at the eligible net-metering system site or the sum of

4

the usage of the eligible credit-recipient accounts associated with the community remote net-

5

metering system over the applicable billing period. This credit shall be equal to the total kilowatt

6

hours of electrical energy generated up to the amount consumed on-site, and/or generated up to the

7

sum of the eligible credit-recipient account usage during the billing period multiplied by the sum

8

of the distribution company’s:

9

     (i) Standard-offer service kilowatt-hour charge for the rate class applicable to the net-

10

metering customer, except that for remote public entity and multi-municipality collaborative net-

11

metering systems that submit an application for an interconnection study on or after July 1, 2017,

12

and community remote net-metering systems, the standard-offer service kilowatt-hour charge shall

13

be net of the renewable energy standard charge or credit;

14

     (ii) Distribution kilowatt-hour charge;

15

     (iii) Transmission kilowatt-hour charge; and

16

     (iv) Transition kilowatt-hour charge.

17

     Notwithstanding the foregoing, except for systems that have requested an interconnection

18

study for which payment has been received by the distribution company, or if an interconnection

19

study is not required, a completed and paid interconnection application, by December 31, 2018, the

20

renewable net-metering credit for all remote public entity and multi-municipal collaborative net-

21

metering systems shall not include the distribution kilowatt-hour charge commencing on January

22

1, 2050. For commercial and industrial customers, the credit does not include any demand charges

23

included on the customer’s bill.

24

     (20)(22) “Renewable self-generator” means an electric distribution service customer of

25

record for the eligible net-metering system or community remote net-metering system at the eligible

26

net-metering system site which system is primarily designed to produce electrical energy for

27

consumption by that same customer at its distribution service account(s), and/or, with respect to

28

community remote net-metering systems, electrical energy which generates net-metering credits to

29

be applied to offset the eligible credit-recipient account usage.

30

     (21)(23) “Third party” means and includes any person or entity, other than the renewable

31

self-generator, who or that owns or operates the eligible net-metering system or community remote

32

net-metering system on the eligible net-metering system site for the benefit of the renewable self-

33

generator.

34

     (22)(24) “Third-party, net-metering financing arrangement” means the financing of

 

LC002218 - Page 7 of 21

1

eligible net-metering systems or community remote net-metering systems through lease

2

arrangements or power/credit purchase agreements between a third party and renewable self-

3

generator, except for those entities under a public entity net-metering financing arrangement. A

4

third party engaged in providing financing arrangements related to such net-metering systems with

5

a public or private entity is not a public utility as defined in § 39-1-2.

6

     39-26.4-3. Net metering.

7

     (a) The following policies regarding net metering of electricity from eligible net-metering

8

systems and community remote net-metering systems and regarding any person that is a renewable

9

self-generator shall apply:

10

     (1)(i) The maximum allowable capacity for eligible net-metering systems, based on

11

nameplate capacity, shall be ten megawatts (10 MW), effective sixty (60) days after passage.

12

Eligible net-metering systems shall be sited outside of core forests with the exception of

13

development on preferred sites in the core forest and the exception of systems that have requested

14

an interconnection study for which payment has been received by the distribution company, or if

15

an interconnection study is not required, a completed and paid interconnection application by the

16

effective date of this section. For systems developed in core forests on preferred sites, no more than

17

one hundred thousand square feet (100,000 sq. ft) of core forest shall be removed, except for work

18

required for utility interconnection or development of a brownfield, in which case no more core

19

forest than necessary for interconnection or brownfield development shall be removed. For projects

20

outside of core forests, there is no cap on system size. The aggregate amount of net metering in the

21

Block Island Utility District doing business as Block Island Power Company and the Pascoag

22

Utility District shall not exceed a maximum percentage of peak load for each utility district as set

23

by the utility district based on its operational characteristics, subject to commission approval; and

24

     (ii) Through December 31, 2018, the maximum aggregate amount of community remote

25

net-metering systems built shall be thirty megawatts (30 MW). Any of the unused MW amount

26

after December 31, 2018, shall remain available to community remote net-metering systems until

27

the MW aggregate amount is interconnected. After December 31, 2018, the commission may

28

expand or modify the aggregate amount after a public hearing upon petition by the office of energy

