Chapter 370
2008 -- S 2441
SUBSTITUTE A AS AMENDED
Enacted 07/08/08
A N A C T
RELATING
TO STATE AFFAIRS AND GOVERNMENT -- ENERGY FACILITY SITING
ACT
Introduced
By: Senator Rhoda E. Perry
Date
Introduced: February 13, 2008
It is enacted by the General Assembly as
follows:
SECTION 1. Section
42-98-1.1 of the General Laws in Chapter 42-98 entitled "Energy
Facility Siting Act" is hereby amended to
read as follows:
42-98-1.1.
Capital city underground utility initiative. -- (a) The public
utilities
commission shall permit the city of Providence
or the city of East Providence, upon petition by a
duly authorized representative of such
municipality, to forego some or all of the respective
municipality's pro rata share of the refund
accruing to the ratepayers of the respective
municipality as computed under section 11(c) of
the 3rd Amended Settlement Agreement in
Docket No. 2930; provided, however, that the
city council of each petitioning ratifies such action
by passage of a resolution.
(b) The public
utilities commission shall permit, upon petition by the attorney general,
for the use of up to two million dollars
($2,000,000) from Narragansett Electric Company's Storm
Contingency Fund for purposes of under grounding
that portion of the E-183 transmission line
under consideration in Energy Facility Siting
Board Docket 2003-01.
(c) Narragansett
Electric Company shall be required to apply to the regional grid
operator or its successor organization for
approval to charge New England regional network
service customers for the capital costs
associated with the construction of Phase II overhead
configuration labeled the "North Bridge
Alignment" as defined by the Settlement Agreement that
was approved by the Energy Facility Siting Board
in Docket 2003-1.
(d) The
Narragansett Electric Company ("company") shall be authorized to
proceed with
the construction of the underground alignment of
the E-183 line referenced in the Settlement
Agreement that was approved by the Energy
Facility Siting Board in Docket 2003-01
("Underground alignment"), including
the acquisition of any property rights needed to implement
the underground alignment subject to the passage
of resolutions by both city councils of the cities
of Providence and East Providence agreeing that
any incremental costs above existing funding
may be included in electric rates of electric
customers in those cities. Such resolutions must be
delivered to the public utilities commission no
later than July 1, 2009. Notwithstanding the terms
of the Settlement, to the extent the actual
costs for the underground alignment exceed the funding
obtained for the project pursuant to this
section and from federal and other sources, the company
is authorized to include the incremental costs
above those funding levels in its distribution rate
base and reflect the revenue requirement in
rates to the electric distribution customers within the
cities of Providence and East Providence, subject
to the timely passage and delivery of the
resolution specified above. Such rate adjustment
shall be made within six (6) months from project
completion, applying the same ratemaking
principles as ordinarily applied to distribution capital
projects when they are allowed in its
distribution rate base by the public utilities commission.
After completion of the underground alignment,
the public utilities commission shall conduct a
review of costs incurred to construct the
underground alignment in order to verify that the
company's calculation and implementation of
rates are in compliance with this section; provided,
further, the auditor general shall perform a
performance audit of state costs.
(e) If the
underground alignment goes forward, the company shall retain such portions of
the properties acquired to implement the
underground alignment as may be necessary and
prudent, and shall transfer any remaining
portions of said properties to the redevelopment
authority of the city in which the property is
located after the completion of the project, at the
city's request and at no additional cost to the
city. Any easements no longer being used by the
company for utility purposes after the
underground alignment is completed also shall be
transferred to the city after the completion of
the project, at the city's request and at no additional
cost to the city. If there is any dispute about
the extent to which property or easements are needed
and therefore should not be transferred, the
public utilities commission shall decide the issue
upon petition by the affected city.
SECTION 2. This
act shall take effect upon passage.
=======
LC00233/SUB A
=======