1 | WHEREAS, Revolution Wind, the “Project”, is a planned 880 megawatt offshore wind |
2 | farm to be constructed and operated by Revolution Wind, LLC, encompassing over 3,600 acres, |
3 | and located approximately 15 miles south of the Rhode Island coast with a plan for up to 79 |
4 | offshore wind turbine generators that will provide Rhode Island with 400 megawatts of power; |
5 | and |
6 | WHEREAS, The Coastal Resources Management Council (CRMC) has the responsibility |
7 | of managing the preservation of the State's coastal resources pursuant to Rhode Island General |
8 | Law § 46-23-6; and |
9 | WHEREAS, Pursuant to Rhode Island General Law § 46-23-1, due to the size and scope |
10 | of the Project, any use or license of the State’s submerged lands is subject to approval, |
11 | disapproval, or conditional approval from the General Assembly; and |
12 | WHEREAS, The Rhode Island Constitution Article VI, Section 1 states, “The general |
13 | assembly shall pass all laws necessary to carry the Constitution into effect” and the Rhode Island |
14 | Constitution Article VI, Section 2 states, “The concurrence of the two houses shall be necessary |
15 | to the enactment of laws”; now, therefore be it |
16 | RESOLVED, That this General Assembly of the State of Rhode Island hereby finds that |
17 | following negotiations between CRMC and Revolution Wind, LLC, CRMC issued a finding that |
18 | the Project is consistent with the State policy, as evidenced by that certain RI CRMC Federal |
19 | Consistency Review of the Revolution Wind Project-Staff Decision Recommendation for |
20 | Concurrence, dated April 25, 2023, CRMC File No. 2021-06-029; and be it further |
| |
1 | RESOLVED, That this General Assembly, in accordance with its powers and duties |
2 | under applicable law, shall conduct a review of the terms and conditions of a submerged land |
3 | lease to be executed in connection with the installation, construction, maintenance, operation, |
4 | decommissioning and removal of certain transmission cables relating to the Project, in |
5 | accordance with applicable law and relevant CRMC regulations. |
======== | |
LC003206 | |
======== | |