29

resources. The commission shall determine within six (6) months of such petition being docketed

30

by the commission whether the benefits of the proposed expansion exceed the cost. This aggregate

31

amount shall not apply to any net-metering financing arrangement involving public entity facilities,

32

multi-municipal collaborative facilities, educational institutions, the federal government, hospitals,

33

or nonprofits or a commercial and industrial customer. By June 30, 2018, the commission shall

34

conduct a study examining the cost and benefit to all customers of the inclusion of the distribution

 

LC002218 - Page 8 of 21

1

charge as a part of the net-metering calculation; and

2

     (iii) The maximum aggregate of net-metering allowable for eligible net-metering systems,

3

as defined by § 39-26.4-2, with the exception of systems that have requested an interconnection

4

study for which payment has been received by the distribution company, or if an interconnection

5

study is not required, a completed and paid interconnection application by effective date of this

6

section, shall be five hundred fifty megawatts, alternating current (550 MWAC), excluding off-

7

shore wind. None of the systems to which this cap applies shall be in core forests unless on a

8

preferred site located within the core forest.

9

     (2) For ease of administering net-metered accounts and stabilizing net-metered account

10

bills, the electric distribution company may elect (but is not required) to estimate for any twelve-

11

month (12) period:

12

     (i) The production from the eligible net-metering system or community remote net-

13

metering system; and

14

     (ii) Aggregate consumption of the net-metered accounts at the eligible net-metering system

15

site or the sum of the consumption of the eligible credit-recipient accounts associated with the

16

community remote net-metering system, and establish a monthly billing plan that reflects the

17

expected credits that would be applied to the net-metered accounts over twelve (12) months. The

18

billing plan would be designed to even out monthly billings over twelve (12) months, regardless of

19

actual production and usage. If such election is made by the electric distribution company, the

20

electric distribution company would reconcile payments and credits under the billing plan to actual

21

production and consumption at the end of the twelve-month (12) period and apply any credits or

22

charges to the net-metered accounts for any positive or negative difference, as applicable. Should

23

there be a material change in circumstances at the eligible net-metering system site or associated

24

accounts during the twelve-month (12) period, the estimates and credits may be adjusted by the

25

electric distribution company during the reconciliation period. The electric distribution company

26

also may elect (but is not required) to issue checks to any net-metering customer in lieu of billing

27

credits or carry-forward credits or charges to the next billing period. For residential-eligible net-

28

metering systems and community remote net-metering systems twenty-five kilowatts (25 KW) or

29

smaller, the electric distribution company, at its option, may administer renewable net-metering

30

credits month to month allowing unused credits to carry forward into the following billing period.

31

     (3) If the electricity generated by an eligible net-metering system or community remote

32

net-metering system during a billing period is equal to, or less than, the net-metering customer’s

33

usage at the eligible net-metering system site or the sum of the usage of the eligible credit-recipient

34

accounts associated with the community remote net-metering system during the billing period, the

 

LC002218 - Page 9 of 21

1

customer shall receive renewable net-metering credits, that shall be applied to offset the net-

2

metering customer’s usage on accounts at the eligible net-metering system site, or shall be used to

3

credit the eligible credit-recipient’s electric account.

4

     (4) If the electricity generated by an eligible net-metering system or community remote

5

net-metering system during a billing period is greater than the net-metering customer’s usage on

6

accounts at the eligible net-metering system site or the sum of the usage of the eligible credit-

7

recipient accounts associated with the community remote net-metering system during the billing

8

period, the customer shall be paid by excess renewable net-metering credits for the excess

9

electricity generated up to an additional twenty-five percent (25%) beyond the net-metering

10

customer’s usage at the eligible net-metering system site, or the sum of the usage of the eligible

11

credit-recipient accounts associated with the community remote net-metering system during the

12

billing period; unless the electric distribution company and net-metering customer have agreed to

13

a billing plan pursuant to subsection (a)(2).

14

     (5) The rates applicable to any net-metered account shall be the same as those that apply

15

to the rate classification that would be applicable to such account in the absence of net metering,

16

including customer and demand charges, and no other charges may be imposed to offset net-

17

metering credits.

18

     (b) The commission shall exempt electric distribution company customer accounts

19

associated with an eligible net-metering system from back-up or standby rates commensurate with

20

the size of the eligible net-metering system, provided that any revenue shortfall caused by any such

21

exemption shall be fully recovered by the electric distribution company through rates.

22

     (c) Any prudent and reasonable costs incurred by the electric distribution company

23

pursuant to achieving compliance with subsection (a) and the annual amount of any renewable net-

24

metering credits or excess renewable net-metering credits provided to accounts associated with

25

eligible net-metering systems or community remote net-metering systems, shall be aggregated by

26

the distribution company and billed to all distribution customers on an annual basis through a

27

uniform, per-kilowatt-hour (KWh) surcharge embedded in the distribution component of the rates

28

reflected on customer bills.

29

     (d) The billing process set out in this section shall be applicable to electric distribution

30

companies thirty (30) days after the enactment of this chapter.

31

     SECTION 2. Sections 39-26.6-1, 39-26.6-3, 39-26.6-5, 39-26.6-12 and 39-26.6-22 of the

32

General Laws in Chapter 39-26.6 entitled "The Renewable Energy Growth Program" are hereby

33

amended to read as follows:

34

     39-26.6-1. Purpose.

 

LC002218 - Page 10 of 21

1

     The purpose of this chapter is to facilitate and promote installation of grid-connected

2

generation of renewable energy; support and encourage development of distributed renewable

3

energy generation systems; reduce environmental impacts; reduce carbon emissions that contribute

4

to climate change by encouraging the siting of renewable energy projects in the load zone of the

5

electric distribution company; diversify the energy-generation sources within the load zone of the

6

electric distribution company; stimulate economic development; improve distribution-system

7

resilience and reliability within the load zone of the electric distribution company; and reduce

8

distribution system costs enable the state to meet its climate and resilience goals, including those

9

established in the act on climate. This includes the goals to facilitate and promote installation of

10

grid-connected generation of renewable energy; support and encourage development of distributed

11

renewable energy generation systems while protecting important core forest areas essential to

12

climate resilience and complying with Rhode Island’s climate change mandates; reduce

13

environmental impacts; reduce carbon emissions that contribute to climate change by encouraging

14

the siting of renewable energy projects in the load zone of the electric distribution company and in

15

preferred areas that have already been disturbed by industry or other uses; diversify the energy-

16

generation sources within the load zone of the electric distribution company; stimulate economic

17

development; and improve distribution-system resilience and reliability with the load zone of the

18

electric distribution company.

19

     39-26.6-3. Definitions.

20

     When used in this chapter, the following terms shall have the following meanings:

21

     (1) “Board” shall mean the distributed-generation board as established pursuant to the

22

provisions of § 39-26.2-10 under the title distributed generation standard contract board, but shall

23

also fulfill the responsibilities set forth in this chapter.

24

     (2) “Ceiling price” means the bidding price cap applicable to an enrollment for a given

25

distributed-generation class, that shall be approved annually for each renewable energy class

26

pursuant to the procedure established in this chapter. The ceiling price for each technology should

27

be a price that would allow a private owner to invest in a given project at a reasonable rate of return,

28

based on recently reported and forecast information on the cost of capital and the cost of generation

29

equipment. The calculation of the reasonable rate of return for a project shall include, where

30

applicable, any state or federal incentives, including, but not limited to, tax incentives.

31

     (3) “Commercial-scale solar project” means a solar distributed-generation project with the

32

nameplate capacity specified in § 39-26.6-7.

33

     (4) “Commission” means the Rhode Island public utilities commission.

34

     (5) “Community remote distributed-generation system” means a distributed-generation

 

LC002218 - Page 11 of 21

1

facility greater than two hundred fifty kilowatt (250 KW) nameplate direct current that allocates

2

bill credits for each kilowatt hour (KWh) generated to a minimum of three (3), eligible recipient-

3

customer accounts, provided that no more than fifty percent (50%) of the credits produced by the

4

system are allocated to one eligible recipient-customer account, and provided further that at least

5

fifty percent (50%) of the credits produced by the system are allocated to eligible recipients in an

6

amount not to exceed that which is produced annually by twenty-five kilowatt (25 KW) AC

7

capacity. The community remote distributed-generation system may transfer credits to eligible

8

recipient-customer accounts in an amount that is equal to, or less than, the sum of the usage of the

9

eligible recipient-customer accounts measured by the three-year-average (3) annual consumption

10

of energy over the previous three (3) years. A projected, annual consumption of energy may be

11

used until the actual three-year-average (3) annual consumption of energy over the previous three

12

(3) years at the eligible recipient-customer accounts becomes available for use in determining

13

eligibility of the generating system. The community remote distributed-generation system may be

14

owned by the same entity that is the customer of record on the net-metered account or may be

15

owned by a third party.

16

     (6) “Core forest” refers to unfragmented forest blocks of single or multiple parcels totaling

17

two hundred fifty (250) acres or greater unbroken by development and at least twenty-five (25)

18

acres from mapped roads, with eligibility questions to be resolved by the director of the department

19

of environmental management. Such determination shall constitute a contested case as defined in

20

§ 42-35-1. Notwithstanding any other provisions of this chapter, no renewable-distributed-

21

generation project that is located or planned to be located in or on a core forest, shall be considered

22

an eligible renewable-distributed-generation project or otherwise be eligible to participate in this

23

program, unless it is on a preferred site.

24

     (6)(7) “Distributed-generation facility” means an electrical-generation facility located in

25

the electric distribution company’s load zone with a nameplate capacity no greater than five

26

megawatts (5 MW), using eligible renewable energy resources as defined by § 39-26-5, including

27

biogas created as a result of anaerobic digestion, but, specifically excluding all other listed eligible

28

biomass fuels, and connected to an electrical power system owned, controlled, or operated by the

29

electric distribution company. For purposes of this chapter, a distributed-generation facility must

30

be a new resource that:

31

     (i) Has not begun operation;

32

     (ii) Is not under construction, but excluding preparatory site work that is less than twenty-

33

five percent (25%) of the estimated total project cost; and

34

     (iii) Except for small-scale solar projects, does not have in place investment or lending

 

LC002218 - Page 12 of 21

1

agreements necessary to finance the construction of the facility prior to the submittal of an

2

application or bid for which the payment of performance-based incentives is sought under this

3

chapter except to the extent that such financing agreements are conditioned upon the project owner

4

being awarded performance-based incentives under the provisions of this chapter. For purposes of

5

this definition, preexisting hydro generation shall be exempt from the provisions of subsection

6

(6)(i) regarding operation, if the hydro-generation facility will need a material investment to restore

7

or maintain reliable and efficient operation and meet all regulatory, environmental, or operational

8

requirements. For purposes of this provision, “material investment” shall mean investment

9

necessary to allow the project to qualify as a new, renewable energy resource under § 39-26-2. To

10

be eligible for this exemption, the hydro-project developer at the time of submitting a bid in the

11

applicable procurement must provide reasonable evidence with its bid application showing the level

12

of investment needed, along with any other facts that support a finding that the investment is

13

material, the determination of which shall be a part of the bid review process set forth in § 39-26.6-

14

16 for the award of bids.

15

     (7)(8) “Distributed-generation project” means a distinct installation of a distributed-

16

generation facility. An installation will be considered distinct if it does not violate the segmentation

17

prohibition set forth in § 39-26.6-9.

18

     (8)(9) “Electric distribution company” means a company defined in § 39-1-2(a)(12),

19

supplying standard-offer service, last-resort service, or any successor service to end-use customers,

20

but not including the Block Island Power Company or the Pascoag Utility District.

21

     (9)(10) “ISO-NE” means Independent System Operator-New England, the Regional

22

Transmission Organization for New England designated by the Federal Energy Regulatory

23

Commission.

24

     (10)(11) “Large distributed-generation project” means a distributed-generation project that

25

has a nameplate capacity that exceeds the size of a small distributed-generation project in a given

26

year, but is no greater than five megawatts (5 MW) nameplate capacity.

27

     (11)(12) “Large-scale solar project” means a solar distributed-generation project with the

28

nameplate capacity specified in § 39-26.6-7.

29

     (12)(13) “Medium-scale solar project” means a solar distributed-generation project with

30

the nameplate capacity specified in § 39-26.6-7.

31

     (13)(14) “Office” means the Rhode Island office of energy resources.

32

     (15) “Preferred sites” means a location for a renewable energy system that has had prior

33

development, including, but not limited to, landfills, gravel pits and quarries, highway and major

34

road median strips, brownfields, superfund sites, parking lots or sites that are designated

 

LC002218 - Page 13 of 21

1

appropriate for carports, and all rooftops including, but not limited to, residential, commercial,

2

industrial and municipal buildings.

3

     (14)(16) “Program year” means a year beginning April 1 and ending March 31, except for

4

the first program year, that may commence after April 1, 2015, subject to commission approval.

5

     (15)(17) “Renewable energy certificate” means a New England Generation Information

6

System renewable energy certificate as defined in § 39-26-2(14).

7

     (16)(18) “Renewable energy classes” means categories for different renewable energy

8

technologies using eligible renewable energy resources as defined by § 39-26-5, including biogas

9

created as a result of anaerobic digestion, but, specifically excluding all other listed eligible biomass

10

fuels specified in § 39-26-2(6). For each program year, in addition to the classes of solar distributed

11

generation specified in § 39-26.6-7, the board shall determine the renewable energy classes as are

12

reasonably feasible for use in meeting distributed-generation objectives from renewable energy

13

resources and are consistent with the goal of meeting the annual target for the program year. The

14

board may make recommendations to the commission to add, eliminate, or adjust renewable energy

15

classes for each program year, provided that the solar classifications set forth in § 39-26.6-7 shall

16

remain in effect for at least the first two (2) program years and no distributed-generation project

17

may exceed five megawatts (5 MW) of nameplate capacity.

18

     (17)(19) “Shared solar facility” means a single small-scale or medium-scale solar facility

19

that must allocate bill credits to at least two (2), and no more than fifty (50), accounts in the same

20

customer class and on the same or adjacent parcels of land. Public entities may allocate such bill

21

credits to at least two (2), and up to fifty (50), accounts without regard to physical location so long

22

as the facility and accounts are within the same municipality. In no case will the annual allocated

23

credits in KWh exceed the prior three-year (3) annual average usage, less any reductions for verified

24

energy-efficiency measures installed at the customer premises, of the customer account to which

25

the bill credits are transferred.

26

     (18)(20) “Small distributed-generation project” means a distributed-generation renewable

27

energy project that has a nameplate capacity within the following: Wind: fifty kilowatts (50 KW)

28

to one and one-half megawatts (1.5 MW); small-scale solar projects and medium-scale solar

29

projects with the capacity limits as specified in § 39-26.6-7. For technologies other than solar and

30

wind, the board shall set the nameplate capacity-size limits, but such limits may not exceed one

31

megawatt (1 MW).

32

     (19)(21) “Small-scale solar project” means a solar distributed-generation project with the

33

nameplate capacity specified in § 39-26.6-7.

34

     39-26.6-5. Tariffs proposed and approved.

 

LC002218 - Page 14 of 21

1

     (a) Each year, for a period of at least five (5) program years, the electric distribution

2

company shall file tariffs with the commission that are designed to provide a multiyear stream of

3

performance-based incentives to eligible renewable-distributed-generation projects for a term of

4

years, under terms and conditions set forth in the tariffs and approved by the commission. The

5

tariffs shall set forth the rights and obligations of the owner of the distributed-generation project

6

and the conditions upon which payment of performance-based incentives by the electric

7

distribution company will be paid. The tariffs shall include the non-price conditions set forth in §§

8

39-26.2-7(2)(i) — (vii) for small distributed-generation projects (other than small- and medium-

9

scale solar) and large distributed-generation projects; provided, however, that the time periods for

10

the projects to reach ninety percent (90%) of output shall be extended to twenty-four (24) months

11

(other than eligible anaerobic-digestion projects, which shall be thirty-six (36) months, and eligible

12

small-scale hydro, which shall be forty-eight (48) months). The non-price conditions in the tariffs

13

for small- and medium-scale solar shall take into account the different circumstances for

14

distributed-generation projects of the smaller sizes.

15

     (b) In addition to the tariff(s), the filing shall include the rules governing the solicitation

16

and enrollment process. The solicitation rules will be designed to ensure the orderly functioning of

17

the distributed-generation growth program and shall be consistent with the legislative purposes of

18

this chapter.

19

     (c) In proposing the tariff(s) and solicitation rules applicable to each year, the tariff(s) and

20

rules shall be developed by the electric distribution company and will be reviewed by the office

21

and the board before being sent to the commission for its approval. The proposed tariffs shall

22

include the ceiling prices and term lengths for each tariff that are recommended by the board. The

23

term lengths shall be from fifteen (15) to twenty (20) years; provided, however, that the board may

24

recommend shorter terms for small-scale solar projects. Whatever term lengths between fifteen

25

(15) and twenty (20) years are chosen for any given tariff, the evaluation of the bids for that tariff

26

shall be done on a consistent basis such that the same term lengths for competing bids are used to

27

determine the winning bids.

28

     (d) The board shall use the same standards for setting ceiling prices as set forth in § 39-

29

26.2-5. In setting the ceiling prices, the board may specifically consider:

30

     (1) Transactions for newly developed renewable energy resources, by technology and size,

31

in the ISO-NE control area and the northeast corridor;

32

     (2) Pricing from bids received during the previous program year;

33

     (3) Environmental benefits, including, but not limited to, reducing carbon emissions;

34

     (4) For community remote distributed-generation systems, administrative costs and

 

LC002218 - Page 15 of 21

1

financial benefits for participating customers;

2

     (5) System benefits; and

3

     (6) Cost-effectiveness: and

4

     (7) Location of projects, including climate resilience and conservation benefits; and

5

     (8) Labor and standards to promote fair labor standards, support local jobs and prioritize

6

hiring and training for workers affected by the transition to renewable energy, under-represented

7

in the work force, of facing employment barriers, including women, people of color, veterans,

8

formerly incarcerated individuals, and people with disabilities.

9

     (e) At least forty-five (45) days before filing the tariff(s) and solicitation rules, the electric

10

distribution company shall provide the tariff(s) and rules in draft form to the board for review. The

11

commission shall have the authority to determine the final terms and conditions in the tariff and

12

rules. Once approved, the commission shall retain exclusive jurisdiction over the performance-

13

based incentive payments, terms, conditions, rights, enforcement, and implementation of the tariffs

14

and rules, subject to appeals pursuant to chapter 5 of this title.

15

     39-26.6-12. Annual bidding and enrollments.

16

     (a) With the exception of the first program year (2015), the electric distribution company,

17

in consultation with the board and office, shall conduct at least three (3) tariff enrollments for each

18

distributed-generation class each program year. For the first program year, the board may

19

recommend that either two (2) or three (3) enrollments be conducted.

20

     (b) During each program year, the tariff enrollments shall have both an annual targeted

21

amount of nameplate megawatts (“annual MW target”) and a nameplate megawatt target for each

22

separate enrollment event (“enrollment MW target”). The enrollment MW target shall comprise the

23

specific portion of the annual MW target sought to be obtained in that enrollment. The enrollment

24

MW targets shall be recommended by the board each year, subject to commission approval. The

25

board shall also recommend a megawatt target for each class (“class MW target”) that comprises a

26

specified portion of the enrollment MW target, subject to commission approval. If the electric

27

distribution company, the office, and the board mutually agree, they may reallocate megawatts

28

during an enrollment from one class to another without commission approval if there is an over-

29

subscription in one class and an under-subscription in another, provided that the annual MW target

30

is not being exceeded, except as provided in § 39-26.6-7.

31

     (c) The annual MW targets shall be established as follows; provided, however, that at least

32

three megawatts (3 MW) of nameplate capacity shall be carved out exclusively for small-scale solar

33

projects in each of the first four (4) program years:

34

     (1) For the first program year (2015), the annual MW target shall be twenty-five nameplate

 

LC002218 - Page 16 of 21

1

megawatts (25 MW);

2

     (2) For the second program year, the annual targets shall be forty nameplate megawatts (40

3

MW);

4

     (3) For the third and fourth program years, the annual target shall be forty nameplate

5

megawatts (40 MW), subject to the conditions set forth in subsection (f) of this section having been

6

met for the applicable prior program year as determined in the manner specified in subsection (g)

7

of this section;

8

     (4) For the fifth program year, the annual target shall be set to obtain the balance of capacity

9

needed to achieve one hundred sixty nameplate megawatts (160 MW) within the five-year (5)

10

distributed-generation growth program, subject to subsection (e) of this section and the conditions

11

set forth in subsection (f) of this section having been met for the fourth program year as determined

12

in the manner specified in subsection (g) of this section; and

13

     (5) From the year 2020 through the year 2029, the annual target for each program year shall

14

be an additional forty nameplate megawatts (40 MW) above the annual target for the preceding all

15

projects that bid in under the relevant ceiling price are eligible, with a target of up to three hundred

16

megawatts (300 MW) for each program year.

17

     (d) During the fifth year of the distributed-generation growth program, the board may

18

recommend to the commission an extension of time in the event that additional time is required to

19

achieve the full one hundred sixty nameplate megawatt (160 MW) target of the program. The

20

commission shall approve the recommendation of the board; provided, however, that the

21

commission may make any modifications to the board’s recommendation that the commission

22

deems appropriate, consistent with the legislative purposes of this chapter as set forth herein.

23

     (e) To the extent there was a shortfall of capacity procured under chapter 26.2 of this title

24

from distributed-generation procurements in 2014, such shortfall amount may be added to the one

25

hundred sixty megawatt (160 MW) target for acquisition in the fifth program year under this

26

chapter. In no event shall the electric distribution company be required to exceed the aggregate

27

amount of one hundred sixty (160) nameplate capacity plus any such shortfall amount over the five

28

(5) years, but may do so voluntarily, in consultation with the board and subject to commission

29

approval.

30

     (f) The conditions specified in subsections (c)(3) and (c)(4) of this section are as follows:

31

(1) That it is reasonable to conclude that the bid prices submitted in the procurements for the large-

32

scale solar and commercial-scale solar classes were reasonably competitive in the immediately

33

preceding program year; (2) That it is reasonable to conclude that the annual MW target specified

34

for the next program year is reasonably achievable; and (3) That the electric distribution company

 

LC002218 - Page 17 of 21

1

was able to, or with reasonably prudent efforts should have been able to, perform the studies and

2

system upgrades on a timely basis necessary to accommodate the number of applications associated

3

with the targets without materially adversely affecting other electric-distribution construction

4

projects needed to provide reliable and safe electric-distribution service. To the extent the board or

5

the commission concludes that any of these conditions have not been met for the applicable

6

program year, the board may recommend, and/or the commission may adopt, a new annual MW

7

target, based on the factors set forth in subsection (h) of this section.

8

     (g) Before the third, fourth, and fifth program years, each year the board shall review the

9

conditions specified in subsection (f) of this section and make a recommendation to the commission

10

for findings as to whether they have been met for the applicable year. The recommendation shall

11

be filed with the commission, with copies to the office and the electric distribution company, and

12

any person who has made a written request to the commission to be included in such notification,

13

such list which may be obtained from the commission clerk, and a notice of such filing shall be

14

posted by the commission on its website. If no party files an objection to the recommended findings

15

within ten (10) business days of the posting, the commission may accept them without hearings. If

16

an objection is filed with a reasonable explanation for its basis, the commission shall hold hearings

17

and make the factual determination of whether the conditions have been met.

18

     (h) In the event that the conditions in subsection (f) of this section have not been met for

19

any program year, then the board and the commission shall take into account the factors set forth

20

below in setting the annual MW target for the following year. In addition, for every program year

21

the board and the commission shall take into account these factors in setting the class MW targets,

22

and the enrollment MW targets for the following year: (1) That the new annual, class, and

23

enrollment levels reasonably assure that competition among projects for the applicable bidding

24

classifications remains robust and likely to yield reasonable and competitive program costs; (2)

25

That, assuming prudent management of the program, the electric distribution company should be

26

able to perform the studies and system upgrades on a timely basis necessary to accommodate the

27

number of applications associated with the targets without materially adversely affecting other

28

electric-distribution construction projects needed to provide reliable and safe electric-distribution

29

service; and (3) Any other reasonable factors that are consistent with the legislative purpose of this

30

chapter as set forth herein, including the program purpose to facilitate the development of

31

renewable distributed generation in the load zone of the electric distribution company at reasonable

32

cost.

33

     (i) The renewable energy growth program is intended to achieve at least an aggregate

34

amount of one hundred sixty nameplate megawatts (160 MW) over five (5) years, plus any shortfall

 

LC002218 - Page 18 of 21

1

amount added in pursuant to subsection (e) of this section. However, after the second program year,

2

the board may, based on market data and other information available to it, including pricing

3

received during previous program years, recommend changes to the annual target for any program

4

year above or below the specified targets in subsection (c) of this section if the board concludes

5

that market conditions are likely to produce favorably low or unfavorably high target pricing during

6

the upcoming program year, provided that the recommendation may not result in the five-year (5),

7

one-hundred-sixty-megawatt-nameplate (160 MW) target, plus any shortfall added pursuant to

8

subsection (e) of this section, being exceeded. Any megawatt reduction in an annual target shall be

9

added to the target in the fifth year of the program (and any subsequent years if necessary) such

10

that the overall program target of one-hundred-sixty-megawatt-nameplate (160 MW) capacity, plus

11

any shortfall added pursuant to subsection (e) of this section, is achieved. In considering these

12

issues, the board and the commission may take into account the reasonableness of current pricing

13

and its impact on all electric distribution customers and the legislative purpose of this chapter as

14

set forth herein, including the program purpose to facilitate the development of renewable

15

distributed generation in the load zone of the electric distribution company at reasonable cost.

16

     (j) The provisions of § 39-26.1-4 shall apply to the annual value of performance-based

17

incentives (actual payments plus the value of net-metering credits, as applicable) provided by the

18

electric distribution company to all the distributed-generation projects under this chapter, subject

19

to the following conditions:

20

     (1) The targets set for the applicable program year for the applicable project classifications

21

were met or, if not met, such failure was due to factors beyond the reasonable control of the electric

22

distribution company;

23

     (2) The electric distribution company has processed applications for service and completed

24

interconnections in a timely and prudent manner for the projects under this chapter, taking into

25

account factors within the electric distribution company’s reasonable control. The commission is

26

authorized to establish more specific performance standards to implement the provisions of this

27

chapter; and

28

     (3) The incentive shall be one and three-quarters percent (1.75%) of the annual value of

29

performance-based incentives. The commission is authorized to establish more specific

30

performance standards to implement the provisions of this paragraph.

31

     39-26.6-22. Zonal and other incentive payments.

32

     In order to provide the electric distribution company and the board with the flexibility to

33

encourage distributed-generation projects to be located in designated geographical areas within its

34

load zone where there is an identifiable system benefit, reliability benefit, or cost savings to the

 

LC002218 - Page 19 of 21

1

distribution system in that geographical area, the electric distribution company, in consultation with

2

the board and the office, may propose to include an incentive-payment adder to the bid price of any

3

winning bidder that proposes a distributed-generation project in the desired geographical area.

4

conservation benefit, or climate resilience benefit in that geographical area, the electric distribution

5

company, the board or the office, shall propose to include an incentive-payment adder to the bid

6

price of any winning bidder that proposes a distributed-generation project in the preferred sites that

7

require remediation. The company, board, or office can also propose disincentive subtractors for

8

projects outside of preferred areas. The electric distribution company also may propose other

9

incentive payments to achieve other technical or public policy objectives that provide identifiable

10

benefits to customers. Any incentive-payment adders must be approved by the commission, and

11

shall not be counted as part of the bid price when the bids are selected at an enrollment event.

12

     SECTION 3. This act shall take effect upon passage.

========

LC002218

========

 

LC002218 - Page 20 of 21

EXPLANATION

BY THE LEGISLATIVE COUNCIL

OF

A N   A C T

RELATING TO PUBLIC UTILITIES AND CARRIES -- NET METERING

***

1

     This act would define core forest and preferred sites and would provide that any net-

2

metering resource owned or operated by a renewable energy developer be treated as an eligible net-

3

metering system provided it is not in a core forest.

4

     This act would take effect upon passage.

========

LC002218

========

 